5.6 ERMUSR 11-09-2021UTILITIES COMMISSION MEETING TO:FROM: ERMU Commission Chris Kerzman –Engineering Manager MEETING DATE: AGENDA ITEM NUMBER: November 9, 2021 5.6 SUBJECT: Field Services Facility Expansion ProjectUpdate ACTION REQUESTED: None BACKGROUND: Construction continues on the Field Services Facility. DISCUSSION: Steel installation has been going very well andthe majority of the joists and decking have been installed. There are now a couple weeks of detailing to be completed. There has been a lot of earthwork and grading happening to prepare for laying the first course of asphalt during the week of November 8. The concrete contractors have installed the retaining walls for stairway entries, stoop foundations, and block wall for overhead doors. Work over the next month will include curb installation and paving through the middle of the site, followed by outdoor electrical installation. Inside the building, the plumbing contractor will be working on underground piping installation to prepare for the floor pour, while the steel contractor finishes up detailing and the precast panel wall contractor finishes up caulking and detailing. The roofing contractor is optimistic that they have an option for insulation. We are working through those details with Kodet Architectural Group, LTD and RJM Construction. ______________________________________________________________________________ Page 1 of 1 97