10.1 SR 11-07-2022To
Mayor and City Council
Agenda Section Meeting Date
Work Session November 7, 2022
Item Description
2023-2027 Capital Improvement Plan
Action Requested
Review the 2023-2027 Capital Improvement Plan.
Request for Action
Item Number
10.1
Prepared by
Lori Ziemer, Finance Director
Reviewed by
Cal Portner, City Administrator
Reviewed by
Background/Discussion
Staff has identified specific capital projects, estimated project costs and binding sources to be completed over the
next five gears. Projects listed for 2023 will be reviewed along with cash flow estimates of the associated project
fund. Projects are reviewed annually and updated with the CIP.
Capital Reserve Fund
The purchase and replacement of IT hardware/software has been funded by excess General Fund fund balance.
The current balance designated for the replacement of IT technology is about $657,000. In addition, the fund
receives interest income and cable franchise fees to be used for miscellaneous capital outlay items. The
undesignated balance of the bind is about $959,000.
Equipment Replacement Fund
Provides funding for the planned replacement of vehicles and mobile equipment. The funding sources are through
annual General Fund department charges and Local Government Aid (LGA). LGA comes from the state general
fund collected through sales and income taxes and can be subject to state unallotment. Department charges are
based on the amortization of equipment and updated annually. The Fleet Committee evaluates the replacement of
vehicles and equipment based on the criteria of age, miles/hours, maintenance costs, and usage type. The 2023-27
vehicle/equipment purchase requests were reviewed and recommended by the Fleet Committee.
Government Building Fund
Used for municipal building constriction/maintenance, landscaping, and remodeling. The facilities maintenance
supervisor and department directors identify needed building improvements which are updated annually. The
landfill expansion fee and interest earnings are the primary funding sources. The landfill expansion fee is
scheduled to expire in 2030 but is expected to end as early as 2027-2028 based on landfill capacitor. The fund has
covered debt service payments for the public works building since 2012 and will also cover the 2023 debt service.
Park Dedication Fund
Recent plat development activity has increased bind revenues to a cash balance of about $1,593,000 as of
9/30/22. Projects planned for 2023 include YAC shade structure and maintenance garage, and a security camera
for the Rivers Edge dock.
The Elk River Vision P' O W E e E 0 6 Y
_-4 rrekoc•onvnvruuty rrith rerolrrtioaag aad.+pirited resorrrzefrrhress, e.ticeptioaal NAWRE
serrice, aarl covvrurit)eagagelveat that eacorrrzrges alid is pir•es pro perzt�,. 1 pelaterl _4rrgrrst 2020
Park Improvement Fund
Funds the replacement and maintenance of park amenities Nvith an annual $250,000 transfer from the Liquor
Fund. The projects identified by the Parks & Recreation Commission for 2023 include the athletic fields master
plan, Lions Park playground, and Woodland Trails storage garage.
Pavement Management Fund/MSA
A franchise fee on gas and electric utilities is the primary ongoing revenue source to provide long-term binding
for the pavement management program. Municipal State Aid (MSA) is also utilized to fund portions of various
street improvement projects. The maintenance portion (25%) of MSA offsets the cost of the sealcoating and
smaller overlay preventative maintenance projects. MnDOT's transportation binding allotment for 2023 will be
about $1,766,000.
Trunk Utility Fund
This fund consists of special assessment revenue from sewer and water improvement projects. The funds will be
used on trunk sewer improvement projects in lieu of having to issue bonds on biture system expansion /
improvements. No projects are identified for 2023.
Funding Yet to be Determined
Capital items or projects pending review that do not have an associated binding source identified.
Other Funds
Projects listed for 2023 that are associated with budgeted binds such as FTCenter, Liquor, Sewer, and Storm-�vater
have been reviewed during budget work sessions or already approved by Council.
Financial Impact
N/A
Mission/Policy/Goal
Identify binding to develop a sustainable and prosperous community.
