5.7 ERMUSR 11-09-2021UTILITIES COMMISSION MEETING
TO: FROM:
ERMU Commission Dave Ninow Water Superintendent
MEETING DATE: AGENDA ITEM NUMBER:
November 9, 2021 5.7
SUBJECT:
County Road 13 Reconstruction Project Update
ACTION REQUESTED:
Authorize payment to Sherburne County for a change order not to exceed agreed upon amount
for water main pipe relocation and insulating work for the CSAH 13 project.
BACKGROUND:
ERMU typically relocates its utility facilities at ERMUs cost to accommodate county and state
road projects. After work began on the County Road 13 (CSAH 13) project, the Countys
contractor discovered that the existing water main pipe conflicted with installation of new a
storm sewer pipe. This discovery raised concerns about the depth of the existing water main
pipes under the new road, and further investigation revealed that approximately 1,587 feet of
water main pipe needed to be lowered and/or insulated.
Because the need to relocate the water main was not identified in the planning stages of the
CSAH 13 project and needed to be undertaken immediately to prevent delay in completion of
the project, ERMU did not have sufficient time to complete the public bidding process and
relocate the water main on its own. It was determined that the only legal way to get the
relocation done and keep the CSAH 13 project on schedule was to have the relocation done by
the Countys contractor through a change order and have ERMU reimburse the County for the
cost of the change order. ERMU staff has been working with a consultant and legal counsel to
determine the appropriate amount of that reimbursement, but it will not exceed $261,882.
DISCUSSION:
Staff will provide a verbal update at the commission meeting.
FINANCIAL IMPACT:
The agreed upon amount is to pay no more than $261,882.
______________________________________________________________________________
Page 1 of 1
98