4.9 SR 05-16-2022Request for Action
To
Item Number
Mayor and Ci T Council
4.9
Agenda Section
Meeting Date
Prepared by
Consent
May 16, 2022
Ryan Sandhoefner, Engineer 1
Item Description
Reviewed by
Change Order 1: 2022 Street Improvements
Justin Femrite P.E., Public Works Director
Reviewed by
Cal Portner, City Administrator
Action Requested
Approve, by motion, the following change order for the 2022 Street Improvement project.
Background/Discussion
CO 1 — Holt St Improvements
■ Holt St is a frontage road that lies between 1971h Ave and Jackson Ave, just west of TH169. A resurfacing
(edge mill and overlay) project is recommended to restore the aged surface that is currently impacting its
rideability due to cracking, potholes, and patches from utility relocate work completed in the past year. With
the closure of 1971h Ave, a window of time is available to complete this work before the heavier traffic
demands expected in 2023.
Financial Impact
CO 1 - $119,157.24
■ Pavement Management funds used for the entire cost
Mission/Policy/Goal
Meet Changing Needs - Agile
Attachments
■ Change Order 1
The Elk River Vision
A welcoming community with revolutionary and spirited resourcefulness, exceptional
service, and community engagement that encourages and inspires pi ospei l_ y.
M
TUREJ
Updated.• August 2020
on reverse side
PROJECT: 2022 Street Improvements
OWNER: City of Ells River
13065 Orono Parkway
Elk River, MN 55330
CONTRACTOR: North Valley, Inc.
CONTRACT FOR: 2022 Street Improvements
SECTION 00671
Change Order
2022 Street improvements
Elk River, Minnesota
No.
DATE OF ISSUANCE: 5/11/2022
You are directed to make the following changes in the Contract Documents.
Description:
Purpose of Change Order: Addition of Holt St Resurfacing
Attachments (List documents supporting change):
North Valley Quote, Site Map
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
Original Contract Price
$ 338.381.70
Original Contract Time
Substantial Completion: 10/15/2022
Final Completion:10 r 15 ' 2022
Previous Change Orders No. to No.
Net change from previous Change Orders
_ _
$
0 Days
Contract Price prior to this Change Order
_
Contract Time prior to this Change Order
Substantial Completion:10/15/2022
$ 338,381.70
Final Completion: 10/15/2022
Net Increase (Decrease) of this Change Order
Net Increase (Decrease) of this Change Order
0 days for Substantial Completion
$119,157.24
days for Final Completion
Contract Price with all approved Change Orders
Contract Time with all approved Cha pe Orders
Substantial 10/151822
Completion:
$ 457,538.94
Final Completion: 10 15 /2022
By
city � lgi
ETCDC No.
, D: APPROVED:
By
City of Elk River
n za;i1P "
By
Ala,,A t/dlky 3. —,x,
Change Order 00671 - 1
Change Order
Instructions
A. General Information
2022 Street Improvements
Elk River, Minnesota
This document was developed to provide a uniform format for handling contract changes that affect
Contract Price or Contract Time. Changes that have been initiated by a Work Directive Change
must be incorporated into a subsequent Change Order if they Affect Price of Time.
Changes that affect Contract Price or Contract Time should be promptly covered by a Change
Order. The practice of accumulating change order items to reduce the administrative burden may
lead to unnecessary disputes.
For supplemental instructions and minor changes not involving a Change in the Contract Price or
Contract Time, a Field Order may be used.
B. Completing the Change Order Form
Engineer initiates the form, including a description of the changes involved and attachments based
upon documents and proposals submitted by Contractor, or requests from Owner, or Both.
Once Engineer has completed and signed the form, all copies should be sent to Contractor for
approval. After approval by Contractor, all copies should be sent to Owner for approval. Engineer
should make distribution of executed copies after approval by Owner.
If a change only applies to price or to the time, cross out the part of the tabulation that does not
apply.
Change Order 00671 - 2
20015 Iguan�hSRieet NW, Suite 100
Nowthen, MN 55330
(763) 274-2580 Fax (763) 274-2584
PLEASE ACCEPT OUR SUB QUOTE FOR THE FOLLOWING PROJECT:
BID DATE: 5/4/2022
BID TIME:
GENERAL CONTRACTOR: CITY OF ELK RIVER
PROJECT DESCRIPTION: ADDITIONAL WORK (HOLT ST
PROJECT NO:
ESTIMATOR: STEWART PACKER
ITEM NO.
DESCRIPTION OF ITEM
QUANTITY
UNIT
PRICE
EXTENDED AMOUNT
MOBILIZATION
100
LS
$ 3.472.08
$ 3,472.08
EDGE MILL (1.25'' - 0'')
4,355,00
SY
$ 1.37
$ 5,96635
1.5" BITUMINOUS WEAR COURSE
1,100.00
TN
$ 88.50
$ 97,350 00
4'' SOLID 2 LINE - MULTI COMP
870.00
LF
$ 0.46
$ 400,20
24'' SOLID LINE - MULTI COMP
48.00
LF
$ 8.68
$ 41664
4'' BROKEN LINE - MULTI COMP
100.00
LF
$ 0.46
$ 46.00
4'' DOUBLE LINE - MULTI COMP
2,520.00
LF
$ 0.90
$ 2,268.00
PAVEMENT MESSAGE - MULTI COMP
123.60
SF
$ 8.68
$ 1,072.85
CROSSWALK - MULTI COMP
30600
SF
$ 7.38
$ 2,25828
MANHOLEADJUST (IRON RING)
10.00
EA
$ 271.26
$ 2,712.60
GATE VALVE ADJUST (IRON RING)
10.00
EA
$ 92.23
$ 922,30
BITUMINOUS PATCHING IF NEEDED
10.00
SY
$ 64.44
$ 644,40
TRAFFIC CONTROL
1.00
LS
$ 1.627.54
$ 1,627 54
TOTAL:
$ 119,157.24
BOND IS INCLUDED, CANNOT DEDUCT FOR ONE
NO TRAFFIC CONTROL
PRICE INCLUDES TAX
RETAINAGE HELD PER OWNERS SPECIFICIATIONS
THIS QUOTE IS PER THE AGC STANDARD SUB -CONTRACT AGREEMENT FOR HIGHWAY/HEAVY-
INDUSTRIAL DIVISION (1956 EDITION, REVISED 1966, REVISED 1980 AND RIDER 1986 REVISION)
UPON REQUEST, NORTH VALLEY, INC. SHALL BE PROVIDED WITH THE LEGAL DESCRIPTION OF THE PROPERTY, THE
NAME AND ADDRESS OF THE OWNER.
NORTH VALLEY, INC. SHALL NOT BE OBLIGATED TO COMMENCE OR CONTINUE SUBCONTRACT WORK UNLESS
ADEQUATE ASSURANCE OF PAYMENT IS RECEIVED.
QUOTE MAY BE WITHDRAWN IN 10 DAYS.
COMMENTS: BID GOOD FOR ITEMS AND MATERIALS QUOTED ABOVE ONLY
PRICES GOOD FOR "2022"
ASPHALZ
100% RECYCLABLE
Page 1