Attachments
■ 2023-2027 Capital Improvement Plan
N:\Pubhc Bodies\ Agenda Packets\ 11-07-'0"\Final\x10.1 sr CIP.docx
City of Elk River, Minnesota
Capital Improvement Plan
2023 thm 2027
PROJECTS BY FUNDING SOURCE
Source
Project# 2023 2024 2025
Capital Reserve - IT}
1
2023 Technology Upgrades
TC-23 71,600
2024 Technology Upgrades
TC-24 103,000
2025 Technology Upgrades
TC-25 92,400
2026 2027 Total
2026 Technology Upgrades TC-26 70,000
2027 Technology Upgrades TC-27 57,000
Capital Reserve - IT Total 71,600 103,000 92,400 70,000 57,000
Capital Reserve - Undesignated I
Financial Software TFN-01
Capital Reserve - Undesignated Total
Equipment Replacement Fund
Facilities Maintenance - Vehicles
BM-01
Building Safety -Vehicles
BZ-01
Fire -Vehicles
FD-01
Fire - Trucks
FD-02
Police - Patrol Squads
PD-01
Police - Unmarked Squads
PD-02
Police - CSO Vehicles
PD-03
Parks - Pickup Trucks
PK-01
Parks - Mobile Equipment
PK-02
Streets - Pickup Trucks
ST-01
Streets - Dump Trucks
ST-02
Streets - Mobile Equipment
ST-03
Equipment Replacement Fund Total
JERMU
Phone System
BL-10
2023 Technology Upgrades
TC-23
2024 Technology Upgrades
TC-24
2025 Technology Upgrades
TC-25
2026 Technology Upgrades
TC-26
2027 Technology Upgrades
TC-27
ERMU Total
Federal Grant I
Kelley Pkwy/Twin Lakes Rd/TH 10 Intersection 11-08
Trail Development PF-64
2023-2027 CAPITAL IMPROVEMENT PLAN
200,000
200,000
160,000
80,000
40,000
50,000
52,000
52,000
195,000
325,000
195,000
65,000
65,000
130,000
80,000
40,000
80,000
53,000
53,000
53,000
260,000
50,000
180,000
55,000
90,000
115,000
105,000
84,000
142,000
230,000
220,000
70,000
125,000
265,000
270,000
14,000
370,000
219,000
495,000
139,000
1,449,000
1,133,000
1,354,000
739,000
591,000
25,400
2,000
36,000
15,600
5,000
3,000
25,400 2,000 51,600 5,000 3,000
2,000,000
830,000
71,600
103,000
92,400
70,000
57,000
394,000
200,000
200,000
240,000
40,000
50,000
104,000
845,000
330,000
159,000
545,000
536,000
645,000
535,000
1,237,000
5,266,000
36,000
25,400
2,000
15,600
5,000
3,000
87,000
2,000,000
830,000
Source Project #
Federal Grant Total
FTCenter
FTCenter - Zamboni -Approved 5/2/22
FTC-02
FTCenter Total
Government Buildings
City Hall - Roof Replacement
BL-01
Public Safety Building - Roof Replacement
BL-02
Public Safety Building - Indoor Range
BL-04
Trott Brook Barn - RoofMindows Replacement
BL-06
Phone System
BL-10
Government Buildings Total
(Liquor Fund - Reviewed with budget
Northbound Liquor - Monument Sign
LS-01
Liquor Fund Total
IMnDOT Cooperative Funds
Kelley Pkwy/Twin Lakes Rd(TH 10 Intersection
11-08
MnDOT Cooperative Funds Total
Municipal State Aid
Hwy 169 Frontage/Backage Road Improvements
11-01
Kelley Pkwy/Twin Lakes Rd(TH 10 Intersection
11-08
County Projects - Cost Share
11-20
Trail Development
PF-64
Municipal State Aid Total
*arkDedicatio 1;
County Projects - Cost Share
11-20
YAC - Park Accessories
PDF 23-1
Rivers Edge Dock - Camera System
PDF 23-2
Ninja/Fitcore Playground
PDF 24-1
Trail Development
PF-64
Park Dedication Total
Park Improvement
Athletic Field Master Plan
PIF 23-1
Playground - Lions Park
PIF 23-2
Park Improvement - Miscellaneous
PIF 23-27
Storage Garage - Woodland Trails
OF 23-4
Playgrounds - Country Crossing/Trott Brook
OF 24-1
Basketball Court - Kliever Lake Fields
PIF 24-2
Basketball Courts - Deerfield/Ridgewood
OF 25-1
2023-2027 CAPITAL IMPROVEMENT PLAN
2023 2024 2025
830,000 2,000,000
202,000
202,000
1,000,000
800,000
150,000
40,000
1,990,000
80,000
80,000
144,000
144,000
13000,000
1,000,000
750,000
3,000,000
1,520,000
450,000
1,970,000 3,750,000
250,000
202,000
9,100
280,000
370,000
211,100 900,000
2026 2027 Total
2,830,000
202,000
202,000
1,000,000
800,000
