4.5 SR 10-17-2022Request for Action To Item Number Mayor and City Council 4.5 Agenda Section Meeting Date Prepared by Consent October 17, 2022 Justin Femrite, P.E., Public Works Director Item Description Reviewed by County Road 33 Cost Participation Agreement with Cal Portner, City Administrator Sherburne County Reviewed by Action Requested Approve, by motion, cost participation agreement with Sherburne County for design modifications on CSAH 33. Background/Discussion As discussed during the preliminary design process for the CSAH 33 Improvements, the city asked Sherburne County to add design elements in their roadway project that would more easily allow for the construction of a trail along the corridor from TH 169 to CSAH 13 in the future. The attached agreement provides for the additional design work needed to make this adjustment. Financial Impact The $136,771.00 represented in the agreement has been identified and include in previous estimates for making accommodation with the current project to allow for a future trail. All city costs associated with this project, including the design costs detailed in the agreement, will be supported from our State Aid Account. Mission/Policy/Goal Opportunity to live, work and play Attachments ■ Cost Participation Agreement The Elk River Vision A welcoming community with revolutionary and spirited resourcefulness, exceptional service, and community engagement that encourages and inspires pi ospei ly. M TUREJ Updated.• August 2020 COST PARTICIPATION AGREEMENT BETWEEN SHERBURNE COUNTY AND CITY OF ELK RIVER CSAH 33 FUTURE TRAIL DESIGN THIS AGREEMENT is made and entered into this day of , 2022, (the "Effective Date") by and between the County of Sherburne, a political subdivision of the State of Minnesota, 13880 Business Center Drive NW, Elk River, Minnesota 55330, (the "County"), and the City of Elk River, 13065 Orono Parkway, Elk River, MN 55330 (the "City"). WHEREAS, the County is in the process of designing certain improvements to CSAH 33 within the City; and WHEREAS, the City desires to construct certain improvements to accommodate a future trail along CSAH 33 within the County's CSAH 33 project area (the "Trail Project"); and WHEREAS, the County and the City agree that it will be cost effective to modify the County's current plans and specification for the CSAH 33 project to accommodate the future Trail Project, and WHEREAS, the City has agreed to be responsible for the additional costs relating to amending the design for CSAH 33 to accommodate the future Trail Project; and WHEREAS, Minn. Stat. § 471.59 authorizes the County and the City to enter into an agreement for the joint exercise of powers and the sharing of resources. NOW, THEREFORE, in consideration of the premises and covenants contained herein and subject to the provisions of Minn. Stat. § 471.59, the parties agree as follows: Purpose. The parties enter into this Agreement for the purpose of redesigning the County's CSAH 33 project to accommodate the City's future Trail Project. 2. Term. Notwithstanding the date of the signatures of the parties, the term of this Agreement shall commence on the Effective Date and shall terminate on the date that the CSAH 33 project design incorporating the Trail Project has been completed. 3. Duties of the County and City. 3.1 Project Design Amendments. The County will amend its current design contract with its contractor (SRF) to modify the Project design in order to accommodate the future Trail Project. 3.2 Cost Participation. The total estimated cost to redesign the County's CSAH 33 project to accommodate the future Trail Project (the "Trail Design Costs") is $163,413.00. The Trail Design Costs include the additional design tasks shown on the attached Exhibits B1 and B3. The future Trail Design Costs shall be shared by the Parties as follows: a. The City will be responsible for the future Trail Design Costs identified on Exhibit B1. This includes 50% of the costs for stormwater/drainage design identified in task 3.15 and 100% of the project costs relating to the remaining tasks. The total estimated City Trail Design Costs are $136,771.00. b. The County will be responsible for the future Trail Design Costs identified on Exhibit B3. This includes 50% of the costs for stormwater/drainage design identified in task 3.15. The total estimated County Trail Design Costs are $26,642.00. The final future Trail Design Costs shall be determined based on the actual approved costs for incorporating the Trail Project pursuant to the terms of the County's design contract. The County will ensure that the Trail Design Costs do not exceed $163,413.00 without prior written approval by the County, which the County will not provide without first consulting with the City. 3.3 Payments to Contractor. For purposes of paying the County's contractor for the Trail Design Costs, the County will process all payment requests from the contractor and will approve or deny the requests as appropriate, pursuant to the terms of the contract. 