2021 Watermain Relocation Improvements Project – Award of Bid
ACTION REQUESTED:
Approve, by motion, award of the low bid and authorize the execution of a contract with G.F.
Jedlicki, Inc. for the 2021 Watermain Relocation Improvements Project.
BACKGROUND:
Staff has been working with Elfering & Associates to design and bid the 2021 Watermain
Relocation Improvements project associated with the Highway 169 Redefine. The project was
noticed for formal bids from July 24, 2021, to August 19, 2021.
DISCUSSION:
The bid opening was August 19, 2021, at 11:00 a.m.; four bids were received. The low
responsible bidder was G.F. Jedlicki, Inc. Staff and Elfering & Associates recommend awarding
the bid to G.F. Jedlicki, Inc. Attached is the bid tabulation and recommendation for award
letter.
FINANCIAL IMPACT:
As presented on bid tabulation.
ATTACHMENT:
•2021 Watermain Relocation Improvements Bid Tabulation
•Elfering & Associates Bid Results and Recommendation for Award Letter
3
BID TABULATION
PROJECT: 2021 Watermain Relocation Improvements
OWNER: Elk River Municipal Utilities
OPENING DATE:August 19, 2021 at 11:00 am
ENGINEER: Elfering & Associates
ITEM ITEM DESCRIPTION
NO.UNIT QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
($)($)($)($)($)($)($)($)
SCHEDULE 1.0 - TH10/ TH169 NORTH BOUND RAMP
1 MOBILIZATION LS 1.00 $5,500.00 $5,500.00 $19,625.00 $19,625.00 $50,000.00 $50,000.00 $5,000.00 $5,000.00
2 CONNECT TO EXISTING WATERMAIN EA 2.00 $7,315.00 $14,630.00 $13,472.50 $26,945.00 $9,022.00 $18,044.00 $14,000.00 $28,000.00
3 16" BUTTERFLY VALVE EA 1.00 $13,350.00 $13,350.00 $10,660.00 $10,660.00 $8,034.00 $8,034.00 $8,000.00 $8,000.00
4 16" WATERMAIN LF 575.00 $214.00 $123,050.00 $154.78 $88,998.50 $272.00 $156,400.00 $200.00 $115,000.00
5 TESTING LS 1.00 $3,200.00 $3,200.00 $5,500.00 $5,500.00 $3,500.00 $3,500.00 $1,500.00 $1,500.00
6 TRAFFIC CONTROL LS 1.00 $3,200.00 $3,200.00 $1,575.00 $1,575.00 $6,500.00 $6,500.00 $2,500.00 $2,500.00
7 RESTORATION LS 1.00 $13,230.00 $13,230.00 $8,272.00 $8,272.00 $3,500.00 $3,500.00 $30,000.00 $30,000.00
SCHEDULE 1.0 - TH10/ TH169 NORTH BOUND RAMP - TOTAL $176,160.00 $161,575.50 $245,978.00 $190,000.00
SCHEDULE 2.0 - MNDOT PARK & RIDE
1 MOBILIZATION LS 1.00 $8,400.00 $8,400.00 $13,625.00 $13,625.00 $50,000.00 $50,000.00 $5,000.00 $5,000.00
2 CONNECT TO EXISTING WATERMAIN EA 3.00 $8,650.00 $25,950.00 $7,972.50 $23,917.50 $6,850.00 $20,550.00 $9,500.00 $28,500.00
3 16" BUTTERFLY VALVE EA 1.00 $8,500.00 $8,500.00 $9,585.00 $9,585.00 $8,034.00 $8,034.00 $7,000.00 $7,000.00
4 16" WATERMAIN LF 1,345.00 $214.00 $287,830.00 $159.95 $215,132.75 $215.00 $289,175.00 $190.00 $255,550.00
5 TESTING LS 1.00 $4,900.00 $4,900.00 $5,500.00 $5,500.00 $4,000.00 $4,000.00 $1,500.00 $1,500.00