150,000
40,000
144,000
2,134,000
80,000
80,000
1,000,000
1,000,000
750,000
3,000,000
1,520,000
450,000
5,720,000
250,000
202,000
9,100
280,000
370,000
1,111,100
45,000
45,000
200,000
200,000
25,750 16,250 16,250 16,250 10,000
84,500
150,000
150,000
250,000
250,000
50,000
50,000
80,000
80,000
Source Project #
2023
2024
2025
2026
2027
Total
Nature Play - Woodland Trails
PIF 25-2
75,000
75,000
Playground/Basketball Court - Riverplace
PIF 26-1
185,000
185,000
Lions Park Shelters
PIF 26-2
300,000
300,000
Playgrounds - Fresno/Mississippi Oaks
PIF 27-1
190,000
190,000
Rivers Edge Park Fountain
PIF 27-2
75,000
75,000
Park Improvement Total
420,750
316,250
171,250
501,250
275,000
1,684,500
Pavement Management
I
Hwy 169 Frontage/Backage Road Improvements
11-01
750,000
750,000
169 Redefine
11-03
1,507,000
1,507,000
County Projects - Cost Share
11-20
750,000
750,000
Pavement Management - Streets
PM-01
3,850,000
300,000
3,600,000
300,000
3,000,000
11,050,000
Pavement Management- ParkingLots/Trails
PM-02
350,000
200,000
350,000
200,000
350,000
1,450,000
Pavement Management Total
4,200,000
2,757,000
4,700,000
500,000
3,350,000
15,507,000
(Sewer Fund - Reviewed with budget
I
Wastewater - Vehicle
WW-06
65,000
65,000
Wastewater - Equipment
WW-12
30,000
200,000
230,000
Wastewater - Lift Station Improvements
WW-19
146,000
55,000
55,000
55,000
55,000
366,000
Wastewater - Clarifier Lining
WW-20
90,000
90,000
Wastewater - Urban Services Expansion
WW-23
13,350,000
13,350,000
Wastewater - Centrifuge Installation
WW-24
6,0003000
6,000,000
Sewer Fund Total
266,000
120,000
13,405,000
255,000
6,055,000
20,101,000
Special Assessments
I
Kelley Pkwy/Twin Lakes RdTTH 10 Intersection
11-08
500,000
500,000
Special Assessments Total
500,000
500,000
(Storm Water - Reviewed with budget
Pavement Management - Streets
PM-01
50,000
100,000
150,000
Stormwater Projects
STW-1
250,000
250,000
500,000
Morton Ave Drainage Improvements
STW-2
250,000
250,000
Storm Water Total
550,000
350,000
900,000
Trunk Utility Fund
169 Redefine 11-03 1,000,000 1,000,000
Wastewater- Urban Services Expansion WW-23 16,8503000 16,850,000
Trunk Utility Fund Total 1,000,000 16,850,000 17,850,000
lYet To Be Determined I
Fire - Engines/Ladders FD-03 2,000,000 800,000 2,800,000
Fire - Burn Building FD-07 500,000 500,000
Business Center Drive Extension - Pending 11-35 700,000 700,000
Yet To Be Determined Total 3,200,000 800,000 4,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Source Project# 2023 2024 2025 2026 2027 Total
GRAND TOTAL
12,865,850 9,131,250 45,168,250 2,070,250 10,331,000 79,566,600
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 thm 2027
PROJECTS BY FUNDING SOURCE
Source Project# 2023 2024 2025
1
2023 Technology Upgrades TC-23 71,600
2024 Technology Upgrades TC-24 103,000
2025 Technology Upgrades TC-25 92,400
2026 2027 Total
2026 Technology Upgrades TC-26 70,000
2027 Technology Upgrades TC-27
Capital Reserve - IT Total
(Capital Reserve - Undesignated
Financial Software TFN-01
Capital Reserve - Undesignated Total
GRAND TOTAL
71,600 103,000 92,400 70,000
200,000
200,000
57,000
57,000
71,600
103,000
92,400
70,000
57,000
394,000
200.000
200,000
271,600 103,000 92,400 70,000 57,000 594,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River
Technology/Software Improvements
Expenditures
Voice server
Simplivity server node
Fiber switch
Security camera system replacement
Mobile management system
Meraki licenses
Enterprise backup system
Microsoft server upgrade
Email archiver,spam, ATP
Phone system replacement
Enterprise backup system
,DSX upgrades
fvleraki switch upgrades
Total Expenditures
Funding Sources:
Capital Reserve -IT