3.4 Payments to the County. After payment is made by the County for the future Trail Design Costs, the County will submit an invoice to the City for reimbursement of the City's share of the future Trail Design Costs. Payment shall be made to the County within 35 days of when an invoice is received by the City. 4. General Provisions. 4.1 Entire Agreement; Amendments. This Agreement constitutes the entire agreement and understanding of the parties with respect to the subject matter hereof and supersedes all prior and contemporaneous agreements, documents and proposals, oral or written, between the parties with respect thereto. Any amendment or modification to this Agreement shall not be valid unless such amendment or modification (i) is in writing and signed by authorized representatives of both parties and (ii) references this Agreement. The terms and conditions of the exhibits are integral parts of this Agreement and are fully incorporated herein by this reference. 4.2 Cooperation. The parties agree to cooperate in the use of resources, including available right-of-way to complete the project as a whole, to the extent feasible and to the extent permitted by law. The parties further agree to cooperate in the administration of the contract and completion of the project, including cooperating in resolving any disputes the parties may have with the contractor(s) both during the project and following completion of the project. The Parties further anticipate a future cost share agreement relating to the construction of the Trail Project as part of the County's CSAH 33 project. 4.3 Notices. Any notices required or permitted to be given under this Agreement shall be delivered personally or sent by certified mail to the other parry as follows: To the County: Andrew Witter Sherburne County Engineer Sherburne County Government Center 13880 Business Center Drive, Suite 100 Elk River, MN 55330 To the City: City Administrator City of Elk River 13065 Orono Parkway Elk River, MN 55330 4.4 Governing Law. This Agreement shall be governed by the laws of the State of Minnesota. For the purpose of resolving conflicts related to or arising out of this Agreement, the parties expressly agree that venue shall be exclusively in the State of Minnesota, County of Sherburne. 4.5 Disbursement of Funds. All funds disbursed by the County or City pursuant to this Agreement shall be disbursed by each entity pursuant to the method provided by law. 4.6 Audit. The parties shall maintain complete and accurate records with respect to costs incurred and services performed under this Agreement for a period of at least six (6) years after the termination of this Agreement. Pursuant to Minn. Stat. § 16C.05, Subd. 5, each parry shall allow the other parry, the State Auditor, or their authorized representatives access to the books, records, documents, and accounting procedures and practices relevant to the subject matter of the Agreement, for purposes of audit. 4.7 Data Practices. All data created, collected, received, stored, used, maintained, or disseminated for any purpose in connection with this Agreement is governed by the Minnesota Data Practices Act, as well as other State and Federal rules and regulations relating to data privacy. 4.8 Assignment and Delegation. Neither parry shall assign its rights or delegate its duties under this Agreement without receiving the prior written consent of the other parry. 4.9 Liabili . Each parry will be solely responsible for its own acts and omissions and the results thereof, to the extent authorized by law. The parties mutually agree to indemnify and hold harmless each other from any claims, losses, costs, expenses or damages resulting from the acts or omissions of the respective officers, agents, or employees relating to activities conducted by either parry under this Agreement. Minnesota Statutes Chapter 466 and other applicable laws govern the parties' liability. 4.10 Severability. In the event that any portion of this Agreement shall be held to be invalid, such invalidity shall not affect the validity of the remainder of this Agreement. IN WITNESS WHEREOF, the Parties hereto have executed this Agreement to be effective as of the Effective Date set forth above. SHERBURNE COUNTY Attest: Barbara Burandt County Board Chair Bruce Messelt County Administrator CITY OF ELK RIVER Attest: John Dietz Mayor, City of Elk River Tina Allard City Clerk EXHIBIT BI CITY TRAIL DESIGN COSTS EXHIBIT B3 COUNTY TRAIL DESIGN COSTS 6/302022 Exhibit B-1 Page 1 of 12 SRF Consulting Group, Inc. Work Tasks and Person -Hour Estimates Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) SRF Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: 13725.00 TASK NO. SUMMARY OF TASKS Project Overview: 1.0 PROJECT MANAGEMENT Amendment No.2 2.0 PRELIMINARY DESIGN 3.0 DESIGN Provide additional design services to shift previously approved alignment of CSAH 