6 TRAFFIC CONTROL LS 1.00 $5,645.00 $5,645.00 $420.00 $420.00 $2,500.00 $2,500.00 $1,000.00 $1,000.00
7 RESTORATION LS 1.00 $27,450.00 $27,450.00 $47,140.00 $47,140.00 $26,000.00 $26,000.00 $65,000.00 $65,000.00
$27,450.00
SCHEDULE 2.0 - MNDOT PARK & RIDE - TOTAL $368,675.00 $315,320.25 $400,259.00 $363,550.00
SCHEDULE 3.0 - FREEPORT AVENUE
1 MOBILIZATION LS 1.00 $7,500.00 $7,500.00 $13,625.00 $13,625.00 $50,000.00 $50,000.00 $35,000.00 $35,000.00
2 CONNECT TO EXISTING WATERMAIN EA 3.00 $9,235.00 $27,705.00 $14,762.50 $44,287.50 $6,966.00 $20,898.00 $10,000.00 $30,000.00
3 CONNECT TO EXISTING SERVICE EA 1.00 $1,145.00 $1,145.00 $6,037.50 $6,037.50 $2,526.00 $2,526.00 $1,200.00 $1,200.00
4 16" BUTTERFLY VALVE EA 2.00 $8,500.00 $17,000.00 $11,305.00 $22,610.00 $8,034.00 $16,068.00 $9,000.00 $18,000.00
5 6" GATE VALVE EA 1.00 $4,450.00 $4,450.00 $7,435.00 $7,435.00 $3,353.30 $3,353.30 $3,250.00 $3,250.00
6 16" WATERMAIN LF 825.00 $268.00 $221,100.00 $226.78 $187,093.50 $295.00 $243,375.00 $250.00 $206,250.00
7 2" COPPER WATER SERVICE LF 100.00 $68.00 $6,800.00 $100.21 $10,021.00 $51.88 $5,188.00 $125.00 $12,500.00
8 2" CORPORATION EA 1.00 $1,465.00 $1,465.00 $2,424.58 $2,424.58 $1,913.33 $1,913.33 $1,600.00 $1,600.00
9 2" CURB STOP AND BOX EA 1.00 $1,780.00 $1,780.00 $2,435.33 $2,435.33 $1,962.73 $1,962.73 $1,600.00 $1,600.00
10 HYDRANT W/ VALVE EA 1.00 $8,230.00 $8,230.00 $8,504.17 $8,504.17 $7,380.92 $7,380.92 $9,000.00 $9,000.00
11 TESTING LS 1.00 $3,665.00 $3,665.00 $5,500.00 $5,500.00 $4,250.00 $4,250.00 $1,500.00 $1,500.00
12 TRAFFIC CONTROL LS 1.00 $9,400.00 $9,400.00 $7,350.00 $7,350.00 $8,500.00 $8,500.00 $38,000.00 $38,000.00
13 RESTORATION LS 1.00 $68,655.00 $68,655.00 $160,500.00 $160,500.00 $37,500.00 $37,500.00 $300,000.00 $300,000.00
SCHEDULE 3.0 - FREEPORT AVENUE - TOTAL $378,895.00 $477,823.58 $402,915.28 $657,900.00
GM CONTRACTINGG. F. JEDLICKI
NORTHDALE CONSTRUCTION CO
INC NEW LOOK CONTRACTING
1 of 2
4
ITEM ITEM DESCRIPTION
NO.UNIT QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
($)($)($)($)($)($)($)($)
GM CONTRACTINGG. F. JEDLICKI
NORTHDALE CONSTRUCTION CO
INC NEW LOOK CONTRACTING
SCHEDULE 4.0 - BOOSTER STATION
1 MOBILIZATION LS 1.00 $3,200.00 $3,200.00 $5,500.00 $5,500.00 $7,000.00 $7,000.00 $1,500.00 $1,500.00
2 REMOVE AND SALVAGE BOOSTER STATION LS 1.00 $22,300.00 $22,300.00 $23,612.50 $23,612.50 $17,500.00 $17,500.00 $15,000.00 $15,000.00
3 TRAFFIC CONTROL LS 1.00 $3,110.00 $3,110.00 $525.00 $525.00 $2,250.00 $2,250.00 $1,500.00 $1,500.00
4 RESTORATION LS 1.00 $2,850.00 $2,850.00 $4,325.00 $4,325.00 $4,000.00 $4,000.00 $5,500.00 $5,500.00
SCHEDULE 4.0 - BOOSTER STATION - TOTAL $31,460.00 $33,962.50 $30,750.00 $23,500.00