Government Building
ERMU icost share)
Total
2023 2024 2025 2026 2027
25,000
52,000
20,000
60,000
25,000
20,000
42.000
30,000
36,000
180.000
25,000
50,000
97,000 105,000 288,000 75,000
30,000
30,000
60,000
Total
25,000
52,000
20,000
90,000
25,000
20,000
42.000
30,000
36,000
180.000
25,000
50,000
30,000
625,000
71,600 103,000 92,400
70,000 1 57,000 394,000
- - 1144,000
- - 144,000
25,400 2,000 51,600
5,000 3,000 87,000
97,000 105,000 288,000
75,000 60,000 625,000
Capital Improvement Plan
City of Elk River, Minnesota
Project # TFN-01
Project Name Financial Software
2023 thru 2027
Department
Finance
Contact
Finance Director
Type
Technology
Useful Life
Unassigned
Category
Software
Description
Update financial software to improve technology efficiences, structured workflows, and integration flexibility with other applications.
Justification
The current financial software is approaching 15 years old and is in need of updating to take advantage of newer technology enhancements and
workflows to improve efficiencies in the financial management of the city.
Expenditures 2023 2024 2025 2026 2027 Total
Software/Hardware 200,000 200,000
200,000 200,000
Funding Sources 2023 2024 2025 2026 2027 Total
Capital Reserve-Undesignated 200,000 200,000
200,000 200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 thm 2027
PROJECTS BY FUNDING SOURCE
Source Project # 2023 2024 2025 2026 2027 Total
Equipment Replacement Fund �
Facilities Maintenance - Vehicles
BM-01
160,000
80,000
240,000
Building Safety -Vehicles
BZ-01
40,000
40,000
Fire - Vehicles
FD-01
50,000
50,000
Fire - Trucks
FD-02
52,000
52,000
104,000
Police - Patrol Squads
PD-01
195,000
325,000
195,000
65,000
65,000
845,000
Police - Unmarked Squads
PD-02
130,000
80,000
40,000
80,000
330,000
Police - CSO Vehicles
PD-03
53,000
53,000
53,000
159,000
Parks - Pickup Trucks
PK-01
260,000
50,000
180,000
55,000
545,000
Parks - Mobile Equipment
PK-02
90,000
115,000
105,000
84,000
142,000
536,000
Streets - Pickup Trucks
ST-01
230,000
220,000
70,000
125,000
645,000
Streets - Dump Trucks
ST-02
265,000
270,000
535,000
Streets -Mobile Equipment
ST-03
14,000
370,000
219,000
495,000
139,000
1,237,000
Equipment Replacement Fund Total
1,449,000
1,133,000
1,354,000
739,000
591,000
5,266,000
GRAND TOTAL
1,449,000
1,133,000
1,354,000
739,000
591,000
5,266,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River
Equipment Replacement Fund
Beginning Cash Balance
Revenues:
Revenues from charges
Local Government Aid
Interest earnings
Other revenues (sale of assets/misc)
Total Revenues
Expenditures:
Capital Equipment -
Police
Fire
Parks
Streets
Facilities Maintenance
Building Safety
Total Expenditures
Revenues overl(under) Expenditures
Ending Cash Balance
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$1,289,726
$766,312
$647,812
$355,812
$727,812
436,500
471,000
509,000
550,000
594,000
466,586
478,000
490,000
502,000
515,000
22,500
15,500
13,000
9,000
18,000
50,000
50.000
50,000
50,000
50,000
975,586
1,014,500
1,062,000
1,111,000
1,177,000
428,000
378,000
328,000
105,000
145,000
52,000
-
102,000
-
-
350,000
165,000
285,000
139,000
142,000
509,000
590,000
559,000
495,000
264,000
160,000
-
80,000
-
-
-
-
-
-
40,000
1,499,000
1,133,000
1,354,000
739,000
591,000
(523,414)
(118,500)
(292,000)
372,000
586,000
$766,312
$647,812
$355,812
$727,812
$1,313,812
WWRMM=mar
W N O O W V FC4N WN NW N N W i
O
V V V V A O O O O 0) 0) WCTi � ? PN N N — O OV V
OD CO V A PO V CO CO N V P. W N CT 0 N W
7 7
NNNNNCn
NNNNNNO
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
W
OO
V
N
W
00
W
lon
V
-�
O
4
Cp
�
V
.P
O
V
�
TI
TI
j
p
7I
C7
�i
0
O
n
`
T
T
0
TI
TI
11
71
m
TI
TI
O
O
°
o.
