6.1k ERMUSR 01-12-2021UTILITIES COMMISSION MEETING
TO:FROM:
ERMU CommissionChris Kerzman– Engineering Manager
MEETING DATE: AGENDA ITEM NUMBER:
January 12, 20216.1k
SUBJECT:
Staff Update
ACTION REQUESTED:
None
DISCUSSION:
The IT/OT Technician continues to assist staff working from home, as well as working
with city staff planning for network upgrades.
The conditional use permit was approved by the City Council at their December 21
meeting. The updated wetland impacts were submitted and reviewed by the Technical
Evaluation Panel and approved. The United StatesArmy Corps of Engineers will be
updating the permit prior to ERMU’spurchase of additional wetlands credits.
We are working with our sales representative to receive a firm delivery date for the
transformer at the field services facility. They are indicating that it may be delayed until
the end of February instead of early February as previously indicated and are citing
COVID-19 delays as the reason.
RJM Construction and our attorney are working through a couple details on the
construction management contract, which will be brought to the Commission at the
February meeting. RJM continues to assist with pre-construction services. Initial
budgetary estimates are slightly higher than budget and they anticipate getting value
engineering estimates to us during the week of January 11.
______________________________________________________________________________
Page 1 of 1