9.4 SR 10-17-2022Request for Action
To
Item Number
Mayor and City Council
9.4
Agenda Section
Meeting Date
Prepared by
Work Session
October 17, 2022
Lori Ziemer, Finance Director
Item Description
Reviewed by
2023-2027 Capital Improvement Plan
Cal Portner, City Administrator
Reviewed by
Action Requested
Review the 2023-2027 Capital Improvement Plan.
Background/Discussion
Staff has identified specific capital projects, estimated project costs and funding sources to be completed over the
next five years. Projects listed for 2023 will be reviewed along with cash flow estimates of the associated project
fund. Projects are reviewed annually and updated with the CIP.
Capital Reserve Fund
The purchase and replacement of IT hardware/software has been funded by excess General Fund fund balance.
The current balance designated for the replacement of IT technology is about $657,000. In addition, the fund
receives interest income and cable franchise fees to be used for miscellaneous capital outlay items. The
undesignated balance of the fund is about $959,000.
Equipment Replacement Fund
Established to provide funding for the planned replacement of vehicles and mobile equipment, the majority of
funding is provided through annual General Fund department charges and Local Government Aid (LGA). LGA
comes from the state general fund dollars that are collected through sales and income taxes and can be subject to
state unallotment. Department charges are based on the amortization of their respective equipment and updated
annually. The Fleet Committee evaluates the replacement of vehicles and equipment based on the criteria of age,
miles/hours, maintenance costs, and usage type. The 2023-2027 vehicle/equipment purchase requests were
reviewed and recommended by the Fleet Committee.
Government Building Fund
Used for municipal building construction/maintenance, landscaping, and remodeling. The facilities maintenance
supervisor and department directors identify needed building improvements which are updated annually. The
landfill expansion fee and interest earnings are the primary funding sources. The landfill expansion fee is
scheduled to expire in 2030 but is expected to end as early as 2027-2028 based on landfill capacity. The fund has
covered debt service payments for the public works building since 2012 and will also cover the 2023 debt service.
Park Dedication Fund
Recent plat development activity has increased fund revenues to a cash balance of about $1,593,000 as of
9/30/22. Projects planned for 2023 include YAC shade structure and maintenance garage, and a security camera
for the Rivers Edge dock.
The Elk River Vision P 0 W E e E 0 0 V
A welcoming community rvitb revolutionary and spirzted resourcefulness, exceptional INATUREJ
service, and community engagement that encourages and inspires prosperz1 Updated. August 2020
Park Improvement Fund
Funds the replacement and maintenance of park amenities with an annual $250,000 transfer from the Liquor
Fund. The projects identified by the Parks & Recreation Commission for 2023 include the athletic fields master
plan, Lions Park playground, and Woodland Trails storage garage.
Pavement Management Fund/MSA
A franchise fee on gas and electric utilities is the primary ongoing revenue source to provide long-term funding
for the pavement management program. Municipal State Aid (MSA) is also utilized to fund portions of various
street improvement projects. The maintenance portion (25%) of MSA offsets the cost of the sealcoating and
smaller overlay preventative maintenance projects. MnDOT's transportation funding allotment for 2023 will be
about $1,766,000.
Trunk Utility Fund
This fund consists of special assessment revenue from sewer and water improvement projects. The funds will be
used on trunk sewer improvement projects in lieu of having to issue bonds on future system expansion /
improvements. No projects are identified for 2023.
Funding Yet to be Determined
Capital items or projects pending review that do not have an associated funding source identified.
Other Funds
Projects listed for 2023 that are associated with budgeted funds such as FTCenter, Liquor, Sewer, and Stormwater
have been reviewed during budget work sessions or already approved by Council.
Financial Impact
N/A
Mission/Policy/Goal
Identify funding to develop a sustainable and prosperous community.
Attachments
■ 2023-2027 Capital Improvement Plan
N:APublic Bodies\Agenda Packets\ 10- 1 7-2022\ Final\ x9.4 sr CIP.docx
City of Elk River, Minnesota
Capital Improvement Plan
2023 thm 2027
PROJECTS BY FUNDING SOURCE
Source Project # 2023 2024 2025 2026 2027 Total
Capital Reserve - IT
2023 Technology Upgrades
TC-23
2024 Technology Upgrades
TC-24
2025 Technology Upgrades
TC-25
2026 Technology Upgrades
TC-26
2027 Technology Upgrades
TC-27
Capital Reserve - IT Total
Ca ital Reserve - Undesi mated
Financial Software
TFN-01
Capital Reserve - Undesignated Total
Equipment Replacement Fund
Facilities Maintenance - Vehicles
BM-01
Building Safety -Vehicles
BZ-01
Fire - Vehicles
FD-01
Fire - Trucks
FD-02
Police - Patrol Squads
PD-01
Police - Unmarked Squads
PD-02
Police - CSO Vehicles
PD-03
Parks - Pickup Trucks
PK-01
Parks - Mobile Equipment
PK-02
Streets - Pickup Trucks
ST-01
Streets - Dump Trucks
ST-02
Streets - Mobile Equipment
ST-03
Equipment Replacement Fund Total
ERMU
Phone System
BL-10
2023 Technology Upgrades
TC-23
2024 Technology Upgrades
TC-24
2025 Technology Upgrades
TC-25
2026 Technology Upgrades
TC-26
2027 Technology Upgrades
TC-27
ERMU Total
Federal Grant
Kelley Pkwy/Twin Lakes Rd(TH 10 Intersection
11-08
Trail Development
PF-64
2023-2027 CAPITAL IMPROVEMENT PLAN
71,600
71,600
103,000
103,000
92,400
92,400
70,000
70,000
57,000
57,000
71,600 103,000 92,400 70,000 57,000
394,000
200,000
200,000
200,000
200,000
160,000
80,000
240,000
40,000
40,000
50,000
50,000
52,000
52,000
104,000
195,000
325,000
195,000
65,000
65,000
845,000
130,000
80,000
40,000
80,000
330,000
53,000
53,000
53,000
159,000
260,000
50,000
180,000
55,000
545,000
90,000
115,000
105,000
84,000
142,000
536,000
230,000
220,000
70,000
125,000
645,000
265,000
270,000
535,000
14,000
370,000
219,000
495,000
139,000
1,237,000
1,449,000
1,133,000
1,354,000
739,000
591,000
5,266,000
36,000 36,000
25,400 25,400
2,000 2,000
15,600 15,600
5,000 5,000
3,000 3,000
25,400 2,000 51,600 5,000 3,000 87,000
2,000,000 2,000,000
830,000 830,000
Source Project# 2023 2024 2025 2026 2027 Total
Federal Grant Total 830,000 2,000,000 2,830,000
FTCenter
FTCenter - Zamboni -Approved 5/2/22
FTC-02
202,000
202,000
FTCenter Total
202,000
202,000
Government Buildings
City Hall - Roof Replacement
BL-01
1,000,000
1,000,000
Public Safety Building - Roof Replacement
BL-02
800,000
800,000
Public Safety Building - Indoor Range
BL-04
150,000
150,000
Trott Brook Barn - RoofMindows Replacement
BL-06
40,000
40,000
Phone System
BL-10
144,000
144,000
Government Buildings Total
1,990,000
144,000
2,134,000
Li uor Fund - Reviewed with budget
Northbound Liquor - Monument Sign
LS-01
80,000
80,000
Liquor Fund Total
80,000
80,000
MnDOT Cooperative Funds
Kelley Pkwy/Twin Lakes Rd(TH 10 Intersection
11-08
1,000,000
1,000,000
MnDOT Cooperative Funds Total
1,000,000
1,000,000
Municipal State Aid
Hwy 169 Frontage/Backage Road Improvements
11-01
750,000
750,000
Kelley Pkwy/Twin Lakes Rd(TH 10 Intersection
11-08
3,000,000
3,000,000
County Projects - Cost Share
11-20
1,520,000
1,520,000
Trail Development
PF-64
450,000
450,000
Municipal State Aid Total
1,970,000
3,750,000