33 north approximately 10 feet to provide additional area along south 4.0 RIGHT OF WAYACQUISITION side for a future 10-foot trail. Update project to include a urban section with curb and gutter along south side from approximately 350 feet west of Auburn 5.0 BRIDGE DESIGN Street eastthru Quincy Street. Update preliminary layout, 30%Construction Plans, 30% Estimate, Fly-Thru Virtual Model for Public Open House and 6.0 CATTLE PASS DESIGN confirm design revisions at Trott Brook. Design will include constructing an urban section (with curb and gutter and storm sewer) from approximately 100 7.0 TROTT BROOK HYDRAULIC DESIGN feet west of the planned cattle pass, under CSAH 33, east over Trott Brook and connect into the proposed curb and gutter atthe roundabout. Re -model noise analysis based upon new alignment and profile east of Quincy Street. Updates will be required for previous wetland delineation graphics and report, design tables and areas for the environmental document and additional effort will be needed to facilitate final design of the corridor. Revise stormwater design to incorporate a storm sewer system, potential pond ing/stormwater treatment and accommodations for future trail. Task numbers correspond to original Work Scope task numbering. Hours for Task 3.15 for Drainage Design reflect a 50/50 split with Sherburne County per cost share agreement. 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 2 of 12 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION 1.0 PROJECT MANAGEMENT Assumptions: - Originally 12 months of active design work requiring general PM activities; overall schedule was up to 1S months. Revised schedule to extend completion date by 9 months due to City consideration of trail. - PMT and Open House meetings will continue to be virtual via Zoom or other video conferencing software. Client Deliverables: - Timely review of draft deliverables 1.1 Additional Administration ofthe project will include additional monthly progress reports with budget status, invoicing, contract amendment requests (if necessary), cost and schedule updates, billing preparation, other non -technical work, communication with the necessary project personnel and all other work to ensure all the project tasks are completed on time, within budget and in accordance with state and federal laws, rules and regulations. 1.2 Progress reports and invoices will be submitted on a monthly basis. The progress report will show the progress for the month and the progress to date for each task, including budget status. 1.3 Due to delay in project schedule additional PMT meetings are anticipated. Project Management Team meetings will be held to confirm the basic project objectives, solidify a work plan, obtain consensus on project requirements, monthly project status and updates. PMT's will also be used to update the project layout and 30% Construction Plans. SRF Deliverables: - Monthly progress and status reports - Schedule monthly project managementteam meetings and other meetings as identified and needed. Prepare meeting minutes. - Coordinate activities with the county via phone, email and written correspondence - Submit invoices in a timely manner SUBTOTAL - TASK 1.0 Work Tasks and Person -Hour Estimates 'SRF 13725.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE 16 - - 10 - - - - - 26 $4,544.00 12 - - - - - - - - 12 $2,325.00 10 - - 15 - - - - - 25 $4,100.00 38 0 0 25 0 0 0 0 0 63 $10,972.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 3 of 12 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION 2.0 PRELIMINARY DESIGN Assumptions: - Construction limits will be included on the layout and considered 30%design. - Major drainage features will be shown on the layout and will include a storm sewer system along with any additional ponding or treatment requirements needed for the new curb & gutter/ boulevard section and future trail accommodations. - Layout with future trail will be developed to study with sufficient detail to understand impacts and costs. The single layout alternative will be based on the preferred concept based on PMT input and County decision. (Assumes no 3D element to layout, 2D only.) - No revisions to the CATEX document are anticipated. Future trail considerations will not be covered in the CATEX, design tables, typical sections or other required NEPA documents. Client Deliverables: - County authorize SRF to move forward with Amendment #2. - Countyto provide additional topographical survey shots along south side of CSAH 33 between TH 169 and Auburn St. (Previously completed and added to project files). - Countyto provide additional topographical survey shots along north side of CSAH 33 between Auburn St and Trott Brook (if deemed necessary) to coverthe proposed alignment shift for CSAH 33. - Review of updated graphics and documents, as necessary. 2.1 Review existing survey data and update existing 3D model to incorporate additional preliminary survey work. Update existing base files for project design. 