Installed 15 new residential services, which involves the installation of a secondary line
once the customer requests service.
Staff is in the process of tearing down the overhead lines on Edison Street now that the
underground infrastructure is complete, and customers have been transferred to that
service.
Staffis also tearing down the overhead lines by the roundabouts on County Road 39 in
Otsegonow that those customers have been transferred to underground service.
th
Work is complete on the Hillside 12 Addition͵
Staff is working on installing the underground feeder cable to replace the overhead
infrastructure at the field services building. This is part of preparations for the facility
expansion construction.
Installed temporary services for the construction project at the Fire/Police station next
to City Hall.
Working on installing underground line for the new Trout Ridge Run Addition.
Staff is replacing the overhead lines with new underground service for a customer on
173rd Avenue and Highway 10.
Installing three phase underground line on Rawlings Avenue in Dayton for a new house
and future development.
Installed two security lights for a customer on Freeport Avenue and Main Street.
Finishing the last details for the electric departments portion of the County State Aid
Highway 12 reconstruction.