5,720,000
Park Dedication
County Projects - Cost Share
11-20
250,000
250,000
YAC - Park Accessories
PDF 23-1
202,000
202,000
Rivers Edge Dock - Camera System
PDF 23-2
9,100
9,100
Ninja/Fitcore Playground
PDF 24-1
280,000
280,000
Trail Development
PF-64
370,000
370,000
Park Dedication Total
211,100
900,000
1,111,100
Park Improvement
Athletic Field Master Plan
PIF 23-1
45,000
45,000
Playground - Lions Park
PIF 23-2
200,000
200,000
Park Improvement - Miscellaneous
PIF 23-27
25,750
16,250
16,250
16,250 10,000 84,500
Storage Garage - Woodland Trails
OF 23-4
150,000
150,000
Playgrounds - Country Crossing/Trott Brook
OF24-1
250,000
250,000
Basketball Court - Kliever Lake Fields
PIF 24-2
50,000
50,000
Basketball Courts - Deerfield/Ridgewood
PIF 25-1
80,000
80,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Source Project # 2023 2024 2025 2026 2027 Total
Nature Play - Woodland Trails
PIF 25-2
75,000
75,000
Playground/Basketball Court - Riverplace
PIF26-1
185,000
185,000
Lions Park Shelters
PIF 26-2
300,000
300,000
Playgrounds - Fresno/Mississippi Oaks
PIF 27-1
190,000
190,000
Rivers Edge Park Fountain
PIF 27-2
75,000
75,000
Park Improvement Total
420,750
316,250
171,250
501,250
275,000
1,684,500
Pavement Mana ement
Hwy 169 Frontage/Backage Road Improvements
II-01
750,000
750,000
169 Redefine
11-03
1,507,000
1,507,000
County Projects - Cost Share
II-20
750,000
750,000
Pavement Management - Streets
PM-01
3,850,000
300,000
3,600,000
300,000
3,000,000
11,050,000
Pavement Management - ParkingLots/Trails
PM-02
350,000
200,000
350,000
200,000
350,000
1,450,000
Pavement Management Total
4,200,000
2,757,000
4,700,000
500,000
3,350,000
15,507,000
Sewer Fund - Reviewed with budget
Wastewater - Vehicle
WW-06
65,000
65,000
Wastewater - Equipment
WW-12
30,000
200,000
230,000
Wastewater - Lift Station Improvements
WW-19
146,000
55,000
55,000
55,000
55,000
366,000
Wastewater- Clarifier Lining
WW-20
90,000
90,000
Wastewater- Urban Services Expansion
WW-23
13,350,000
13,350,000
Wastewater -Centrifuge Installation
WW-24
6,000,000
6,000,000
Sewer Fund Total
266,000
120,000
13,405,000
255,000
6,055,000
20,101,000
Special Assessments
Kelley Pkwy/Twin Lakes Rd/TH 10 Intersection
II-08
500,000
500,000
Special Assessments Total
500,000
500,000
Storm Water - Reviewed with budget
Pavement Management - Streets
PM-01
50,000
100,000
150,000
Stormwater Projects
STW-1
250,000
250,000
500,000
Morton Ave Drainage Improvements
STW-2
250,000
250,000
Storm Water Total
550,000
350,000
900,000
Trunk Utility Fund
169 Redefine
11-03
1,000,000
1,000,000
Wastewater - Urban Services Expansion
WW-23
16,850,000
16,850,000
Trunk Utility Fund Total
1,000,000 16,850,000
17,850,000
Yet To Be Determined
Fire - Engines/Ladders
FD-03
2,000,000
800,000
2,800,000
Fire - Burn Building
FD-07
500,000
500,000
Business Center Drive Extension - Pending
II-35
700,000
700,000
Yet To Be Determined Total
3,200,000
800,000
4,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Source Project# 2023 2024 2025 2026 2027 Total
GRAND TOTAL 12,865,850 9,131,250 45,168,250 2,070,250 10,331,000 79,566,600
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 thm 2027
PROJECTS BY FUNDING SOURCE
Source Project# 2023 2024 2025
TC-23
2023 Technology Upgrades
2024 Technology Upgrades
TC-24
2025 Technology Upgrades
TC-25
2026 Technology Upgrades
TC-26
2027 Technology Upgrades
TC-27
Capital Reserve - IT Total
ICapital Reserve - Undesignated
Financial Software TFN-01
Capital Reserve - Undesignated Total
GRAND TOTAL
71,600
103,000
71,600 103,000
200,000
200,000
271,600 103,000
2026 2027
Total
71,600
103,000
92,400 92,400
70,000 70,000
57,000 57,000
92,400 70,000 57,000 394,000
200.000
200,000
92,400 70,000 57,000 594,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River
Technology/Software Improvements
Expenditures
2023
2024
2025
2026
2027
Total
Voice server
25,000
25,000
Simplivity server node
52,000
52,000
Fiber switch
20,000
20,000
Security camera system replacement
60,000
30,000
90,000
Mobile management system
25,000
25,000
Meraki licenses
20,000
20,000
Enter rise backup system
42,000
42.000
Microsoft server upgrade
30,000
30,000
Email archiver,s am, ATP
36,000
36,000
Phone system replacement
180,000
180,000
Enterprise backup system
25,000
25,000
DSX upgrades
50,000
50,000
Meraki switch upgrades
30,000
30,000
Total Expenditures
97,000
105,000
288,000
75,000
60,000
625,000
Funding Sources:
Capital Reserve -IT
71,600
103,000 1
92,400
70,000
57,000
394 000
Government Building
-
-
144,000
-
-
144,000
ERMU cost share)
25,400
2,000
51,600
5,000
3,000
87,000
Total
97,000
105,000
288,000
75,000
60,000
625,000
2023 thru 2027
Department Finance
City of Elk River, Minnesota Contact Finance Director
Project # TFN-01 Type Technology
Useful Life Unassigned
Project Name Financial Software Category Software
Description
Update financial software to improve technology efficiences, structured workflows, and integration flexibility with other applications
Justification
Me current financial software is approaching 15 years old and is in need of updating to take advantage of newer technology enhancements and
workflows to improve efficiencies in the financial management of the city.
Expenditures 2023 2024 2025 2026 2027 Total
Software/Hardware 200,000 200,000
Total 200,000 200,000
Funding Sources
Capital Reserve-Undesignated
2023
200,000
2024
2025 2026
2027 Total
200,000
Total 200,000 200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 thm 2027
PROJECTS BY FUNDING SOURCE
Source Project# 2023 2024 2025
Equipment Replacement Fund
Facilities Maintenance - Vehicles
BM-01
Building Safety -Vehicles
BZ-01
Fire - Vehicles
FD-01
Fire - Trucks
FD-02
Police - Patrol Squads
PD-01
Police - Unmarked Squads
PD-02
Police - CSO Vehicles
PD-03
Parks - Pickup Trucks
PK-01
Parks - Mobile Equipment
PK-02
Streets - Pickup Trucks
ST-01
Streets - Dump Trucks
ST-02
Streets - Mobile Equipment
ST-03
Equipment Replacement Fund Total
GRAND TOTAL
2026 2027 Total
160,000
80,000
240,000
40,000
40,000
50,000
50,000
52,000
52,000
104,000
195,000
325,000
195,000
65,000
65,000
845,000
130,000
80,000
40,000
80,000
330,000
53,000
53,000
53,000
159,000
260,000
50,000
180,000
55,000
545,000
90,000
115,000
105,000
84,000
142,000
536,000
230,000
220,000
70,000
125,000
645,000
265,000
270,000
535,000
14,000
370,000
219,000
495,000
139,000
1,237,000
1,449,000
1,133,000
1,354,000
739,000
591,000
51266,000
1,449,000
1,133,000
1,354,000
739,000
591,000
5,266,000
2023-202 7 CAF11 L drLiPAUVE7 ENE PLAN
City of Elk River
Equipment Replacement Fund
Beginning Cash Balance
Revenues:
Revenues from charges
Local Government Aid
Interest earnings
Other revenues (sale of assets/misc)
Total Revenues
Expenditures:
Capital Equipment -
Police
Fire
Parks
Streets
Facilities Maintenance
Building Safety
Total Expenditures
Revenues overl(under) Expenditures
Ending Cash Balance
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$1,289,726
$766,312
$647,812
$355,812
$727,812
436,500
471,000
509,000
550,000
594,000
466,586
478,000
490,000
502,000
515,000
22,500
15,500
13,000
9,000
18,000
50.000
50.000
50,000
50,000
50.000
975,586
1,014,500
1,062,000
1,111,000
1,177,000
428,000
378,000
328,000
105,000
145,000
52,000
-
102,000
-
-
350,000
165,000
285,000
139,000
142,000
509,000
590,000
559,000
495,000
264,000
160,000
-
80,000
-
-
-
-
-
-
40,000
1,499,000
1,133,000
1,354,000
739,000
591,000
(523,414)
(118,500)
(292,000)
372,000
586,000
$766,312
$647,812
$355,812
$727,812
$1,313,812
2023 Equipment Purchases
No.
