5.2. BASR 09-22-2020 Request for Action
Cir•ci
Elk -
River=
To Item Number
Board of Adjustments 5.2
Agenda Section Meeting Date Prepared by
Public Hearings September 22, 2020 Chris Leeseberg, Senior Planner
Item Description Reviewed by
Elk River Municipal Utilities— 1643 Main St. Chris Leeseber , Senior Planner
NW, Case No.V 20-14 Reviewed by
Impervious Surface Coverage of 65% (allowed
25%)
Action Requested
Approve,by motion,the 65%impervious surfacing variance for the
following reasons:
1. The general purpose and intent of the ordinance are met.
2. The property has a land use of residential and the use is
consistent with the Comprehensive Plan.
3. The proposed use is reasonable and is permitted in the zoning
ordinance. L)
CR 33
4. The plight of the petitioner is due to circumstances unique to
the property not a consequence of the petitioner's own action
or inaction. z
5. The variance will not alter the essential character of the locality. RR
Background/Discussion Hwy 10
This application is part of the Elk River Municipal Utilities (ERMU) -
CR 12
building expansion project. The project will consist of a Zone Change
(ZC 20-03), a Conditional Use Permit (CU 20-19),Preliminary and
Final Plat (P 20-13 &P 20-14), a Variance (V 20-14), and an Easement
Vacation (EV 20-05). The subject site is at the southeast corner of the
intersection of Main St. and Tipton Ave. y
�y
,o
6y
ERMU is requesting a variance of the amount of allowed impervious
surfacing within the Shoreland Management District to construct their
proposed project. Figure i -
Applicable Regulation
(The applicant's responses are italicized with staff's notes after.)
Variances may be granted when the petitioner establishes that the variance satisfies all five of the criteria described
below. The variance is:
1. Is in harmony with the general purpose and intent of the ordinance,and
The Elk River Vision P O N E R E o s Y
A welcoming community avith revolutionary and spirited resourcefulness, exceptional [NAWRE
service, and community engagement that encourages and inspires prosperity. Updated.August 2020
The variance to allow an increased impervious surface is in harmony with the general intent of the ordinance. The city code does
not have a different regulation for impervious surface of a commercial, industrial or public use within the shoreland overlay and
siVyrestnas all sites to 25% impervious coverage. The site exists today with 43% impervious surface and we are
incorporating additional stormwater management methods on the site to account for the additional impervious surface proposed.
Wl'e believe this meets the intent of the ordinance to protect Elk River from additional stormwater and pollution impacts.
While the applicant is asking for 65% of impervious lot coverage, they are implementing stormwater
management methods resulting in no additional discharge from the site than currently exists.
2. Is consistent with the City of Elk River Comprehensive Plan.
The variances are consistent with the City of Elk River Comprehensive Plan because they allow ERMU to expand within the
existing site. ERMU provides all mater service to Elk River, which is a necessity for the community. ERMU has also been
implementing additional measures to conserve water where possible and to reduce environmental concerns, which will be aided
by the expansion.
The subject area has an underlying land use of Mississippi Connections,which is consistent with the R1-c
zoning district and permits Governmental Facilities. The use will be consistent with the Comprehensive
Plan.
Variances may be granted when the petitioner establishes that there are practical difficulties in complying with the
zoning ordinance. Practical difficulties mean that:
3. The petitioner proposes to use the property in a reasonable manner not permitted by the zoning
ordinance;
ire are proposing to continue the existing use of the property as a government facility which is a permitted conditional use for
the R-7c honing district. The proposed variances allow ERMU to expand from the existing structures and make needed
improvements to the site to allow smooth operations and continuedgrowth.
It is reasonable for a company to expand their operations and to implement stormwater management
methods to mitigate any adverse effects of additional impervious surfacing.
4. The plight of the petitioner is due to circumstances unique to the property not a consequence of the
petition's own action or inaction; and
The variance requests are due to the existing buildings and site layout and the code restrictions that have been put in place
since the property was initially developed. This site is unique in that it is restricted by shoreland overlay standards that are
catered towards residential lotsyou typically find near a lake. The combination of these circumstances creates a unique
property.
The allowable hardcover on this site creates significant constraints. The existing structure is already
exceeding hardcover limitations and due to adjacent wetlands and a stormwater pond, there are no
alternative options to achieve the desired goal for expansion.Additionally, critical infrastructure to the
operation of ERMU is located at this site and could not be relocated.
5. The variance,if granted,will not alter the essential character of the locality.
The variances, ifgranted, will not change the essential character of the locality. The ERMU site has existed in this location
for many years and become a part of the locality. These variances will allow the site to be developed around the existing
buildings and to remain with the same character that exists today.