a
a
a
a
a
a
a
a
s
fl:
N
O
V?
p
W
C
p
C
C
C
C
W
N
v
cw
ccn
"
O
O
O
O
CA O
<
CD
O
O
aO
rt
r
r+
<<
.+
0O
WO
CD
3
<
7
m
c
N
CD
O
O
w
0
o
x
c
W
N
X
CD
N
W
1
CD
CD
O
Cu
0
w
1
0
0
o
0
0
0
o
N
co
w
CD
CDrt
0
0
CD
CD
CD
7c
x
W,x
x
x
C)
C f
n
C)
n
C7
n
n
n
n
C
w
w
w
w
w
w
O
O
O
CD
O
O
0
+
a�
v
Wow
3
v
�
K
;L
3
3
o
O
3
-�
o
v�
T.
3
CD
�
:
rr
CD
CD
CD
r-ol
a
a
Q
M
C
-u-u
'U
-u
m
�
-I
TI
TI
0
0
m
m
0
m
m
m
-n
�.
cx
x
x<��
m
m
m
o
3
w
x
x
x
o
a
a
a
a
a
a
a
a
y
c
O
5
-O
c
c
c
O
c
O
c
c
a
c
O
r►
C
<<
C
C
<
C
y
W
O
O
O
N
W
NZ
CD
cn
=
m
cu
cn
cn
cn
m
y
C
C)
n
C
C
c
c
C
c
c
O
O
7C
;r;r
o
X
o
X
Zl
o
X,
o
X
o
W,
o
�r
o
;r
-1
O
O"
LD
<
CD
<
N
<
�
CD
Q
u
cr
M
S
CD
Q
N
N
C1
C1
C%
6
C L
n
CD
CD
CD
m
a
m
CA
C7
0
a
r
s
m
69
A
69
.69
N
4A
69
69
-69
69
69
Efi
w
w
ffl
Ee
EH
to
69
4A
<fl
69
Efl
E9
&9
-Ph
OO
O
O
O
0
O
O
3
O
P.
O
O
O
O
O
N
J
OOC1
W
O
C)
O
a
O
0
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
m
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O,
O
O
O
O
O
O
O
N
N
N
N
N
N
U
O
O
O
O
O
O
O
a
a
a
a
s
a
a
(�
C0D
C0D
CD
CD
CD
CD
CD
m
CD
m
CD
m
m
a
a
a
a
n
o.
a
Department /
Year
Description (Mfr/Model)
Unit #
FACILITIES 61AINT
370
2012
Ford F350 Utility Pick_ o
372
2008
Ford XL F350
373
2001
Ford F250
374
2004
JD Gator
377
Ford F250
FABS
511
2015
GMC Sierra 1500
FIRE
E
401
2015
Chevrolet Tahoe (Fire Chief)
411
2004
Ford F350 Grass #3
412
2006
Ford F350 Grass #4
PARKS
700
2014
Cat 257D Skid Steer w/Tracks
701
1988
Snow Scoot - Yellow tHillside}
702
1988
Snow Scoot - Red ; Hillside',
714
2012
Bombardier Ski-Doo Skandic
715
2014
Ski-Doo Skandic 600 SWT
718
2003
Suzuki4x4 ATV
719
2003
Suzuki 4x4 ATV
722
2017
Toro Z-Master Zero Turn Mower
723
2017
"Toro Groundsmaster 5910 Wide Area
26
2015
John Deere Zero Turn Mower
29
Ford F250
7 ' C.