Unit #
Old Description
Department
New Vehicle Description
Est. Cost
1
373
2001 Ford F250 Pickup
Facilities Maint.
Ford F250
$50,000
2
372
2008 Ford F350
Facilities Maint.
Ford F350
$60,000
3
Addition
Facilities Maint.
Ford F250
$50,000
4
601
2017 Ford Utility
Police - Patrol
Ford Utility Hybrid
$65,000
5
605
2016 Ford Taurus
Police - Unmarked
Chevrolet Traverse
$40,000
6
612
2014 Ford Utility
Police - CSO
Ford Utility Hybrid
$53,000
7
623
2017 Ford Utility
Police - Patrol
Ford Utility Hybrid
$65,000
8
624
2014 Ford Utility
Police - Unmarked
Chevrolet Traverse
$50,000
9
627
2015 Chevrolet Equinox
Police - Unmarked
Chevrolet Traverse
$40,000
10
628
2018 Ford Utility
Police - Patrol
Ford Utility Hybrid
$65,000
11
411
2004 Ford F350 Grass #3
Fire.
Ford F350
$52,000
12
732
2009 JD Tractor 5095
Parks
Tractor
$90,000
13
742
2001 Chevrolet 1500
Parks
Pickup Truck
$50,000
14
748
2007 GMC 1-Ton
Parks
Pickup Truck
$60,000
15
749
2005 Chev Silverado 2500
Parks
Pickup Truck
$50,000
16
751
2008 Ford F250
Parks
Pickup Truck
$50,000
17
Addition
Parks
Pickup Truck
$50,000
18
87
2008 Crafco Pavement Router
Streets
Pavement Router
$14,000
19
122
2008 Ford F250
Streets
Pickup Truck
$50,000
20
124
2002 Dodge Ram 1500
Streets
Pickup Truck
$50,000
21
237
2007 International Dump Truck
Streets
Dump Truck
$265,000
22
239
2008 Ford F550
Streets
1-Ton Truck
$70,000
23
248
1988 Ford F350
Streets
Pickup Truck
$60,000
TOTAL
$1,449,000
2022 order cancelled
2022 order cancelled
2022 order cancelled
022 order cancelled
2021 order cancelled
2021 order cancelled
2021 order cancelled
Department /
Unit #
Year
Description (MfrlModel)
2023-2027 Equipment Re lacement
2023
2024
1 2025
2026
2027
FACILITIES
MAINT
$160,000
$0
$80,000
$0
$0
370
2012
Ford F350 Utility Pickup
$60,000
372
2008
Ford XL F350
$60,000
373
2001
Ford F250
$50,000
374
2004
JD Gator
$20,000
377
Ford F250
$50,000
FABS
$0
$0
$0
$0
$40,000
511
2015
GMC Sierra 1500
$40,000
FIRE
$52,000
$2,000.000
$002,000
$0
$0
401
2015
Chevrolet Tahoe [Fire Chief}
$50,000
411
2004
Ford F350 Grass #3
$52,000
412
2006
Ford F350 Grass #4
1 $52,000
PARKS
$360,000
$165,000
$286,000
$139,000
$142,000
700
2014
Cat 257D Skid Steer w/Tracks
$90,000
701
1988
SnowScoot- Yellow Hillside
$12,000
702
1988
Snow Scoot - Red Hillside
$12,000
714
2012
Bombardier Ski-Doo Skandic
$15,000
715
2014
Ski-Doo Skandic 600 SWT
$15,000
718
2003
Suzuki 4x4 ATV
$14,000
719
2003
Suzuki 4x4 ATV
1
$14,000
722
2017
Toro Z-Master Zero Turn Mower
$17,000
723
2017
Toro Groundsmaster 5910 Wide Area
$125,000
728
2015
John Deere Zero Turn Mower
$17,000
729
Ford F250
$50,000
730
2015
Kromer Field Commander B100
$45 000
731
2009
Chev Silverado 250OHD
$50,000
732
2009
John Deere Tractor 5095
$90,000
738
2012
John Deere Tractor 4720
$70,000
742
2001
Chevy 1500
$50,000
743
2011
GMC 2500 HD
$55,000
745
2012
GMC Sierra Picku , 3500
$60,000
746
2011
Ford F550
$70,000
748
2007
GMC 3500 1-Ton
$60,000
749
2005
Chevrolet Silverado 2500
$50,000
751
2008
Ford F250 Pickup
$50,000
752
2008
Ford F250 Pickup
$50,000
POLICE
$378,000
$378,000
$328,000
$105,000
$145,000
601
2017
Ford Police Interceptor Utility
$65,000
602
2020
Ford Interceptor Hybrid
$65,000
603
2016
Ford Taurus Interceptor Sedan - Unmarked
$40,000
604
2021
Ford Interceptor Utility
$65,000
605
2016
Ford Taurus Interceptor Sedan - Unmarked
$40,000
606
2020
Ford Interceptor Hybrid
$65,000
607
2015
Ford Interceptor Utility - Unmarked
$40,000
608
2020
Ford Interceptor Hybrid
$65,000
609
2016
Ford Interceptor
$65,000
611
2014
Ford Police Interceptor Utility - CSO
$53,000
612
2014
Ford Police Interceptor Utility - CSO
$53,000
613
2021
Ford Police Interceptor Utili
$65,000
614
2017
Ford Police Interceptor Utility - CSO
$53,000
615
2019
Ford Interceptor Hybrid
$65,000
616
2015
Ford Interceptor Utili -Unmarked
$40,000
617
2021
Ford Interceptor Hybrid
$65,000
618
2018
Ford Interceptor Utility - Unmarked
$40,005
619
2014
Ford Police Interceptor Utility - Unmarked
$40,000
623
2017
Ford Interceptor Utility
$65,000
624
2014
Ford Police Interceptor Utility - Unmarked
$50,000
626
2020
Ford Interceptor Hybrid
$65,000
627
2015
Chevrolet Equinox - Unmarked
$40,000
628
2018
Ford Interce for Utili - Patrol Unmarked
$65,000
$65,000
Department
Unit #
Year
Description (Mfr/Model)
2023-2027 Equipment Re lacement
2023
2024
2025
2026
2027
STREETS
$609,000
$590.000
$559,000
$495,000
$264.000_
79
2000
Vermeer Brush Chi er
$90,000
80
2012
JD Tractor
$140,000
82
2010
Bobcat Skid Loader S300
$75,000
87
2008
Crafco Pavement Cutter Router
$14,000
88
2011
Falcon Asphalt Patcher Patch Trailer)
$95,000
89
2001
Komatsu Forklift
$125,000
90
2011
Schwarze Patch Trailer (Velocity Trailer)
$100,000
91
2015
CAT Skid Steer
$80,000
93
2010
In ersol Rand Air Compressor
$25,000
94
2010
Crafco Pavement Cutter Router
$14,000
99
2012
Crafco Pavement Cutter Router
$14,000
122
2008
Ford PickuE F250
$50,000
123
2010
Ford Pickup F250
_ _
$55,000
124
2002
Dodge Ram 1500
$50,000
237
2007
International Dump Truck 7400
$265,000
239
2008
Ford F550
$70,000
241
2010
Ford F550
$160,000
242
2010
Ford F550
$70,000
243
2011
International Dump Truck 7600 SFA 6x4
$270,000
244
2011
Dodge 1 Ton 5500
$60,000
245
2014
Ford F450
$70,000
248
1988
Ford F350
$60,000
309
2012
Elgin Pelican Sweeper
$230,000
312
1 2012
ICat Loader 924H
1 $235,000
Equipment Replacement Fund Total
$1,449,000
$1,133,000
$1,354,0D0
$739,0001
$591,000
Source
City of Elk River, Minnesota
Capital Improvement Plan
2023 thru 2027
PROJECTS BY FUNDING SOURCE
Project# 2023 2024 2025 2026 2027
Government Buildings r
City Hall - Roof Replacement BL-01
Public Safety Building - Roof Replacement BL-02
Public Safety Building - Indoor Range BL-04
Trott Brook Barn - RoofMindows Replacement BL-06
Phone System BL-10
Government Buildings Total
GRAND TOTAL
1,000,000
800,000
160,000
40,000
1,990,000
144,000
144,000
Total
1,000,000
800,000
150,000
40,000
144,000
2,134,000
1,990,000 144,000 2,134,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk Fiver
Government Building
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
Cash Balance - Beginning
$4,593,009
$4,388,814
$6,206,494
$7,946,174
$9,930,133
Revenues:
Landfill expansion fee
2,100,000
2,125,000
2,150,000
2,175,000
2,200,000
Interest earnings
80,500
88,000
124,000
198,654
248,253
Total Revenues
2,180,500
2,213,000
2,274,000
2,373,654
2,448,253
Expenditures:
City hall - Roof replacement
1,000,000
-
-
-
-
Public Safety Building:
Roof replacement
800,000
-
-
-
-
Indoor range
150,000
-
-
-
-
Trott Brook Barn - Roof/windows
40,000
-
-
-
-
Phone system replacement
-
-
144,000
-
-
Debt Service -
2020B PW Building Bonds (Call 2/1/2029) *
394,695
395,320
390,320
389,695
393,195
Total Expenditures
2,384,695
395,320
534,320
389,695
393,195
Revenues over/(under) Expenditures
(204,195)
1,817,680
1,739,680
1,983,959
2,055,058
Cash Balance - Ending
$4,388,814
$6,206,494