2.2.1 Project Management- Environmental Document 2.2.11 Right-of-way. Recompute the number of parcels affected and amounts (permanent easements, permanent right-of-way, temporary easements) resultingfrom shifting CSAH 33 north. Update previous right-of-way impact figures. 2.2.15 Construction and Highway Traffic Noise. Review previous traffic noise analysis started in 2021 and make adjustments for proposed centerline shift east of Quincy Street. Assumes noise abatement measures do not meet MnDOT reasonableness or feasibility criteria. Noise wall solicitation not required. Work Tasks and Person -Hour Estimates 'SRF 13725.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE 2 4 1 4 1 - - 4 S 1 7 - 16 4 6 $72S.00 5 $S94.00 17 $2,070.00 24 $3,179.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 4 of 12 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION 2.2.16 Floodplain Management. Review FEMA floodplain map and determine additional floodplain impacts due to road shift and future trail grading, includingfill in wetlands in the floodplain. Update previous floodplain impactfigure. 2.2.20 Update geometric design tables, including existing and proposed typical sections to reflect urban section. (Assume no design exceptions and no future trail shown.) SRF Deliverables: - Revised preliminary alignment layout drawings for the selected study options as part of the CATEX document. - Revised Design Tables and Typical Sections - CATEX - Revised noise analysis - Updated Wetland Delineation graphics SUBTOTAL - TASK 2.0 Work Tasks and Person -Hour Estimates PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II 4 3 'SRF 13725.00 PROF.I TECH. SUPPORT TOTALS EST.FEE 4 - - S $996.00 4 - - 7 $S52.00 3 11 0 13 0 28 12 0 0 67 $8,719.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 5 of 12 SRF Consulting Group, Inc. Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION 3.0 DESIGN Assumptions: - Realignment of CSAH 33 (up toll feet north) is requested from 350 feet west of Auburn Street thru Smith Street and sections along the new corridor prior to the roundabout to accommodate the future trail along south side of CSAH 33. - Right of way linework needs to be updated for CSAH 33 centerline shift. - No intersection lighting required at side streets. - No trail surfacing or subbase (aggregate or bituminous) is planned. - An urban section consisting of curb and gutter along south edge of shoulder from approximately 350 feet west of Auburn Street east through the intersection of Quincy Street is planned for accommodating the future trail. Additional sections of urban (curb and gutter) are planned from approximately 100 feet of the planned cattle pass east to the roundabout. - Urban boulevard width will be a typical 5 feet measured from face of curb to the grading PI for the section of CSAH 33 from the TH 169 exit ramp east thru Quincy Street. - Trail is not carried anyfurtherthan a graphical representation (2D) - Additional stormwater treatment locations, including pond(s) will be reviewed to accommodate both the current project and future trail construction. Storm water treatment locations will be located and designed to provide flexibility for the current and future expansion abilities. - Adjust two previously proposed stormwater treatment ditches to accommodate road shift to the north. Proposed design does NOT account for treatment of future trail impervious. - No pedestrian ramps or ADA design are included forthe futuretrail. - Engineer's Estimate and Statement of Estimated Quantities (SEQ) will be expanded to provide separate quantity columns for County & City cost participation for CSAH 33 and separate column for County participation on CSAH 13. - No specific driveway design required for future trail considerations. SRF will cut sections at driveways for new CSAH 33 alignment and review driveway slopes for general conformity for future trail. Minor grade adjustments will be reviewed (if necessary) to facilitate the future trail as deemed reasonable with this project. - No modifications to the roundabout are included with this additional scope. - QC reviews are included in each task as necessary. - No bench will be graded into the back slope alongthe rural section east of Quincy Street forthe future trail. Work Tasks and Person -Hour Estimates PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. 'SRF 13725.00 SUPPORT TOTALS EST.FEE 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 6 of 12 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION Client Deliverables: - Review of 30% Plans (2nd submittal package) - Review of updated preliminary layout, cost estimates and memos associated with the future trail accommodation. - State Aid project number provided by City of Elk River 3.1.1 Provide additional project management including day to day check -ins with staffto assure project remains on the revised schedule due to additional of trail. 