8.1. SR 02-01-2021
The Elk River Vision
A welcoming community with revolutionary and spirited resourcefulness, exceptional
service, and community engagement that encourages and inspires prosperity. Updated: August 2020
Request for Action
To
Mayor and City Council
Item Number
8.1
Agenda Section
General Business
Meeting Date
February 1, 2021
Prepared by
Amanda Erickson, Environmental Coordinator
Item Description
LORE Project Update and Fish Restocking
Request
Reviewed by
Brandon Wisner, Engineering Project Manager
Reviewed by
Cal Portner, City Administrator
Action Requested
1. Discuss overall LORE project update.
2. Consider/Approve by motion, adding fish restocking cost to the LORE budget.
Background/Discussion
The Lake Orono Restoration and Enhancement (LORE) project continues to move forward with significant
dredging and hauling occurring soon with the presence of colder weather.
Project Update
The existing conditions lake survey was recently completed, and the results are very similar to the survey
completed in 2019 by WSB, the project consultant. The data found the lake bottom elevations were almost always
within 2” of the previous survey, although more elevations were found to be higher than lower. This data was used
to compute an updated estimated quantity of material for excavation. WSB has estimated that an additional 5,000
cubic yards of material will need to be removed to meet desired water depths as approved for the project. The
original estimation was 125,000 cubic yards. The plan specifications require a minimum depth of excavation. It is
possible New Look Contracting, the project contractor, may over-excavate a few inches to ensure these depths are
reached, which would further increase the quantity of material removed.
Our best estimate anticipates 130,000 cubic yards at minimum of sediment removed. Due to the warm weather
and schedule concerns, WSB is reluctant to recommend increased quantity of excavation to ensure completion of
the project and stay within permitting requirements. The overall project budget continues to stay well under the
projected amount, however additional costs and change orders may be necessary in the coming months to ensure
the project is completed fully and within the timeframe restraints. At this time, staff estimates there will be an
assessment to private lakeshore property owners, however the estimated amount should be significantly lower
than that outlined in the May 2020 Feasibility Summary.
Fish Restocking Request
The Orono Lake Improvement District (OLID) Board and some lakeshore residents are concerned about the
potential decline in fish populations due to the drawdown, winterkill, and possible overfishing this winter. The
OLID evaluated options to resolve this concern with the help of the Department of Natural Resources (DNR)
Fisheries Manager. They considered adding an aerator to reduce overfishing, however due to cost and logistical
concerns this option was not pursued. The DNR recommended restocking the lake with fish after the LORE
N:\Public Bodies\Agenda Packets\02-01-2021\Final\Laserfiche\x8.1 sr LORE Project Update and Fish Restocking.docx
project is complete to account for any observed winterkill or overfishing. DNR staff has offered to partner with
the city and provide guidance in determining fish populations based on a fish survey this spring, after the lake is
returned to its normal water level.
The OLID Board is requesting the cost of the fish restocking be allocated from the LORE budget. If the City
Council feels strongly that some of the funding come from the OLID, the board would consider it, as they have
$2,000 available. However, they feel reserving this amount for future fish restocking is more prudent. Based on
their research and conversation with the DNR, the Board believes the fish restocking is the most cost-effective
option providing the highest value to the lake and its users. They have contacted five local Fish Distributors for
cost estimates. The actual cost for fish would be dependent on the fish survey and recommendations from the
DNR.
The estimated cost is $5,000 - $7,000 depending on the types of fish available and observed population decline.
This amount can be added to the overall LORE project budget and better defined later. The assessment amount
does not need to be determined until a later date, likely when a significant portion of the project is completed,
including other potential costs from the contractor, consultant, or additional fees.
Financial Impact
LORE project budget – additional fish restocking fee
Mission/Policy/Goal
Meet changing needs - Agile
Attachments
▪ WSB Lake Orono Improvement Project Memo January 22, 2021
▪ OLID Board: Fish Restocking 2021 Cost Proposal
\\wsbgvfiles01\projects\015125-000\Admin\Construction Admin\Additional Excavation01222021.docx 701 XENIA AVENUE S | SUITE 300 | MINNEAPOLIS, MN | 55416 | 763.541.4800 | WSBENG.COM Memorandum
To: Brandon Wisner, City of Elk River
From: Pete Willenbring, P.E., WSB
Date: January 22, 2021
Re: Lake Orono Improvement Project
WSB Project No. 015125-000
As provided for in the Plans and Specifications for the LORE project, a lake bottom survey was
undertaken immediately prior to the commencement of dredging for the purpose of developing
updated and jointly agreed upon pre-excavation elevations with the contractor that will be used to
compute amount of material removed once the excavation is completed. This survey was
undertaken as a collaborative effort with New Look Contracting in 2021.
The recent survey found that lake bottom elevations were almost always within plus or
minus 2 inches of the previous 2019 survey, however more elevations were found to be
higher than lower. Given the soft conditions on the lake bottom and opportunity for more
sediment to accumulate since the last survey, these elevations are well within survey tolerances,
and to some extent an increase and or deviation from the previous survey was expected.
The updated survey information was used to compute an updated estimated quantity of material
that would need to be removed to achieve the water depths proposed in the plan. These
computations indicate that because the lake bottom has more areas that are slightly higher than
previously surveyed, approximately 5,000 yards of additional material will need to be removed in
the various areas to meet desired water depths. This compares to a previous estimate of 125,000
yards.