$7,946,174
$9,930,133
$11,985,191
* Debt service transition to tax levy
Capital Improvement Plan
City of Elk River, Minnesota
Project # BL-01
Project Name City Hall -Roof Replacement
Description
�ity Hall roof replacement
2023 thru 2027
3ttstificatio
�ity hall roof is beyond its 20 year life expectancy and repairs are needed more frequently.
Department Public Buildings
Contact Facilities Maintenance Supt.
Type Building
Useful Life 20 years
Category Buildings
Expenditures 2023 2024 2025 2026 2027 Total
Buildings 1,000,000 1,000,000
Total 1,000,000 1,000,000
Funding Sources 2023 2024 2025 2026 2027 Total
Government Buildings 1,000,000 1,000,000
Total 1,000,000 1,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
BL-02
Public Safety Building - Roof Replacement
2023 2027
Description 1
'ublic safety building partial roof replacement on existing section of the building
Department Public Buildings
Contact Facilities Maintenance Supt.
Type Building
Useful Life 20 years
Category Buildings
Justification
[be roof of the public safety building is past its life expectancy and roof repairs are required more frequently with sections starting to pull away
iom the side walls of the building.
Expenditures 2023 2024 2025 2026 2027 Total
Buildings 800,000 800,000
Total 800,000
Funding Sources 2023 2024 2025 2026 2027 Total
800,000
Government Buildings 800,000 800,000
Total 800,000 800,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # BL-04
Project Name Public Safety Building - Indoor Range
Description
Jpgrade the indoor firing range at the public safety building
2023 2027
Public Safety Building
Police Chief
Maintenance
15 years
Building Maintenance
Justification J
The indoor range used by the police department is nearing 20 years old and there is a need to upgrade the equipment and rail system to current
standards. The indoor range is vital to the training and qualification of police officers as required by the MN POST board.
Expenditures 2023 2024 2025 2026 2027 Total
Building Maintenance 150,000
Total 150,000
Funding Sources 2023 2024 2025 2026 2027 Total
Government Buildings
150,000
150,000
150,000 150,000
TOW 150,000 150,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 2027
City of Elk River, Minnesota
BL-06
Trott Brook Barn - Roof/Windows Replacement
f
Trott Brook Barn roof and window replacement
`Justification l
IThe shingles are in need of replacement and several windows are broken or with rotting window frames.
Expenditures 2023
Buildings 40,000
Total 40,000
Public Buildings
Facilities Maintenance Supt.
Building
20 years
Buildings
2024 2025 2026 2027 Totak
40,000
40,000
Funding Sources 2023 2024 2025 2026 2027 Total
Govemment Buildings 40,000 40,000
Total 40,000
40,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # BL-10
Project Name Phone System
Description
Phone system replacement
2023 thru 2027
Department
Technology/Communications
Contact
IT Manager
Type
Equipment
Useful Life
10 years
Category
Technology
Justification
Che phone system was installed in 2015 and is scheduled for replacement due to technology and communication advancements.
Expenditures 2023 2024 2025 2026 2027 Total
Total
Funding Sources
ERMU
Government Buildings
Total
180,000
180,000
180,000
180,000
2023 2024 2025 2026 2027 Total
36,000
144,000
180,000
36,000
144,000
180,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
2023 2027
PROJECTS BY FUNDING SOURCE
Source Project # 2023 2024 2025 2026 2027 Total
Park Dedication 1
County Projects - Cost Share
11-20
250,000
250,000
YAC - Park Accessories
PDF 23-1
202,000
202,000
Rivers Edge Dock - Camera System
PDF 23-2
9,100
9,100
Ninja/Fitcore Playground - Lions Park
PDF 24-1
280,000
280,000
Trail Development
PF-64
370,000
370,000
Park Dedication Total
211,100
900,000
1,111,100
Park Improvement
Athletic Field Master Plan
PIF 23-1
45,000
45,000
Playground - Lions Park
PIF 23-2
200,000
200,000
Park Improvement - Miscellaneous
PIF 23-27
25,750
16,250
16,250
16,250
10,000
84,500
Storage Garage - Woodland Trails
PIF 23-4
150,000
150,000
Playgrounds - Country Crossingfrrott Brook
PIF 24-1
250,000
250,000
Basketball Court - Kliever Lake Fields
PIF 24-2
50,000
50,000
Basketball Courts - Deerfield/Ridgewood
PIF 25-1
80,000
80,000
Nature Play - Woodland Trails
PIF 25-2
75,000
75,000
Playground/Basketball Court - Riverplace
PIF26-1
185,000
185,000
Lions Park Shelters
PIF 26-2
300,000
300,000
Playgrounds - Fresno/Mississippi Oaks
PIF 27-1
190,000
190,000
Rivers Edge Park Fountain
PIF 27-2
75,000
75,000
Park Improvement Total
420,750
316,250
171,250
501,250
275,000
1,684,500
GRAND TOTAL
631,850
1,216,250
171,250
501,250
275,000
2,795,600
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River
Park Dedication Fund
Cash Balance - Beginning
Revenues:
Park dedication
Sale of property - Pinewood CD
Interest
Total Revenues
Expenditures:
Miscellaneous
Pinewood - irrigation/utility hookup
Ninja/Fitcore system
YAC - shade structure
Orono Pk - sec. cameras
TH 10 Trail Lights
YAC - park maintenance garage
Rivers Edge Dock - camera system
Skate Park Lighting
Trail Development
CR 44 Trail - Local cost share
Total Expenditures
Revenues over/(under) Expenditures
Cash Balance - Ending
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$1,582,311
$1,577,491
$883,771
$1,078,051
$1,275,831
150,000
150,000
150,000
150,000
150,000
28,780
28,780
28,780
28,780
28,780
27,500
27,500
15,500
19,000
22,500
206,280
206,280
194,280
197,780
201,280
-
280,000
-
-
-
142,000
-
-
-
-
60,000
-
-
-
-
9,100
-
-
-
-
-
370,000
-
-
-
-
250,000
-
-
-
211,100
900,000
-
-
-
(4,820)
(693,720)
194,280
197,780
201,280
$1,577,491
$883,771
$1,078,051
$1,275,831
$1,477,111
City of Elk River
Park Improvement Fund
Cash Balance - Beginning
Revenues:
2023 2024 2025
Estimate Estimate Estimate
$194,237 $52,653 $103
2026 2027
Estimate Estimate
$87,053 ($162,697)
Interest Income
3,500
1,000
-
1,500
-
Youth Football - Oak Knoll Lights
7,416
-
-
-
-
Lacrosse - Oak Knoll Lights
4,450
4,450
4,450
-
-
Sponsorships
13,800
8,250
3,750
-
-
Transfer In -Liquor Fund
250,000
250,000
250,000
250,000
250,000
Total Revenues
279,166
263,700
258,200
251,500
250,000
Expenditures:
Athletic fields demand analysis/master plan
45,000
-
-
-
-
WHHCA Friends of the Mississippi partnership
6,250
6,250
6,250
6,250
-
Great Northern Trail regional master plan
9,500
-
-
-
-
Country Crossing playground
-
125,000
-
-
-
Deerfield basketball court
-
-
50,000
-
-
Lions Park playground
200,000
-
-
-
-
Ridgewood basketball court
-
-
30,000
-
-
Riverplace - playground/basketball court
-
-
-
185,000
-
Trott Brook playground
-
125,000
-
-
-
Kliever Lake Fields - basketball court
-
50,000
-
-
-
Woodland Trails storage garage
150,000
-
-
-
-
Woodland Trails nature play area
-
-
75,000
-
-
Misc. projects
10,000
10,000
10,000
10,000
10,000
Lions Park Shelters replacements (3)
-
-
-
300,000
-
Fresno Park Playground
