SUBJECT:
Staff Update
ACTION REQUESTED:
None
DISCUSSION:
Delivered eightnew water meters, sealed the meter,installed an encoder receiver
transmitter, and took curb stop ties.
Completed 15 BACTI/Total Chlorine Residual Samples
o All confirmed negative for Coliform Bacteria.
o Bacteriological/Disinfectant Residual Monthly Report submitted to the MDH
Completed 21 routine fluoride samples
o All samples met MDH standards.
o Submitted MDH Fluoride Report
Submitted Discharge Monitoring Report for the Diesel Generation Plant to the
Minnesota Pollution Control Agency.
With combined efforts of staff in many departments at ERMU along with Robyn Hoerr
from Minnesota Rural Water Association and Terry Bovee Water Resource Planner,
there is continued progress on a draft of part two of the Well Head Protection Plan
revision. We are on track to meet the deadline for submitting the plan revision by
February 2023.
The existing roofing for the Well 3 water treatment building has been removed and
replaced. This was part of the 2022 Capital Projects budget as the roof has reached the
end of its lifespan and had developed leaks.
th
Water Department staff have been working with the contactor for Miske Meadows 8
Additionon performing water main shutdowns for connection of new water main pipe
in that development.
ATTACHMENTS:
September 2022 Pumping by Well