Most of the impervious surfacing (yard area) is screened by building,vegetation, and grade changes. The
essential character will not be altered.
Financial Impact
None
Council Meeting
If denied, or an appeal is made by any interested party by October 2,2020, this item will go to the October 19,
2020, City Council meeting.
Attachments
■ Location Map
■ Site Plan
■ Applicant's Narrative
Narrative
Rezoning, Conditional Use
Permit, Preliminary Plat, Final
Plat, ROW Vacation and Variance
August 31, 2020
PREPARED FOR
Elk River Municipal Utilities
P.O. Box 430
Elk River, MN 55330
PREPARED BY
Landform Professional Services, LLC
105 5th Ave S, Suite 513
Minneapolis, MN 55401
Elk River Municipal Utilities
Landform®, SensiblyGreen® and Site to Finish® are registered service marks of Landform Professional Services, LLC
TABLE OF CONTENTS
Introduction .................................................................................................................................................. 1
Rezoning ........................................................................................................................................................ 1
Conditional Use Permit ................................................................................................................................. 2
Preliminary Plat and Final Plat ...................................................................................................................... 4
Vacation ........................................................................................................................................................ 4
Variance ........................................................................................................................................................ 5
Summary ....................................................................................................................................................... 7
Contact Information ...................................................................................................................................... 7
Elk River Municipal Utilities, Elk River, MN August 31, 2020
ERMU18001 1
Introduction
On behalf of Elk River Municipal Utilities (ERMU), Landform is pleased to submit this application for rezoning,
conditional use permit, preliminary plat, final plat, ROW vacation and variances to allow construction of a new
maintenance facility and associated site improvements at the southeast quadrant of Main Street and Main Street in
Elk River. The site includes several parcels that will be consolidated to create a new 8.47-acre site. The existing
homes will be removed, but the existing power plant and utility building will remain as part of the new maintenance
complex. We are excited about the improvements proposed for this site to better serve the residents and businesses
in Elk River.
Rezoning
Description of Request
We are requesting a rezoning of the following parcels from the R-2a Two Family Residential zoning district to the
R-1c Single Family Residential zoning district.
• 75-411-0120
• 75-411-0230
• 75-411-0210
• 75-411-0240
What is the purpose of the Zone Change?
There are currently two zoning districts present in the parcels that will be combined to create the single large parcel
for ERMU. The purpose of the rezoning is to have a consistent zoning district for the entire ERMU site. We are
requesting the rezoning to R-1c because of the consistency with the surrounding zone districts.
What has changed to warrant the Zone Change?
The change that is occurring to warrant the zoning change is that the existing homes with the proposed zoning
change have been purchased by ERMU and will be demolished to make room for the new maintenance facility. The
proposed work includes combining the existing lots into a single larger parcel and now is the appropriate time to
rezone the existing properties to have a consistent zoning for the entire parcel after combination.
How is the request consistent with the Elk River Comprehensive Plan?
The request is consistent with the Elk River Comprehensive Plan because it meets the goals set out for the
Mississippi Connections land use guidance for the property. The Mississippi Connections area is
encouraged to maintain the public facilities within the guided area and to encourage redevelopment and
continued improvement in the facilities.
How compatible is it with surrounding properties?
Elk River Municipal Utilities, Elk River, MN August 31, 2020
ERMU18001 2
The zoning change is compatible with the surrounding districts. The change to an R-1c zoning district will
make the site have the same zoning as the surrounding area.
What are the benefits to the City?
The City benefits from the zoning change as it is needed to make necessary improvements to the ERMU
site for continued service to the residents and businesses in the Elk River community.
Conditional Use Permit
Description of Request
We are requesting a conditional use permit to allow a government facility in the R-1c zoning district. A government
facility is a permitted conditional use in the R-1c zoning district.
Site Improvements
A new 59,518 sq. ft. building will be constructed on the northwest corner of the site that will have space for office and
vehicle storage. The building exterior will be constructed using precast concrete panels, metal wall panels and face
brick.
The current code requires one parking space per 300 sq. ft. of building space. With the existing buildings and new
building there will be a total of 72,724 sq. ft. of building area on the site. This would require 243 parking stalls to be
provided on the site. A variance request from this requirement is being requested to allow the site to provide 45
parking stalls. Further detail regarding the variance request is included below.
A single monument sign is being proposed to identify the site. The sign location has yet to be determined but a sign
permit will be applied for prior to installation and will comply with setback, size and height requirements.
The new building being constructed on the site will operate during the same hours of operation as the current
facilities from 8 a.m. to 4:30 p.m. ERMU currently employs 30 people at this location and the new building will provide
space for identified future positions to be filled.
An additional 75 trees will be added to the site to partially screen the parking and building from the adjacent
roadways. In addition, the vehicle operations are to the rear of the site screened by the building.