-
-
-
-
100,000
Mississippi Oaks Playground
-
-
-
-
90,000
Rivers Edge Park fountain
-
-
-
-
75,000
Total Expenditures
420,750
316,250
171,250
501,250
275,000
Revenues over/(under) Expenditures
(141,584)
(52,550)
86,950
(249.750)
(25.000)
Cash Balance - Ending
$52,653
$103
$87,053
($162,697)
($187,697)
Parks Commission Recommended 10-5-22
Capital Improvement Flan
City of Elk River, Minnesota
?roject ii PDF 23-1
ProjectNamL YAC -Park Accessories
Description
Shade structure - $142,000
?ark maintenance garage - $60,000
Justification
Acquisition, development, or improvement of the city's park systems.
2023 2027
Park Improvement
Park & Rec. Director
Improvement
Unassigned
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Improvements 202,000 202,000
Funding Sources
Park Dedication
TOW 202,000
2023 2024 2025 2026 2027 Total
202,000 202,000
Total 202,000 202,000
202,000
Capital Improvement Plan
City of Elk River, Minnesota
PDF 23-2
Rivers Edge Dock - Camera System
Description I
amera system for the dock at Rivers Edge Commons Park
Justification
>ecurity camera system to monitor the downtown dock area.
2023 2027
Park Improvement
Park & Rec. Director
Equipment
7 years
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 9,100 9,100
Total 9,100 9,100
Funding Sources 2023 2024 2025 2026 2027 Total
Park Dedication 9,100 9,100
Total 9,100 9,100
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Projects€ PDF 24-1
Project Name Ninja/Fitcore Playground
Description
Jinja/Fitcore playground system
Justification I
kcquisition, development, or improvement of the city's park systems.
Expenditures
Improvements
2023 2027
€�rtrnent Park Improvement
Park & Rec. Director
Equipment
Playground Equipment
2023 2024 2025 2026 2027 Total
280,000
280,000
Total 280,000 280,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Dedication 280,000 280,000
Total
280,000
280,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PIF 23-1
Project Name Athletic Field Master Plan
Description
4thletic fields master plan
2023 thru 2027
Department Park Improvement
Contact Park & Rec. Director
Type Study
Useful Life Unassigned
Category Park Improvements
Justification I
Determine the community needs and usage of the city's athletic fields and develop a master plan based on the demand analysis.
Expenditures 2023 2024 2025 2026 2027 Total
Design 45,000 45,000
Total 45,000 45,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 45,000 45,000
Total 45,000
45,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
PIF 23-2
Playground - Lions Park
Description I
Jpdate playground at Lion John Wei Park
Justification I
knnual maintenance/repairs of our park system.
Expenditures
Equipment
Funding Sources
2023 thru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Equipment
Useful Life
15 years
Category
Playground Equipment
2023 2024 2025 2026 2027 Total
200,000
Total 200,000
2023 2024 2025 2026 2027 Total
200,000
200,000
Park Improvement 200,000 200,000
Total 200,000 200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# PIF 234
Project Name Storage Garage - Woodland Trails
Description
7onstruction of storage garage
2023 thru 2027
Justification I
Storage garage for equipment used for the maintenance of Woodland Trails Regional Park.
Department
Park Improvement
Contact
Park & Rec. Director
Type
Building
Useful Life
25 years
Category
Buildings
Expenditures
2023 2024
2025 2026 2027 Total
Buildings
150,000
150,000
Funding Sources
Total 150,000
2023 2024
150,000
2025 2026 2027 Total
Park Improvement
150,000
150,000
Total 150,000
150,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# PIF 23-27
Project Name Park Improvement -Miscellaneous
Description
WHHCA - Friends of the Mississippi partnership - $6,250
Great Northern Trail master plan - $9,500
Miscellaneous park projects - $10,000
Justification
Various park improvement expenditurces
2023 ;'hru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Unassigned
Useful Life
Unassigned
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Other 25,750 16,250 16,250 16,250 10,000 84,500
Total 25,750 16,250 16,250 16,250 10,000 84,500
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 25,750 16,250 16,250 16,250 10,000 84,500
Total 25,750 16,250 16,250 16,250 10,000 84,500
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 2027
City of Elk River, Minnesota
Project# PIF 24-1
Project Name Playgrounds - Country Crossing/Trott Brook
Description
Replace playgrounds at Country Crossing and Trott Brook parks
Justification !
Annual maintenance/repairs of our park system.
Department
Park Improvement
Contact
Park & Rec. Director
Type
Equipment
Useful Life
15 years
Category
Playground Equipment
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 250,000 250,000
Total 250,000 250,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 250,000 250,000
Total 250,000 250,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PIF 24-2
Project K,: Basketball Court - Kliever Lake Fields
Description
tenlace basketball court at Kliever Lake Fields
Justification
knnual maintenance/repairs of our park system.
2023 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Improvements 50,000 50,000
Total 50,000 50,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 50,000 50,000
Total
50,000
50,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# PIF 25-1
Project Name Basketball Courts - Deerfield/Ridgewood
Description
teplace basketball courts at Deerfield and Ridgewood parks
Justification
knnual maintenance/repairs of our park system.
2023 thru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Improvements
Funding Sources
Park Improvement
80,000
80,000
Total 80,000 80,000
2023 2024 2025 2026 2027 Total
Total
80,000
80,000
80,000
80,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
City of Elk River, Minnesota
Project # PIF 25-2
Project Name Nature Play - Woodland Trails
Description
�onstruct nature play area at Woodland Trails Regional Park
Justification
knnual maintenance/repairs of our park system.
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Improvements 75,000 75,000
Total 75,000 75,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 75,000 75,000
75,000
75,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
PIF 26-1
Playground/Basketball Court - Riverplace
Description I
Fe —placement of playground equipment and basketball court
Justification I
Annual maintenance/repairs of our park system.
2023 thru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 125,000
Improvements 60,000
Total
185,000
125,000
60,000
185,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 185,000 185,000
185,000 185,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PIF 26-2
Project Name Lions Park Shelters
Description
Replace park shelters (3) at Lion John Weicht Park
Justification
knnual replacementlimprovement of our park system.