3.1.2 Provide design supportto assist with restartingthe CATEX document to reflect the changes to the project. 3.1.3 Receive additional topographical points and data (County to perform survey) along north project limits to update base files, and existing 3D model (if deemed necessary). 3.1.4 Review CSAH 33 alignment. Layout proposed 10-11 foot shift north from Auburn Street thru Smith Street and from Quincy Street east to the west channelization for the roundabout. Modify alignment to reflect final alignment. Coordinate alignment shift with County. 3.1.5 Update the geometry basefile to reflectthe proposed CSAH 33 shift. Update includes mainline, left bypass lanes, driveways, side street connections and other affected geometry. Update includes showingthe future trail location for schematical visual purposes only (no 3D design). Future trail will not be depicted on construction plans or cross sections. 3.1.6 Recut existing groundlines along newly established alignments for Auburn Street, Yale Street, Vance Street, Ulysses Street and Smith Street. 3.1.7 Review CSAH 33 profile based upon adjusted alignment. Areas of specific concern include at Ulysses Street (sight lines) and east of Quincy Street where CSAH 33 splits two residential driveways. (Assumes alignment shift is approved at 10 or 11 feet, onetime update.) 3.1.8 Extend alignments and update profiles for Auburn Street, Yale Street, Vance Street, Ulysses Street and Smith Street due to CSAH 33 alignment/profile shifts. 3.1.9 Recompute intersection sightlines at each intersection (excludes CSAH 13) due to alignment and profiles revisions. Make corrective updates deemed appropriated for alignment and/or profiles (mainline or side street). 3.1.10 Update Civil 3D models to incorporate urban typical section and 5-foot boulevard along south side of CSAH 33 from approximately 350 feet west of Auburn Street east to Quincy Street. 3.1.11 Update Civil 3D models to develop urban section from approximately 1OO feet west of cattle pass east to the roundabout. 3.1.12 Update proposed right of way linework in right of way basefile to reflect alignment shifts where appropriate. 3.1.13 Recut cross sections (existing groundlines and proposed) along revised alignment and profile. Review sections, make appropriate revisions or adjustments. Cut sections to plan sheets. Work Tasks and Person -Hour Estimates 'SRF 13725.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE 6 - - 20 - - - - - 26 $4,044.00 4 - - 4 - - 8 - - 16 $2,192.00 5 5 $720.00 4 - - 12 - - - - - 16 $2,504.00 - - - 6 - 8 - - - 14 $1,744.00 - - - 1 - 4 - - - 5 $584.00 2 - - 16 - - - - - 18 $2,692.00 - - - 2 - 8 - - - 10 $1,168.00 - - - 4 - 12 - - - 16 $1,896.00 - - - 8 - - - - - 8 $1,152.00 - - - 16 - - - - - 16 $2,304.00 - - - 1 - 4 - - - 5 $584.00 2 - - 16 - - - - - 18 $2,692.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 7 of 12 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION 3.1.14 Review driveway grades along both sides of CSAH 33 to accountfor shifted alignment and future trail along south side. Make appropriate adjustments to driveway grades as deemed necessary. 3.1.15 Stormwater/ Drainage design 3.1.15.1 Stormwater treatment ditch revisions 3.1.15.2 Catch basin spacing and storm sewer design to State Aid standards from 400 ft west of Auburn St. to Quincy St. 3.1.15.3 Catch basin spacing and storm sewer design (1,500 feet) to State Aid standards from 100 ft west of planned cattle pass to the proposed roundabout. 3.1.15.4 Prepare additional Drainage Quantities and Tabulations for 60%, 95%and 100% Plan submittals (beyond what was included for culverts in original scope). 3.1.15.5 Review drainage ditches and coordinate special ditch profiles. 3.1.15.6 Update Drainage Map for revisions and document future trail 3.1.16 Update previous 30% Construction Plans to incorporate revisions for future trail, storm sewer system and extended project limits to TH 169. Revised Sheets include updates or creating additional sheets for the following: Title Sheet General Layout Inplace Utility Tabulation Typical Sections Alignment Plans and Tabulations Topography and Utility Plans Construction Plan and Profile Profiles Drainage and Superovulation Plans Drainage Profiles, Tabulations and Details Storm Water Pollution Prevention Plan (SWPPP) Contour Plans Cross Sections 3.1.17 Prepare updated 30% Cost Estimate using SRF 1-pager cost estimate tool. 3.1.1E Perform a QC check of revised 30% Plan package (plans and cost estimate), document comments and complete recommended corrections. 3.1.19 Submit 30% Construction Plans to County and City for review and comment.(PDF document) 3.1.20 Receive 30% review comments from County and City, update Comment Resolution tracking document. Respond to comments. 3.1.21 Additional quantities, documentation and effort to tabulate quantities will be required, beyond the original Contract, for County and City cost participation. Items include but are not limited to: mobilization, earthwork, storm sewer and temporary easements. 