Standards for Issuance
We have reviewed the request in accordance with City ordinance standards in Section 30-654 and find that the
ordinance standards have been met. Specifically:
1. Will not endanger, injure or detrimentally affect the use and enjoyment of other property in the immediate
vicinity or the public health, safety, morals, comfort, convenience or general welfare of the neighborhood or
the city.
Elk River Municipal Utilities, Elk River, MN August 31, 2020
ERMU18001 3
The conditional use to allow a government facility will not affect the properties located in the immediate
vicinity or the nearby neighborhood. The ERMU facility has been located on the site for many years and the
use is only being updated and expanded to serve the community.
2. Will be consistent with the comprehensive plan.
The proposed use is consistent with the comprehensive plan which encourages investment and
improvement in businesses to aid in job growth. ERMU is a government facility that provides a necessary
service to the residents of Elk River and is consistent with the comprehensive plan which encourages
existing public facilities to expand as needed to serve the community.
3. Will not impede the normal and orderly development and improvement of surrounding vacant property.
The expanded development of the ERMU site will not impede adjacent properties from developing or
improving their properties.
4. Will be served adequately by and will not adversely affect essential public facilities and services including
streets, police and fire protection, drainage, refuse disposal, water and sewer systems, parks and schools;
and will not, in particular, create traffic congestion or interference with traffic on adjacent and neighboring
public thoroughfares.
The improvements to the ERMU facility will not adversely impact the public facilities and service including
streets, police, fire, utilities, parks, schools or traffic.
5. Will not involve uses, activities, processes, materials, equipment and conditions of operation that will be
detrimental to any persons or property because of excessive traffic, noise, smoke, fumes, glare, odors, dust
or vibrations.
The proposed government facility use will not cause excessive traffic, noise, smoke, fumes, glare, odors,
dust or vibrations that would impact other properties.
6. Will not result in the destruction, loss or damage of a natural, scenic or historic feature of major importance.
The proposed improvements to the ERMU site include keeping the existing power plant and maintaining the
area adjacent to Elk River.
7. Will fully comply with all other requirements of this Code, including any applicable requirements and
standards for the issuance of a license or permit to establish and operate the proposed use in the city.
The use will comply with all the requirements of the city code with the exception of the variances associated
with this application as identified below.
Elk River Municipal Utilities, Elk River, MN August 31, 2020
ERMU18001 4
Preliminary Plat and Final Plat
Description of Request
We are requesting a preliminary and final plat to combine the following parcels into a single lot for ERMU:
• 75-411-0110 (1705 Main Street)
• 75-411-0130 (No Address)
• 75-411-0120 (1643 Main Street)
• 75-411-0230 (No Address)
• 75-411-0210 (1639 Main Street)
• 75-411-0240 (1627 Main Street)
• 75-411-0220 (No Address)
• 75-411-0250 (1437 Main Street)
The preliminary and final plat will combine the eight existing lots into a single lot to allow for the new building and
associated site improvements to be constructed to serve ERMU.
Vacation
Description of Request
We are requesting vacation of 4th (Depot) Street, which is an unimproved public right-of-way that extends northeast
from Main Street north of Lot 6, Block 1 Auditor’s Addition to the Village of Elk River to Main Street on the north and
east of Lot 8, Block 2, Auditor’s Addition to the Village of Elk River. The right-of-way is not adjacent to public waters.
In order to maintain access to the property at 1433 Main Street NW, we are not requesting vacation for the triangular
portion lying east of the east line of parcel 75-411-0130 (extended) as shown on the attached graphics.
What is the purpose of the Vacation?
The purpose of the vacation is to allow redevelopment of the site as the Elk River Municipal Utilities maintenance
facility. The existing power plant buildings will remain and the two homes on the north portion of the site will be
demolished.
How is the request consistent with the City of Elk River Comprehensive Plan?
The request would allow development of a new Elk River Municipal Utilities maintenance facility, which will help
provide reliable service to Elk River residents is consistent with Comprehensive Plan. Specifically:
1. It is consistent with the vision statement themes to provide “well maintained and reliable infrastructure” and
“As an Energy City, Elk River seeks to promote sustainable and energy efficient forms of development.”
Elk River Municipal Utilities, Elk River, MN August 31, 2020
ERMU18001 5
2. The Transportation Chapter does not anticipate construction of a new street in this location. Therefore,
vacation of the street would not be inconsistent with the plan.
3. The Utilities Chapter of the plan notes “Elk River Municipal Utilities provides electric and water services to
Elk River and surrounding areas and is responsible for the construction, operation and maintenance of
these systems.” Vacation of the right-of-way allows them to expand the maintenance facilities to better
serve the community.