2023 4hru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
20 years
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Improvements
Total
Funding Sources
Park Improvement
Total
300,000
300,000
300,000
300,000
2023 2024 2025 2026 2027 Total
300,000 300,000
300,000 300,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement plan
City of Elk River, Minnesota
2roject h PIF 27-1
Project Name- Playgrounds - Fresno/Mississippi Oaks
2023 2027
Description L
teplace playgrounds at Fresno ($100,000) and Mississippi Oaks ($90,000) parks
Justification
knnual replacement/improvement of our park system.
Expenditures
Equipment
Total
Funding Sources
Park Improvement
2023 2024 2025
Department
Park Improvement
Contact
Park & Rec. Director
Type
Equipment
Useful Life
15 years
Category
Playground Equipment
2026 2027 Total
190,000 190,000
190,000 190,000
2023 2024 2025 2026 2027 Total
190,000 190,000
190,000 190,000
,:es;:�-�cr�, L.i4PITfiLa�.�rncar::ata..�t rt.,esv
Capital Improvement Plan
City of Elk River, Minnesota
PIF 27-2
Rivers Edge Park Fountain
Description
Zeplace fountain at Rivers Edge Park
Justification
knnual replacement/improvement of our park system.
Expenditures
Improvements
Funding Sources
Park Improvement
2023
2023 thru 2027
2024 2025
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
2026 2027 Total
75,000 75,000
75,000 75,000
2023 2024 2025 2026 2027
75,000
Total
75,000
Total ro,uuu ro,uuu
1023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 thru 2027
PROJECTS BY FUNDING SOURCE
Source Project # 2023 2024 2025 2026 2027 Total
1
11-01
Hwy 169 Frontage/Backage Road Improvements
Kelley PkwylTwin Lakes Rd/TH 10 Intersection
11-08
County Projects - Cost Share
11-20
Trail Development
PF-64
Municipal State Aid Total
'Pavement Management
Hwy 169 FrontageBackage Road Improvements
11-01
169 Redefine
11-03
County Projects - Cost Share
11-20
Pavement Management - Streets
PM-01
Pavement Management - Parking Lots/Trails
PM-02
Pavement Management Total
rung Utilit k Fund
169 Redefine
11-03
Wastewater - Urban Services Expansion
WW-23
Trunk Utility Fund Total
GRAND TOTAL
750,000
3,000,000
1,520,000
450,000
1,970,000 3,750,000
750,000
3,000,000
1,520,000
450,000
5,720,000
750,000
750,000
1,507,000
1,507,000
750,000
750,000
3,850,000 300,000
3,600,000 300,000 3,000,000
11,050,000
350,000 200,000
350,000 200,000 350,000
1,450,000
4,200,000 2,757,000
4,700,000 500,000 3,350,000
15,507,000
1,000,000
16,850,000
1,000,000 16,850,000
1,000,000
16,850,000
17,850,000
4,200,000 5,727,000 25,300,000 500,000 3,350,000 39,077,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River
Pavement Management Fund
Cash Balance - Beginning
Revenues:
Charges for Services -
Franchise Fee
Other Revenue -
Interest
MSA - Street Maintenance
Total Revenues
Expenditures:
Street Projects
Hwy 169 Project
County Projects - cost share
Sealcoat/Overlay program
Parking Lots
Trails
Total Expenditures
Revenues less Expenditures
Cash Balance - Ending
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$6,884,375
$4,819,875
$4,177,375
$1,598,875
$3,188,875
1,557,000
1,573,000
1,589,000
1,605,000
1,621,000
137,500
96,500
83,500
32,000
64,000
441,000
445,000
449,000
453,000
458,000
2,135,500
2,114,500
2,121,500
2,090,000
2,143,000
3,650,000
100,000
3,400,000
100,000
2,800,000
-
1,507,000
750,000
-
-
-
750,000
-
-
-
200,000
200,000
200,000
200,000
200,000
350,000
-
350,000
-
350,000
-
200,000
-
200,000
-
4,200,000
2,757,000
4,700,000
500,000
3,350,000
(2,064,500)
(642,500)
(2,578,500)
1,590,000
(1,207,000)
$4,819,875
$4,177,375
$1,598,875
$3,188,875
$1,981,875
Municipal State Aid - Construction Balance
2023
2024
2025
2026
2027
Beginning balance
$ 2,256,563
$ 4,022,722
$ 3,853,722
$ 1,940,722
$ 3,814,722
New Allotment (average)
1,766,159
1,801,000
1,837,000
1,874,000
1,911,000
Allocations:
County Projects - Local cost share
-
(1,520,000)
-
-
-
Trail Development
-
(450,000)
-
-
-
Hwy 169 Frontage/Backage Roads
-
-
(750,000)
-
-
Kelley Pkwy/Twin Lakes Rd/Th 10
-
-
(3,000,000 i
-
-
Total Allocations
-
(1,970,000)
(3,750,000)
-
-
Ending Balance
$4,022,722
$3,853,722
$1,940,722
$3,814,722
$5,725,722
"=State -aid roads portion of pavement management plan
City of Elk River
Trunk Utility Fund
Cash Balance - Beginning
Revenues:
Special Assessments
Interest
Total Revenues
Expenditures:
Hwy 169 utility modifications
NE & NW urban services expansion
Total Expenditures
Revenues over/(under) Expenditures
Cash Balance - Ending
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$1,861,014
$1,984,314
$1,109,614
($15,627,586)
($15,536,786)
90,800
90,800
90,800
90,800
90,800
32,500
34,500
22,000
-
-
123,300
125,300
112,800
90,800
90,800
-
1,000,000
-
-
-
-
-
16,850,000
1z3,3uu (W4,MU) (1(j,737,2u0) 90,800 90,800
$1,984,314 $1,109,614 ($15,627,586) ($15,536,786) ($15,445,986)
1 k
River �'••.
4 1
0.5 1 _
Miles
Capital Improvement Plan
City of Elk River, Minnesota
Project # PM-01
Project Name Pavement Management - Streets
2023 thru 2027
Department
Infrastructure Improvements
Contact
Public Works Director
Type
Improvement
Useful Life
25 years
Category
Street Construction
Description I
Preventative maintenance on our streets includes sealcoating, crackfilling and small overlay projects.
itreet improvement projects to replace, overlay or rehabilitate aged and deteriorated streets, storm drainage, and adjacent walks will be completed
-very other year.
Justification I
Individual street pavement conditions will dictate what pavement management technique will be utilized to extend the life of that specific street
Segment. These techniques may range from preventative maintenance to a full reconstruction of the surface and aggregate base. As they are
mplemented, the prescribed techniques will continually be gauged to assure their performance is proper in extending the life of our pavements.
Expenditures
2023
2024
2025
2026
2027
Design
100,000
100,000
200,000
Construction
3,700,000
3,500,000
3,000,000
10,200,000
Maintenance
200,000
200,000
200,000
200,000
800,000
Total
3,900,000
300,000
3,700,000
300,000
3,000,000
11,200,000
Funding Sources
2023
2024
2025
2026
2027
Total
Pavement Management Fund
3,860,000
300,000
3,600,000
300,000
3,000,000
11,050,000
Storm Water
50,000
100,000
150,000
Total
3,900,000
300,000
3,700,000
300,000
3,000,000
11,200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
City of Elk River, Minnesota
Project # PM-02
Project Name Pavement Management - Parking Lots/Trails
Description I
)vcrlay and sealcoat public parking lots and trails as needed
Department
Infrastructure Improvements
Contact
Public Works Director
Type
Maintenance
Useful Life
15 years
Category
Street Maintenance
,Justification
?rojects will be prioritized based on condition and available funding after all street maintenance project needs are met.
Expenditures
2023
2024
2025
2026
2027
Total
Parking Lot
350,000
350,000
350,000
1,050,000
Trails
200,000
200,000
400,000
Total
350,000
200,000
350,000
200,000
350,000
1,450,000
Funding Sources
2023
2024
2025
2026
2027
Total
Pavement Management Fund
350,000
200,000
350,000
200,000
350,000
1,450,000
Total
350,000
200,000
350,000
200,000
350,000
1,450,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
II-20
County Projects - Cost Share
2023 2027
Description
City share of county projects include:
1) CR 33 Realignment and future trail preparation ($2,000,000 less $480,000 county tumback)
2) CR 44 Reconstruction and Trail
Justification
'ity participation in projects initiated by Sherburne County.