3.1.22 Prior/ ongoing design services to review project corridor for the trail, update geometry file, update layout, update typical sections, update Civil 3D templates for urban trail and process cross sections. Prepare cost estimates, prepare for and attend client meetings to discuss trail, prepare trail memo to document trail decision making process and detailed design elements. Work Tasks and Person -Hour Estimates PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I 4 S 'SRF 13725.00 TECH. SUPPORT TOTALS EST.FEE 12 $1,456.00 3 - - - 13 - - 15 - 31 $3,964.00 10 - - - 32 - - 70 - 112 $14,165.00 3 - - - S - - 10 - 21 $2,754.00 2 - - - 6 - - 17 - 25 $3,135.00 2 - - 4 12 - - - - 18 $2,452.00 - - - - 1 - - 2 - 3 $360.00 3 - - 20 - 40 20 - - S3 $9,962.00 1 - - 4 - S - - - 13 $1,650.00 4 - - 4 - 6 - - - 14 $2,012.00 - - - 2 - 4 - - - 6 $725.00 2 - - 6 - 4 - - - 12 $1,692.00 - - - S - 20 - - - 2S $3,352.00 40 - - 100 - 12 - - - 152 $23,45O.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/30/2022 SRF Consulting Group, Inc. Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION 3.1.23 Prepare Amendment#2 for additional design scope for future trail planning. 3.1.24 Update project layout including color file, typical sections and notes for use with Public Open House No. 2. Future trail will be depicted on layout for public comment. Provide QC check of layout, make recommended revisions, submit to County and City for review. 3.1.25 Update Infraworks model and fly through for public open house #2. 3.1.25.1 Update Infraworks model and hatchingfor shifted alignment. Prep model for usage by video experts. Future trail will not be modeled in 3D and construction limits will be based upon current proposed construction, not future trail impacts. 3.1.25.2 Video editing, sync timing, review video and final edits. Coordinate depiction of future trail overlaid on Infraworks model. 3.1.26 Update overall project schedule to reflect additional design work detailed above to incorporate future trail and accountfor schedule delays due to trail decision process. 3.2.2 Revise previous wetland delineation graphics to reflectthe proposed shifted alignment of CSAH 33. Coordinate with TEP panel on revised graphics and confirm if additional review is required. If additional review needed, resubmit previous wetland delineation report for TEP panel sign off. SRF Deliverables: - Revised 30%Construction Plans and Estimate (pdf) -Amendment #2 - Revised Project Layout& Drainage Area Map - Revised Intersection Sight Distance calculations - Infraworks Fly-Thru video (updated) - Additional/revised wetland delineation graphics SUBTOTAL - TASK 3.0 4.0 RIGHT OF WAY ACQUISITION Assumptions: - No additional right of way parcels required for proposed centerline of CSAH 33 north. Client Deliverables: None 4.1 No tasks required. SRF Deliverables: None SUBTOTAL - TASK 4.0 Exhibit B-1 Work Tasks and Person -Hour Estimates Page 8 of 12 'SRF 13725.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE 24 - - 10 - - - - - 34 $6,096.00 2 - - 6 - 14 - - - 22 $2,792.00 1 - - 16 - 4 - - - 21 $2,93S.00 1 6 - - - - - - 6 13 $1,934.00 4 - - 20 - - - - - 24 $3,656.00 - 4 - - - - 4 - - S $1,120.00 120 10 0 0 0 315 0 0 72 156 0 0 32 114 0 0 6 825 $113,980.00 - 0 $0.00 0 0 $0.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 9 of 12 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION 5.0 BRIDGE DESIGN Assumptions: - Bridge (box culvert) station/location remains unchanged. - Overall length of bridge (box culvert) is not anticipated to change with future trail consideration. Client Deliverables: None 5.1 Review bridge (box culvert) geometrics to accommodate future trail with urban typical section on south side of CSAH 33. SRF Deliverables: - Updated CAD base files. SUBTOTAL - TASK 5.0 Work Tasks and Person -Hour Estimates 'SRF 13725.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE 4 4 $576.00 0 0 0 4 0 0 0 0 0 4 $576.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 10 of 12 SRF Consulting Group, Inc. Work Tasks and Person -Hour Estimates Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) ` �� Amendment No. 2 - Future Trail / Storm Sewer Design J Subconsultants: 13725.00 TASK NO. TASK DESCRIPTION PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE 6.0 CATTLE PASS DESIGN Assumptions: - Cattle pass located at CSAH 33 STA. 177+00 - Review current design for cattle pass based upon proposed urban section and future trail widths. Determine if modifications are needed from current design. - Cattle pass alignment will not be impacted with proposed curb and gutter section. Client Deliverables: None 6.1 Review cattle pass geometrics and profile to accommodate future trail with - - - - - - - - - 0 $0.00 possible urban typical section on south side of CSAH 33. 6.2 Cross section review, coordinate with roadway drainage design / treatment - - - 1 - - - 4 - 5 $616.00 elements to incorporate proposed trail along south side of CSAH 33. 