2015
Kromer Field Commander B100
731
2009
Chev Silverado 250OHD
732
2009
John Deere Tractor 5095
738
2012
John Deere Tractor 4720
742
2001
Chev 1500
743
2011
GMC500 HD
745
2012
GMC Sierra Pickup 3500
746
2011
Ford F550
748
2007
GMC 3500 1-Ton
749
2005
Chevrolet Silverado 2500
751
2008
Ford F250 Pickup
752
2008
Ford F250 Pickup?
POLICE
601
2017
Ford Police Interceptor Utility
602
2020
Ford Interceptor Hybrid
603
2016
Ford Taurus Interceptor Sedan - Unmarked
604
2021
Ford Interceptor Utility
605
2016
Ford Taurus Interceptor Sedan - Unmarked
606
2020
Ford Interceptor Hybrid
607
2015
Ford Interceptor Utility - Unmarked
608
2020
Ford Interceptor Hybrid
609
2016
Ford Interceptor
611
2014
Ford Police Interceptor Utility - CSO
612
2014
Ford Police Interceptor Utility - CSO
613
2021
Ford Police Interceptor Utility
614
2017
Ford Police Interceptor Utility_ - CSO
615
2019
Ford Interceptor Hybrid
616
2015
Ford Interceptor Utility - Unmarked
617
2021
Ford Interceptor HPnd
618
2018
Ford Interceptor Utility - Unmarked
619
2014
Ford Police Interceptor Utility - Unmarked
623
2017
Ford Interceptor
Utility
624
2014
Ford Police
Interceptor Utility - Unmarked
626
2020
Ford Interceptor Hybrid
627
2015
Chevrolet Equinox - Unmarked
628
2018
Ford Interceptor Utility - Patrol ;Unmarked,
2023-2027 Equipment Replacement
2023 2024
2025
2026
2027
$160,000' $0
$80,000
$0
$0
$60,000
$60, 000
$50,000
$20,000
$50,000
$0 $0.
$0
$0
40,000
40,000
$52.000 $2.000.000,
$902``000
50
$0-
$50,000
$52,000
$52,000
$360,000 $165.000
$286 000
$139,000
$142,000
$90,000
$12,000
$12,000,
$15,000
$15,000
$14,000.
$14,000
$17,000
$125,000
$17,000
$50,000
$45, 000
$50,000
$90,000
$70, 000 1
$50,000
$55,000
$60, 000
$70,000
$60, 000 I
$50,000
$50,000 !
$50,000 I
$378,000 $378.000 $328.0001 $105,000 $145.000
$65,000 1
$65,000
$40,000
$65,000
$40,000
$65,000
$40,000
$65,000
$65,000
$53,000
$53,000
$65,000
$53,000
$65,000
$40,000
$65,000
I It�aa0,000
f 146,000
$65,000
$50,000
$65,000 I
$40,000
$65,000
$65,000
Department
Year
Description (Mfr/Model)
2023-2027 E
uipment Replacement
Unit #
2023.
2024
2025
20026
2027
STREETS
$509.000
$590.000
$559,000
$495,000
$264,000
79
2000
Vermeer Brush Chipper
$90,000
80
2012
JD Tractor
$140,000
82
2010
Bobcat Skid Loader S300
$75,000
87
2008
Crafco Pavement Cutter r Router
$14,000
88
2011
Falcon Asphalt Patcher i Latch Trailer;
$95,000
89
2001
Komatsu Forklift
$125,000
90
2011
Schwarze Patch Trailer (,Velocity Trailer)
$100,000
91
2015
CAT Skid Steer
$80,000
93
2010
Ingersol Rand Air Compressor
$25,000
94
2010
Crafco Pavement Cutter (Router
$14,000
99
2012
Crafco Pavement Cutter (.Router
$14,000
122
2008
Ford Pickup F250
$50,000
123
2010
Ford Pickup F250
$55,000
124
2002
Dod,e Ram 1500
$50,000
237
2007
International Dump Truck 7400
$265,000
239
2008
Ford F550
$70,000
241
2010
Ford F550
$160,000
242
2010
Ford F550
$70,000'
243
2011
International Dump Truck 7600 SFA 6x4
$270,000
244
2011
❑oche 1 Ton 5500
$60,000
245
2014
Ford F450
$70,000
248
1988
Ford F350
SC,0 ;ire;
309
2012
Elgin Pelican Sweeper
$230,000
312
2012
Cat Loader 924H
$235,OriG
Equipment Replacement Fund Total
$`.449,000 $1,133,000
51,354,000
$739,000
$591,000
Source
City Hall - Roof Replacement
Public Safety Building - Roof Replacement
Public Safety Building - Indoor Range
Trott Brook Barn - RoofMindows Replacement
Phone System
City of Elk River, Minnesota
Capital Improvement Plan
2023 thru 2027
PROJECTS
BY FUNDING SOURCE
Project#
2023 2024 2025
BL-01
1,000,000
BL-02
800,000
BL-04
160,000
BL-06
40,000
BL-10
144,000
Government Buildings Total