In addition, because the contractor’s equipment cannot excavate to an exact depth, and our
specifications require a minimum depth excavation, it is possible the contractor may over-
excavate a few inches, which could further increase the quantity of material removed.
Based on the above, our best estimate is to now anticipate between 130,000 and 150,000 yards
of material will be removed from the lake as part of the project, and unless other direction is
provided to the contractor, estimate the total construction cost to come in between $2,175,000
and $2,400,000. If you have any questions, please feel free to contact me at 612.360.1288.
1
LAKE ORONO FISH RESTOCKING 2021 COST PROPOSAL
OVERVIEW
1. Project Background and Description
With the upcoming LORE project we inquired into different options that could be taken to improve the
fish survival while the 6.5’ drawdown was in place. The fish are confined to the few “deeper” areas of the
lake during this time and are especially vulnerable and easy to target in these conditions. The primary
concern that we have heard from lake owners and community fisherman is the potential damaging effect
the LORE project will have on the fish population. When the lake drawdown first occurred there was an
estimated 500+ adult fish that were driven over the dam and rescued from the lower pools to be
released into the Mississippi River by concerned lake owners. Given these numbers we conservatively
estimate at least 5,000 fish were lost over the dam during the initial drawdown. Another lake owner has
documented a weekly average of 15+ fish kill walking the same 400 foot stretch of shoreline along Main
Street since the drawdown has been in place.
The DNR was unable to issue a temporary restriction on fishing during the LORE project to reduce the
threat of overfishing but has instead supported installing an aeration system. A lake owner offered use of
a ½ HP Kasco surface aerator but our expert aeration sources found this system to be inefficient and not
up to the task. Recommended by the DNR, installing a 3 HP Aire O2 surface aspirator would reduce
overfishing by preventing fishing directly over the deepest fish habitat where they will gather due to the
lowered lake levels. After consulting with ERMU the electrical infrastructure in the proximity of where
the aspirator would be placed (off the West point of the Orono cemetery) would not be sufficient for the
3HP unit. Instead a 2HP, single phase unit was quoted and required a higher gauge cable which in result
increased the estimated cost to $9,7852.86. Initially we were estimating the cost to be $4-5,000 and that
has doubled due to the higher material costs and additional electrical requirements that were not
anticipated.
At this time due to the increased costs we are proposing as an alternative to installing an aerator, and as
recommended by the DNR, use of funds from the LORE project for fish restocking in partnership with the
DNR. Joe Stewig, DNR Area Fisheries Manager has been very helpful and has offered to partner with us to
determine what the fish population is in the spring and work with us to restock. The goal would be to
replace any fish kill with fingerling and adult species that would be able to spawn in the upcoming
season.
2
2. Project Scope
The OLID believes it would be appropriate for the City to use LORE funds for fish restocking since Lake
Orono is a public lake and all public users would be impacted. If the City feels strongly that some of
the funding should come from OLID, the board would consider that as well. The highest amount
available being $2,000. However, reserving that amount for future stocking needs may be most
prudent.
With the higher costs and additional steps associated with the aerator, we believe restocking would
be the most cost effective, beneficial and provide the most value to the lake and it’s users, per Joe
Stewig’s recommendation. The DNR has offered to conduct a survey to compare how the lake is
performing relative to similar lakes and determine how much restocking is needed at that time.
The DNR has offered that if we forego the aeration system and that the lake takes some winterkill
and/or overfishing occurs they are willing to work with the OLID to restock the lake. They would bring
in their shock boat to survey the fish and assist with locating some mature bass and bluegills to stock
before they spawn.
The DNR provided a list of 6 Fish Distributors in the area and contact was made with 5 to estimate
restocking costs, all sources were similar in costs. Ron Rademacher was one of the recommended fish
distributors and previously provided stocking to Orono Lake after the last dredge. His previous
knowledge and understanding of the lake ecosystem was beneficial when discussing the plan to
restock. Per Ron, the cost to restock the lake would be approximately $5,000 based on the 1998
restocking costs. A major fish kill of 75% or more would increase the cost to $7,000 however this may
be lower depending on availability of fish from the DNR. Estimates were based on restocking bluegill,
black crappies, yellow perch and small mouth bass.
The estimated cost of 3-6” bluegill and black crappies were $1.25-1.50 a piece. The cost for a 2-5lb.
pair of small mouth bass that can spawn before the end of May was $50. Each pair being capable of
producing 5,000-12,000 eggs per nest. Yellow perch were not available from all suppliers however
Ron Rademacher would be able to provide them at the $1.25-1.50 pricing. Some restocking may be
done in the fall of 2021 or Spring of 2022 depending on the timing of ice out, when the water was
brought back to its normal level, when the survey was completed and availability of fish at that time.
3
3. Costs Involved
(500-750) $1.25-1.50 apiece 3-6” Blue Gill
(500-750) $1.25-1.50 apiece 3-6” Crappies
(500-750) $1.25-1.50 3-6” Yellow Perch
(30-60) $50 per adult pair Small Mouth Bass. (May wait to restock them Spring 2022)
$5,000 total cost with anticipated loss of fish.
or
$7,000 total cost with a large winterkill however the DNR will be able to provide some fish lowering
the overall cost.
4. High-Level Timeline/Schedule
Fish Distributor’s would need to schedule stocking by early May to stock fish prior to end of May in time for the new
fish to spawn in Lake Orono.