Departineast Infrastructure Improvements
Public Works Director
Infrastructure
25 years
Street Construction
Expenditures 2023
2024 2025
2026 2027 Total
Improvements
2,520,000
2,520,000
Total
2,520,000
2,520,000
Funding Sources 2023
2024 2025
2026 2027 Total
Municipal State Aid
1,520,000
1,520,000
Park Dedication
250,000
250,000
Pavement Management Fund
750,000
750,000
Total
2,520,000
2,520,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # II-03
Project Name 169 Redefine
2023 2027
Description
' ocal cost share for MNDOT project to reconstruct TH 169 through Elk River, including sewer modifications.
Infrastructure Improvements
Public Works Director
Infrastructure
25 years
Street & Utility Construction
Justification
Safety and mobility improvement to the TH 169 corridor and provide better local connection across the highway. Visual quality enhanced railings,
street lights, plantings, colors and textures of the final elements of the TH 169 project.
Expenditures 2023
2024 2025
2026 2027 Total
Improvements
2,507,000
2,507,000
Total
Funding Sources 2023
2,507,000
2024 2025
2,507,000
2026 2027 Total
Pavement Management Fund
Trunk Utility Fund
1,507,000
1,000,000
1,507,000
1,000,000
Total
2,507,000
2,507,000
Capital Improvement Plan 2023
City of Elk River, Minnesota
Project # II-01
Project Name Hwy 169 FrontageBackage Road Improvements
2027
Department
Infrastructure Improvements
Contact
Public Works Director
Type
Infrastructure
Useful Life
25 years
Category
Street Construction
Description I
5esign and implement improvements to the frontage and backage road system east and west of the Hwy 169 Redefine project
Justification
Improvements to the local road connections to Hwy 169 to assure the successful completion of connecting commercial uses on the east side of
Hwy 169 from Main Street to Dodge Avenue.
Expenditures 2023 2024 2025 2026 2027 Total
Construction 1,500,000 1,500,000
Total 1,500,000 1,500,000
Funding Sources 2023 2024 2025 2026 2027 Total
Municipal State Aid
Pavement Management Fund
Total
750,000 750,000
750,000 750,000
1,500,000
1,500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023
City of Elk River, Minnesota
II-08
Kelley Pkwy/Twin Lakes Rd/TH 10 Intersection
2027
Infrastructure Improvements
Public Works Director
Improvement
25 years
Street Construction
Description
:�omplete frontage road Kelley Parkway and Twin Lakes Road extension to new signalized intersection on TH 10/169 at 168th Avenue
Justification
System expansion and access control on TH 10/169 corridor from 171st Avenue to 165th Avenue.
Expenditures 2023 2024 2025 2026 2027 Total
Construction 6,500,000 6,500,000
Total 6,500,000 6,500,000
Funding Sources 2023
2024 2025 2026
2027 Total
Federal Grant
2,000,000
2,000,000
MnDOT Cooperative Funds
1,000,000
1,000,000
Municipal State Aid
3,000,000
3,000,000
Special Assessments
500,000
500,000
Total
6,500,000
6,500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PF-64
Project Name Trail Development
2023 thru 2027
Description
Trail extensions and ADA improvements on the following road segments:
1) Cleveland St NW (CR 40) - CR 12 to south of Twin Lakes Pkwy
2) Mississippi Rd NW (CR 30) - Troy St NW to Naples St NW
3) Mississippi Rd NW (CR 30) - Denver St NW to Orono Rd NW
4) Twin Lakes Rd NW - Twin Lakes Pkwy to Cleveland Rd NW
Department
Park improvement
Contact
Public Works Director
Type
improvement
Useful Life
20 years
Category
Trail improvements
Justification
Trail exptensions and ADA improvements allow for increased options of multi -modal transportation and create a safer path for users to bike, walk,
and roll. These extensions fill in gaps in the current city trail system along the county road system.
Expenditures 2023
2024 2025
2026 2027 Total
Trails
1,650,000
1,650,000
Total
1,650,000
1,650,000
Funding Sources 2023
2024 2025
2026 2027 Total
Federal Grant
830,000
830,000
Municipal State Aid
450,000
450,000
Park Dedication
370,000
370,000
Total
1,650,000
1,650,000
2023-2027 CAPITAL IMPR&vPMENT PLAN
Capital Improvement Flan
City of Elk River, Minnesota
Project# WW-23
Project Name Wastewater - Urban Services Expansion
2023 thru 2027
Department
Sewer Department
Contact
Public Works Director
Type
Infrastructure
Useful Life
Unassigned
Category
Plant Expansion
Description
Crunk system upgrades and expansion including headworks, receiving, regional lift stations, forcemains, and gravity sewer.
Justification.
ontinued improvements to support future development in the expanded urban service area (NE & NW areas of the city).
Expenditures
Improvements
Funding Sources
Sewer Fund
Trunk Utility Fund
2023 2024 2025 2026 2027 Total
13,350,000
16,850,000
13,350,000
16,850,000
Total 30,200,000 30,200,000
2023 2024 2025 2026 2027 Tntal
13,350,000
13,350,000
16,850,000
16,850,000
Total 30,200,000
30,200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improve
2023 dwu 2027
PROJECTS BY FUNDING SOURCE
Source Project# 2023 2024 2025 2026 2027 Total
Fire - Engines/Ladders FD-03 2,000,000 800,000 2,800,000
Fire - Bum Building FD-07 500,000 500,000
Business Center Drive Extension 11-35 700,000 700,000
Yet To Be Determined Total 3,200,000 800,000 4,000,000
GRAND TOTAL 3,200,000 800,000 4,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Projects FD-03
Fire - Engines/Ladders
Description
!023 - #419 - 1990 Pierce Ladder
!025 - #416 - 2005 Pierce Engine 2
2023 thru 2027
Justification
Based on annual condition assessment. The fire engines/ladders are the primary front-line response units.
Fire
�a Fire Chief
Vehicle
20 years
Vehicles
Expenditures 2023 2024 2025 2026 2027 Total
Vehicles 2,000,000 800,000 2,800,000
Total 2,000,000 800,000 2,800,000
Funding Sources 2023 2024 2025 2026 2027 Total
Yet To Be Determined 2,000,000 800,000 2,800,000
Total 2,000,000 800,000 2,800,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
FD-07
Fire - Burn Building
Description
?ire bum building for training
2023 thru 2027
Department
Fire
Contact
Fire Chief
Type
Building
Useful Life
25 years
Category
Buildings
Justification
or the continued required training for firefighters to have live fire training. Acquiring residential structures are no longer a long-term solution and
he lack of live fire training is making the job of firefighting unsafe.
Expenditures 2023 2024 2025 2026 2027 Total
Buildings 500,000 500,000
Total 500,000 500,000
Funding Sources 2023 2024 2025 2026 2027 Total
Yet To Be Determined 500,000 500,000
Total 500,000 500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Pending Developer Project
Capital Improvement Plan
City of Elk River, Minnesota
Project ii II-35
Project Name Business Center Drive Extension
2023 2027
Description
Extend Business Center Drive from Waco Street west to Big Lake Township
Department
Infrastructure Improvements
Contact
Planning Manager
Type
Infrastructure
Useful Life
25 years
Category
Street Construction
l
the project will complete a long planned connection of a frontage road system from Waco Street to Big Lake Township to better serve
ransportation needs in the area. The project will further complete a water system loop and add sewer service to an unserved developable parcel.