GRAND TOTAL
1,990,000 144,000
1,990,000 144,000
2026 2027 Total
1,000,000
800,000
150,000
40,000
144,000
2,134,000
2,134,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk Fiver
Government Building
Cash Balance - Beginning
Revenues:
Landfill expansion fee
Interest earnings
Total Revenues
Expenditures:
City hall - Roof replacement
Public Safety Building:
Roof replacement
Indoor range
Trott Brook Barn - Roof/windows
Phone system replacement
Debt Service -
2020B PW Building Bonds (Call 2/1/2029)
Total Expenditures
Revenues over/(under) Expenditures
Cash Balance - Ending
* Debt service transition to tax levy
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$4,593,009
$4,388,814
$6,206,494
$7,946,174
$9,930,133
2,100,000
80,500
2,180,500
1,000,000
800,000
150,000
40,000
394,695
2,384,695
(204,195)
$4,388,814
2,125,000
2,150,000
2,175,000
2,200,000
88,000
124,000
198,654
248,253
2,213,000
2,274,000
2,373,654
2,448,253
-
144,000
-
-
395,320
390,320
389,695
393,195
395,320
534,320
389,695
393,195
1,817,680
1,739,680
1,983,959
2,055,058
$6,206,494
$7,946,174
$9,930,133
$11,985,191
Capital Improvement Plan
City of Elk River, Minnesota
Project # BL-01
Project Name City Hall -Roof Replacement
Description
City Hall roof replacement
2023 thru 2027
Justification I
City hall roof is beyond its 20 year life expectancy and repairs are needed more frequently.
Department Public Buildings
Contact Facilities Maintenance Supt.
Type Building
Useful Life 20 years
Category Buildings
Expenditures 2023 2024 2025 2026 2027 Total
Buildings 1,000,000 1,000,000
1,000,000 1,000,000f
Funding Sources 2023 2024 2025 2026 2027 Total
Government Buildings 1,000,000 1,000,000
1,000,000 1,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
BL-02
Public Safety Building - Roof Replacement
2023 2027
Public safety building partial roof replacement on existing section of the building
Department Public Buildings
Contact Facilities Maintenance Supt.
Type Building
Useful Life 20 years
Category Buildings
.fustification
The roof of the public safety building is past its life expectancy and roof repairs are required more frequently with sections starting to pull away
from the side walls of the building.
Expenditures
Buildings
Funding Sources
Government Buildings
2023 2024 2025 2026 2027 Total
800,000 800,000
800,000 800,000
2023 2024 2025 2026 2027 Total
800,000 800,000
800,000 800,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # BL-04
Project Name Public Safety Building - Indoor Range
Description I
Upgrade the indoor firing range at the public safety building
2023 2027
Public Safety Building
Police Chief
Maintenance
15 years
Building Maintenance
Justification
The indoor range used by the police department is nearing 20 years old and there is a need to upgrade the equipment and rail system to current
standards. The indoor range is vital to the training and qualification of police officers as required by the MN POST board.
Expenditures 2023 2024 2025 2026 2027 Total
Building Maintenance 150,000 150,000
Total 150,000 150,000
Funding Sources 2023 2024 2025 2026 2027 Total
Government Buildings 150,000 150,000
Total 150,000 150,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
City of Elk River, Minnesota
Project # BL-06
Project Name Trott Brook Barn - Roof/Windows Replacement
Description
Trott Brook Barn roof and window replacement
Justification I
The shingles are in need of replacement and several windows are broken or with rotting window frames.
Department Public Buildings
Contact Facilities Maintenance Supt.