4. Our proposal would be consistent with the Utilities Chapter implementation goal to “Develop community
utility facilities to the same aesthetic, environmental and development standards required for private
property.”
What has changed to warrant the vacation?
The street was platted but never constructed and consolidation of several lots to create a developable parcel for the
new Elk River Municipal Utilities maintenance facility requires the vacation. Vacation of the unimproved right-of-way
will allow for development of this necessary public facility.
How compatible is it with surrounding properties?
The new maintenance site would be bound by the river on the south, Main Street on the west and north and
residential property to the east. Vacation of the right-of-way would allow redevelopment of the property and the north
portion of the of the right-of-way will remain to provide access to the adjacent property (parcel 75-133-4211).
What are the benefits to the City?
The vacation allows full use of the site for the Elk River Municipal Utilities maintenance facility. If this unimproved
right-of-way were to remain it would render the site unusable for the intended purpose.
Variance
Description of Request
We are requesting the following variances from city code in order to develop the site:
1. Variance to allow an impervious surface coverage of 61% where 25% is allowed in Section 30-2025.
2. Variance to allow the reduced number of parking stalls of 45 where 243 is required by city code Section 30-
903.
3. Variance to allow a reduced front yard parking setback of 15 feet where 25 feet is required in Section 30-
895.
We have reviewed the requests in accordance with City ordinance standards in Section 30-635 and find that the
ordinance standards have been met. Specifically
Elk River Municipal Utilities, Elk River, MN August 31, 2020
ERMU18001 6
1. The variance is in harmony with the general purpose and intent of the ordinance.
The variance to allow an increased impervious surface is in harmony with the general intent of the
ordinance. The city code does not have a different regulation for impervious surface of a commercial,
industrial or public use within the shoreland overlay and simply restricts all sites to 25% impervious
coverage. The site exists today with 43% impervious surface and we are incorporating additional stormwater
management methods on the site to account for the additional impervious surface proposed. We believe this
meets the intent of the ordinance to protect Elk River from additional stormwater and pollution impacts.
The variance to allow a reduced number of parking stalls is in harmony with the general intent of the
ordinance. The ERMU site is unlike most other sites with most of the building space being used for vehicle
storage, with a smaller portion being used for office space. Given the number employees working on the site
and the minimal number of guests at this location we believe 45 parking spaces to be sufficient for ERMU’s
needs. Additionally, adding greater parking would increase the impervious surface on the site which we are
trying to avoid.
The variance to allow a reduced parking setback meets the general intent of the ordinance. The current
parking setback section restricts a nonresidential use in a single-family district to the same requirements as
the business park district. We have met the intent of the ordinance by locating parking spaces outside of the
setback with all spaces facing towards the interior of the site but are unable to have drive aisle located out of
the parking setback given the location of the existing building. We believe this meets the intent of the
ordinance to have parking not placed or oriented too close to a pedestrian area.
2. The variance is consistent with the City of Elk River comprehensive plan.
The variances are consistent with the City of Elk River comprehensive plan because they allow ERMU to
expand within the existing site. ERMU provides all water service to Elk River, which is a necessity for the
community. ERMU has also been implementing additional measures to conserve water where possible and
to reduce environmental concerns, which will be aided by the expansion.
3. The petitioner proposes to use the property in a reasonable manner not permitted by the zoning ordinance;
We are proposing to continue the existing use of the property as a government facility which is a permitted
conditional use for the R-1c zoning district. The proposed variances allow ERMU to expand from the
existing structures and make needed improvements to the site to allow smooth operations and continued
growth.
4. The plight of the petitioner is due to circumstances unique to the property not a consequence of the
petition's own action or inaction; and
The variance requests are due to the existing buildings and site layout and the code restrictions that have
been put in place since the property was initially developed. This site is unique in that it is restricted by
shoreland overlay standards that are catered towards residential lots you typically find near a lake. The
combination of these circumstances creates a unique property.
5. The variance, if granted, will not alter the essential character of the locality.
Elk River Municipal Utilities, Elk River, MN August 31, 2020
ERMU18001 7
The variances, if granted, will not change the essential character of the locality. The ERMU site has existed
in this location for many years and become a part of the locality. These variances will allow the site to be
developed around the existing buildings and to remain with the same character that exists today.
Summary
We respectfully request approval of the rezoning, conditional use permit, preliminary plat, final plat, ROW vacation
and variances to allow construction of the new maintenance facility for Elk River Municipal Utilities on the site.
Contact Information
This document was prepared by:
Kevin Shay
Landform
105 South Fifth Avenue, Suite 513
Minneapolis, MN 55401
Any additional questions regarding this application can be directed to Kevin Shay at kshay@landform.net or
612.638.0228.