Expenditures
Design/Construction
Funding Sources
2023 2024 2025 2026 2027
700,000 _ 700,000
Total 700,000 700,000
2023 2024 2025 2026 2027
Yet To Be Determined 700,000 700,000
Total 700,000 700,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 thru 2027
PROJECTS BY FUNDING SOURCE
Source Project # 2023 2024 2025
FTCenter - Zamboni FTC-02
FTCenter Total
Licruor Fund
Northbound Liquor - Monument Sign LS-01
Liquor Fund Total
[Sewer Fund I
Wastewater - Vehide
WW-06
Wastewater - Equipment
WW-12
Wastewater - Lift Station Improvements
WW-19
Wastewater - Clarifier Lining
WW-20
Wastewater - Urban Services Expansion
WW-23
Wastewater- Centrifuge Installation
WW-24
Sewer Fund Total
Storm Water
Pavement Management - Streets PM-01
Stormwater Projects STW-1
Morton Ave Drainage Improvements STW-2
Storm Water Total
GRAND TOTAL
2023-2027 CAPITAL IMPROVEMENT PLAN
202,000
202,000
80,000
80,000
2026 2027 Total
202,000
202,000
80,000
80,000
65,000 65,000
30,000 200,000 230,000
146,000 55,000 55,000 55,000 55,000 366,000
90,000 90,000
13,350,000 13,350,000
6,000,000 6,000,000
266,000 120,000 13,405,000 255,000 6,055,000 20,101,000
50,000
100,000
150,000
250,000
250,000
500,000
250,000
250,000
550,000
350,000
900,000
1,098,000
120,000 13,755,000
255,000 6,055,000 21,283,000
These projects have been approved or
were reviewed during budget work sessions.
Capital Improvement Plan
City of Elk River, Minnesota
FTC-02
FTCenter - Zamboni
Description
tenlace 2008 Zamboni
2023 2027
Justification
3ased on age and condition of equipment needed for ice operations maintenance of the FTCenter.
Expenditures
Equipment
Funding Sources
FTCenter
2023
202,000
Total 202,000
2024 2025 2026
Department FTCenter
Contact Multipurpose Facility Supt.
Equipment
15 years
Equipment
2027 Total
202,000
202,000
2023 2024 2025 2026 2027 Total
202,000
202,000
Total 202,000 202,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # LS-01
Project Name Northbound Liquor - Monument Sign
Description
Northbound monument sign
2023 ¢hru 2027
Department
Liquor Fund
Contact
Liquor Operations Manager
Type
Improvement
Useful Life
20 years
Category
Buildings
New monument sign for Northbound Liquor, with an updated logo, will need to be installed due to visibility related to the reconstruction of TH
169.
Expenditures
Improvements
2023 2024 2025 2026 2027 Total
80,000
Total 80,000
Funding Sources 2023 2024 2025 2026 2027 Total
80,000
80,000
Liquor Fund 80,000 80,000
Total 80,000
80,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 rhru 2027
City of Elk River, Minnesota
WW-06
Wastewater - Vehicle
Description
'ickup Track
Justification I
kn additional pickup is needed due to current staffing.
Expenditures 2023 2024 2025
Vehicles
Funding Sources
Department Sewer Department
Contact Chief Wastewater Operator
Type Vehicle
Useful Life 10 years
Category Vehicles
2026 2027 Total
65,000 65,000
Total 65,000 65,000
2023 2024 2025 2026 2027 Total
65,000 65,000
Total 65,000 65,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# WW-12
Project Name Wastewater - Equipment
Description
>.023 - Sewer line rapid assessment tool (SL-RAT)
>-026 - Sewer camera trailer
2023 thru 2027
Department Sewer Department
Contact Chief Wastewater Operator
Type Equipment
Useful Life 25 yews
Category Equipment
Justification
2023 - The SL-RAT allows for the inspection of 10,000-20,000 feet of sewer lines per day and maintenance efforts can be concentrated on cleaning
out the dirty lines since it is getting harder to jet half the sewer lines each year.
2026 - The sewer camera trailer, which is used frequently to televise sewer mains for preventative maintenance, was purchased in 2010 and is
starting to show signs of wear.
Expenditures 2023 2024 2025 2026 2027 Total
Equipment
Funding Sources
Sewer Fund
30,000
Total 30,000
200,000
200,000
230,000
230,000
2023 2024 2025 2026 2027 Total
30,000 200,000 230,000
Total 30,000 200,000 230,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
WW-19
Wastewater - Lift Station Improvements
Description I
M23 - Chopper pumps for lift stations
?023-2027 - Arc flash safety lift station panels
2023 2027
�z;sa,astY4'.xsk Sewer Department
Chief Wastewater Operator
Equipment
15 years
Equipment
- Chopper pumps eliminate the debris that plugs the lift station pumps.
2027 - The lift station panels are starting to age and with newer tecnologies the arc flash safety panels make it safer for the wastewater
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 146,000 55,000 55,000 55,000 55,000 366,000
Funding Sources
Sewer Fund
Total 146,000
55,000
55,000
55,000
55,000
366,000
2023
2024
2025
2026
2027
Total
146,000 55,000 55,000 55,000 55,000 366,000
Total 146,000 55,000 55,000 55,000 55,000 366,000
Capital Improvement Plan
City of Elk River, Minnesota
Project# WW-20
Project Name Wastewater - Clarifier Lining
2023 thru 2027
Description
iiperline high performance lining to the concrete walls in the clarifier troughs.
Department Sewer Department
Contact Chief Wastewater Operator
Type Maintenance
Useful Life Unassigned
Category Sewer Maintenance
Justification I
)and blast and spray with Spectrshield the concrete walls in the clarifier troughs that are starting to deteriorate.
Expenditures 2023 2024 2025 2026 2027 Total
Maintenance 90,000 90,000
Total 90,000 90,000
Funding Sources 2023 2024 2025 2026 2027 Total
Sewer Fund 90,000 90,000
Total 90,000 90,000
2023-2027 CAPITAL IMPROVEMENTPLAN
Capital Improvement Plan
City of Elk River, Minnesota
'roject1r WW-24
Project ] Wastewater - Centrifuge Installation
Description I
. eplace undersized screw presses with centrifuges
2023 2027
-,,�artment Sewer Department
Contact Chief Wastewater Operator
Type Improvement
Useful Life 25 years
Category Utilities
Justification
Original screw presses were undersized and are expected to be beyond capacity need of the wastewater treatment plant 30 years earlier than
designed.
Expenditures 2023 2024 2025 2026 2027 Total
Improvements 6,000,000 6,000,000
Total 6,000,000 6,000,000
Funding Sources 2023 2024 2025 2026 2027 Total
Sewer Fund 6,000,000 6,000,000
Total
6,000,000 6,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project ft STW-1
Project Name Stormwater Projects
2023 2027
Department
Storm Water
Contact
Storm Water Coordinator
Type
Maintenance
Useful Life
Unassigned
Category
Utilities
Description
Bi-annual pond cleaning, stormwater repairs, BMP inventory.
Z023 - Public shoreline improvements
Z025 - Elk Park Center basin and Zane Street basin
Storm water infrastructure projects combined with street projects are included on the pavement management CIP sheet.)
Justification
These projects include the testing, removal, and disposal of sediment deposits from our stormwater ponds. This is needed to assure the storm water
>ystem is functioning as designed and achieving the water quality standards of our NPDES permit.
the smaller stormwater repairs include minor pipe upsizing, culvert replacement, manhole and catch basin repairs and fixing of washout areas.
Expenditures 2023 2024 2025 2026 2027 Total
Construction/Maintenance 250,000 250,000 500,000
Funding Sources
Storm Water
Total 250,000 250,000 500,000
2023 2024 2025 2026 2027 Total
250,000
Total 250,000
250,000
250,000
500,000
500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# STW-2
Project Name Morton Ave Drainage Improvements
Description
dorton Avenue stormwater drainage improvements
2023 thru 2027
Department
Storm Water
Contact
Storm Water Coordinator
Type
Improvement
Useful Life
50 years
Category
Utilities
Justification
Precipitation volume and intensity weather patterns have contributed to temporary street flooding at Morton Avenue north of Main Street that
spreads outside of the right-of-way.
Expenditures
Improvements
2023 2024
250,000
Total 250,000
Funding Sources 2023 2024 2025 2026 2027 Total
2025 2026
Storm Water 250,000
Total 250,000
2027 Total
250,000
250,000
250,000
250,000
2023-2027 CAPITAL IMFA VEA1AA'T PLAN