6.3 Revise ditch profiles and cross section updates necessary to incorporate the future - - - 2 - - 4 2 - S $944.00 trail and modified cattle pass into proposed surface model and plans. SRF Deliverables: - Incorporation of cattle pass modification details into plans SUBTOTAL-TASK6 0 0 0 3 0 0 4 6 0 13 $1,560.00 7.0 TROTT BROOK HYDRAULIC DESIGN Assumptions: - Extending proposed box culvert at Trott Brook not required for grading location of future trail using a urban typical section on south side of CSAH 33. Client Deliverables: None 7.1 Confirm hydraulic modeling previously developed correctly reflects accommodating 1 2 - - - - 4 - - 7 $964.00 the future trail by extendingthe urban section to the south side of CSAH 33. SRF Deliverables: -None SUBTOTAL - TASK 7 1 2 0 0 0 0 4 0 0 7 $964.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 11 of 12 SRF Consulting Group, Inc. Work Tasks and Person -Hour Estimates Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) ` �� Amendment No. 2 - Future Trail / Storm Sewer Design J Subconsultants: 13725.00 TASK NO. TASK DESCRIPTION PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE Software Version Deliverables SRF will utilize the current version of the software deemed at the start of the project. SRF will assess the need to upgrade software versions based on the software vendors User License Agreement and the viable upgrade path for existing project content. In the event that a specific CAD or other software version is required per deliverables specified in a contract for services, SRF shall comply with the specified version provided that the specified version may not conflict with SRF's contractual obligation to its software vendors regarding the supported software versions at the time of delivery. In the case of conflict between contractual obligations and software vendors User License Agreement, the vendor supported version will be delivered to the client and SRF will notify the client in writing of the software version that will be utilized prior to delivery. If there are associated costs, SRF will identify the costs and the additional costs will be mutually agreed upon. TOTAL ESTIMATED PERSON -HOURS 162 23 0 360 72 184 52 120 6 979 AVERAGE HOURLY BILLING RATE $194.00 $175.00 $150.00 $144.00 $124.00 $110.00 $105.00 $115.00 $115.00 ESTIMATED LABOR AND OVERHEAD $31,425.00 $4,025.00 $0.00 $51,54O.00 $S,92S.00 $20,240.00 $5,460.00 $14,160.00 $690.00 $136,771.00 SRF ESTIMATED DIRECT NON -SALARY EXPENSES $0.00 SUBTOTAL: (SRF Labor and Expenses) $136,771.00 SUBCONSULTANTS: $0.00 TOTAL ESTIMATED FEE (SRF and Subconsultants combined) $136,771.00 SRF ESTIMATE OF DIRECT NON -SALARY EXPENSES: MILEAGE: Personal Vehicles 0 Miles@ $O.5S5 $0.00 SUBCONSULTANTS: SRF EXPENSES: $0.00 SUBOONSULTANTS: $0.00 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-1 Page 12 of 12 SRF Consulting Group, Inc. Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 2 - Future Trail / Storm Sewer Design Subconsultants: TASK NO. TASK DESCRIPTION Work Tasks and Person -Hour Estimates 'SRF 13725.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS EST. FEE SUMMARYOFCOSTS: PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS 1 PROJECT MANAGEMENT $ 7,372.00 $ - $ - $ 3,600.00 $ - $ - $ - $ - $ - $10,972.00 2 PRELIMINARY DESIGN $ 582.00 $ 1,925.00 $ - $ 1,872.00 $ - $ 3,080.00 $ 1,260.00 $ - $ - $8,719.00 3 DESIGN $ 23,280.00 $ 1,750.00 $ - $ 45,360.00 $ 8,928.00 $ 17,160.00 $ 3,360.00 $ 13,452.00 $ 690.00 $113,980.00 4 RIGHT OF WAYACQUISITION $ - $ - $ - $ - $ - $ - $ - $ - $ - $0.00 5 BRIDGE DESIGN $ - $ - $ - $ 576.00 $ - $ - $ - $ - $ - $576.00 6 CATTLE PASS DESIGN $ - $ - $ - $ 432.00 $ - $ - $ 420.00 $ 708.00 $ - $1,560.00 7 TROTT BROOK HYDRAULIC DESIGN $ 194.00 $ 350.00 $ - $ - $ - $ - $ 420.00 $ - $ - $964.00 TOTALS $31,428.00 $4,025.00 $0.00 $51,840.00 $8,928.00 $20,240.00 $5,460.00 $14,160.00 $690.00 $136,771.00 SUMMARY OF HOURS: PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT TOTALS 1 PROJECT MANAGEMENT 38 - - 25 - - - - - 63 2 PRELIMINARY DESIGN 3 11 - 13 - 28 12 - - 67 3 DESIGN 120 10 - 315 72 156 32 114 6 S25 4 RIGHT OF WAYACQUISITION - - - - - - - - - 0 5 BRIDGE DESIGN - - - 4 - - - - - 4 6 CATTLE PASS DESIGN - - - 3 - - 4 6 - 13 7 TROTT BROOK HYDRAULIC DESIGN 1 2 - - - - 4 - - 7 TOTALS 162 23 0 360 72 184 52 120 6 979 13725 Amd_2_Rev3.alsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-3 Page 1 of 3 SRF Consulting Group, Inc. Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 3 - Future Trail / Drainage Design Subconsultants: TASK NO. SUMMARY OF TASKS 3.0 DESIGN Work Tasks and Person -Hour Estimates 'SRF Project Overview: Amendment No. 3 Provide additional design services to shift previously approved alignment of CSAH 33 north approximately 10 feet to provide additional area along south side for a future 10-foot trail. Update project to include a urban section with curb and gutter along south side from approximately 350 feet west of Auburn Street east thru Quincy Street. Design will include constructing an urban section (with curb and gutter and storm sewer) from approximately 100 feet west of the planned cattle pass, under CSAH 33, east over Trott Brook and connect into the proposed curb and gutter atthe roundabout. Revise stormwater design to incorporate a storm sewer system, potential pond ing/stormwater treatment and accommodations for future trai Task numbers correspond to original Work Scope task numbering. Hours for Task 3.15 for Drainage Design reflect a 50/50 split with Clty of Elk River per cost share agreement. 13725.00 13725 Amd 3.xlsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-3 Page 2 of 3 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 3 - Future Trail / Drainage Design Subconsultants: Assumptions: - Realignment of CSAH 33 (up to 11 feet north) is requested from 350 feet west of Auburn Street thru Smith Street and sections alongthe new corridor prior to the roundaboutto accommodate the future trail along south side of CSAH 33. - No trail surfacing or subbase (aggregate or bituminous) is planned. - An urban section consisting of curb and gutter along south edge of shoulder from approximately 350 feet west of Auburn Street east through the intersection of Quincy Street is planned for accommodating the future trail. Additional sections of urban (curb and gutter) are planned from approximately 100 feet of the planned cattle pass easttothe roundabout. - Urban boulevard width will be a typical 5 feet measured from face of curb to the grading PI for the section of CSAH 33 from the TH 169 exit ramp east thru Quincy Street. - Additional stormwater treatment locations, including pond(s) will be reviewed to accommodate both the current project and future trail construction. Stormwater treatment locations will be located and designed to provide flexibility for the current and future expansion abilities. - Adjust two previously proposed stormwater treatment ditches to accommodate road shiftto the north. Proposed design does NOT account for treatment of future trail impervious. - QC reviews are included in each task as necessary. - No bench will be graded into the back slope alongthe rural section east of Quincy Street for the future trail. Client Deliverables: - Review of 30% Plans (2nd submittal package) - Review of updated preliminary layout, cost estimates and memos associated with the future trail accommodation. 3.1.15 Stormwater/ Drainage design 3.1.15.1 Stormwater treatment ditch revisions 3.1.15.2 Catch basin spacing and storm sewer design to State Aid standards from 400 ft west of Auburn St. to Quincy St. 3.1.15.3 Catch basin spacing and storm sewer design (1,500 feet) to State Aid standards from 100 ft west of planned cattle pass to the proposed roundabout. 3.1.15.4 Prepare additional Drainage Quantities and Tabulations for 60%, 95%and 100% Plan submittals (beyond what was included for culverts in original scope). 3.1.15.5 Review drainage ditches and coordinate special ditch profiles. 3.1.15.6 Update Drainage Map for revisions and document future trail SRF Deliverables: - Revised Project Layout& Drainage Area Map - Drainage Plan Sheets SUBTOTAL - TASK 3.0 Work Tasks and Person -Hour Estimates 'SRF 13725.00 2 - - - 12 - - 15 - 29 $3,646.00 10 - - - 33 - - 70 - 113 $14,292.00 3 - - - S - - 10 - 21 $2,754.00 2 - - - 6 - - 17 - 25 $3,13S.00 2 - - 4 12 - - - - 13 $2,452.00 - - - - 1 - - 2 - 3 $360.00 19 0 0 4 72 0 0 114 0 209 $26,642.00 13725 Amd 3.xlsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN 6/302022 Exhibit B-3 Page 3 of 3 SRF Consulting Group, Inc Client: Sherburne County Project: CSAH 33 Auburn Street to CSAH 13 (Twin Lakes Road) Amendment No. 3 - Future Trail / Drainage Design Subconsultants: Work Tasks and Person -Hour Estimates 'SRF 13725.00 TOTAL ESTIMATED PERSON -HOURS 19 0 0 4 72 0 0 114 0 209 AVERAGE HOURLY BILLING RATE $194.00 $175.00 $150.00 $144.00 $124.00 $110.00 $105.00 $115.00 $115.00 ESTIMATED LABOR AND OVERHEAD $3,656.00 $0.00 $0.00 $576.00 $S,92S.00 $0.00 $0.00 $13,452.00 $0.00 $26,642.00 SRF ESTIMATED DIRECT NON -SALARY EXPENSES $0.00 SUBTOTAL: (SRF Labor and Expenses) $26,642.00 SUBCONSULTANTS: $0.00 TOTAL ESTIMATED FEE (SRF and Subconsuttants combined) $26,642.00 SRF ESTIMATE OF DIRECT NON -SALARY EXPENSES: MILEAGE: Personal Vehicles 0 Miles@ $O.5S5 $0.00 SUBCONSULTANTS: SUMMARY OF COSTS: 3 DESIGN TOTALS SUMMARY OF HOURS: 3 DESIGN TOTALS SRF EXPENSES: $0.00 SUBOONSULTANTS: $0.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT $ 3,656.00 $ - $ - $ 576.00 $ S,92S.00 $ - $ - $ 13,452.00 $ - $3,686.00 $0.00 $0.00 $576.00 $8,928.00 $0.00 $0.00 $13,452.00 $0.00 PROF. VIII-VII PROF. VI PROF. V PROF. IV PROF. III PROF. II PROF. I TECH. SUPPORT 19 - - 4 72 - - 114 - 19 0 0 4 72 0 0 114 0 TOTALS $26,642.00 $26,642.00 TOTALS 209 209 13725 Amd 3.xlsx SRF CONSULTING GROUP, INC. MINNEAPOLIS. MN