ALTERNATE 1.0 - GAS STATION REALIGNMENT
1 ALTERNATE ALIGNMENT LS 1 $66,455.00 $66,455.00 $56,450.00 $56,450.00 $45,000.00 $45,000.00 $215,000.00 $215,000.00
ALTERNATE 1.0 - GAST STATION REALIGNMENT - TOTAL $66,455.00 $56,450.00 $45,000.00 $215,000.00
BID SUMMARY - TOTAL
SCHEDULE 1.0 - TH10/ TH169 NORTH BOUND RAMP - TOTAL $176,160.00 $161,575.50 $245,978.00 $190,000.00
SCHEDULE 2.0 - MNDOT PARK & RIDE - TOTAL $368,675.00 $315,320.25 $400,259.00 $363,550.00
SCHEDULE 3.0 - FREEPORT AVENUE - TOTAL $378,895.00 $477,823.58 $402,915.28 $657,900.00
SCHEDULE 4.0 - BOOSTER STATION - TOTAL $31,460.00 $33,962.50 $30,750.00 $23,500.00
TOTAL BASE BID $955,190.00 $988,681.83 $1,079,902.28 $1,234,950.00
ALTERNATE 1.0 $66,455.00 $56,450.00 $45,000.00 $215,000.00
TOTAL BASE BID WITH ALTERNATE 1.0 $1,021,645.00 $1,045,131.83 $1,124,902.28 $1,449,950.00
I HEREBY CERTIFY THAT THIS IS AN ACCURATE TABULATION OF THE BIDS
RECEIVED FOR THE ABOVE MENTIONED PROJECT.
NAME: Kristie Elfering, P.E.
DATE: August 19, 2021
MN REG. NO.: 42350
2 of 2
5
10062 Flanders Court NE – Blaine, MN 55449 – Ph: (763) 780-0450 Fax (763) 780-0452
August 20, 2021
File: 235037E-0071
Mr. Dave Ninow
Elk River Municipal Utilities
13069 Orono Parkway
PO Box 430
Elk River, MN 55330
RE: 2021 WATERMAIN RELOCATION IMPROVEMENTS PROJECT
ELK RIVER MUNICIPAL UTILITIES
Dear Mr. Ninow:
Bids were opened for the above referenced project at 11:00 a.m. on Thursday, August
19, 2021 in accordance with the Advertisement for Bids. Four (4) bids were received
from the following companies listed below from lowest to highest total bid:
Corporation Total Base Bid Total Base Bid with Alternate
G. F. Jedlicki $ 955,190.00 $1,021,645.00
Northdale Construction $ 988,681.83 $1,045,131.83
GM Contracting $1,079,902.28 $1,124,902.28
New Look Contracting $1,234,950.00 $1,449,950.00
The low bid received from G. F. Jedlicki is over the anticipated construction costs, but
based on the bids received appears to be competitive and all bids have been reviewed
for errors and/or omissions. G. F. Jedlicki has completed projects within the City of Elk
River and past experience with them reflects that they are a responsive and responsible
bidder.
In review of the bids we believe that ERMU has received a competitive bid for the work
and the higher costs are a result of the current upward trend in construction prices and
materials. The work also needs to be completed ahead of the MnDOT TH 169 project.
We would recommend that ERMU award the project to G. F. Jedlicki as the low,
responsible bidder.
If you have any questions concerning this information, please call me at (763) 780-0450
Ext. 2.
Sincerely,
Elfering & Associates
Kristie Elfering, P.E.