Type Building
Useful Life 20 years
Category Buildings
Expenditures 2023 2024 2025 2026 2027 Total
Buildings 40,000 40,000
40,000 40,000
Funding Sources 2023 2024 2025 2026 2027 Total
Government Buildings 40,000 40,000
40,000 40,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # BL-10
Project Name Phone System
Description
Phone system replacement
2023 thru 2027
Department
Technology/Communications
Contact
IT Manager
Type
Equipment
Useful Life
10 years
Category
Technology
The phone system was installed in 2015 and is scheduled for replacement due to technology and communication advancements.
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 180,000 180,000
Total 180,000 180,000
Funding Sources 2023 2024 2025 2026 2027
ERMU 36,000 36,000
Government Buildings 144,000 144,000
180,000 180,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 dmi 2027
PROJECTS BY FUNDING SOURCE
Source Project #
2023
2024
2025
2026
2027
Total
County Projects - Cost Share
i
11-20
250,000
250,000
YAC - Park Accessories
PDF 23-1
202,000
202,000
Rivers Edge Dock - Camera System
PDF 23-2
9,100
9,100
Ninja/Fitcore Playground - Lions Park
PDF 24-1
280,000
280,000
Trail Development
PF-64
370,000
370,000
Park Dedication Total
211,100
900,000
1,111,100
Park Improvement
Athletic Field Master Plan
PIF 23-1
45,000
45,000
Playground - Lions Park
PIF 23-2
200,000
200,000
Park Improvement - Miscellaneous
PIF 23-27
25,750
16,250
16,250
16,250
10,000
84,500
Storage Garage - Woodland Trails
PIF 23-4
150,000
150,000
Playgrounds - Country Crossingfrrott Brook
PIF 24-1
250,000
250,000
Basketball Court - Kliever Lake Fields
PIF 24-2
50,000
50,000
Basketball Courts - Deerfield/Ridgewood
PIF 25-1
80,000
80,000
Nature Play - Woodland Trails
PIF 25-2
75,000
75,000
Playground/Basketball Court - Riverplace
PIF26-1
185,000
185,000
Lions Park Shelters
PIF 26-2
300,000
300,000
Playgrounds - Fresno/Mississippi Oaks
PIF 27-1
190,000
190,000
Rivers Edge Park Fountain
PIF 27-2
75,000
75,000
Park Improvement Total
420,750
316,250
171,250
501,250
275,000
1,684,500
GRAND TOTAL
631,850
1,216,250
171,250
501,250
275,000
2,795,600
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River
Park Dedication Fund
Cash Balance - Beginning
Revenues:
Park dedication
Sale of property - Pinewood CD
Interest
Total Revenues
Expenditures:
Ninja/Fitcore system
YAC - shade structure
YAC - park maintenance garage
Rivers Edge Dock - camera system
Trail Development
CR 44 Trail - Local cost share
Total Expenditures
Revenues over/(under) Expenditures
Cash Balance - Ending
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$1,582,311
$1,577,491
$883,771
$1,078,051
$1,275,831
150,000
150,000
150,000
150,000
150,000
28,780
28,780
28,780
28,780
28,780
27,500
27,500
15,500
19,000
22,500
206,280
206,280
194,280
197,780
201,280
-
280,000
-
-
-
142, 000
-
-
-
-
60,000
-
-
-
-
9,100
-
-
-
-
-
370,000
-
-
-
-
250,000
-
-
-
211,100
900,000
-
-
-
(4,820)
(693,720)
194,280
197,780
201,280
$1,577,491
$883,771
$1,078,051
$1,275,831
$1,477,111
City of Elk River
Park Improvement Fund
Cash Balance - Beginning
Revenues:
Interest Income
Youth Football - Oak Knoll Lights
Lacrosse - Oak Knoll Lights
Sponsorships
Transfer In -Liquor Fund
Total Revenues
Expenditures:
Athletic fields demand analysis/master plan
WHHCA Friends of the Mississippi partnership
Great Northern Trail regional master plan
Country Crossing playground
Deerfield basketball court
Lions Park playground
Ridgewood basketball court
Riverplace - playground/basketball court
Trott Brook playground
Kliever Lake Fields - basketball court
Woodland Trails storage garage
Woodland Trails nature play area
Misc. projects
Lions Park Shelters replacements (3)
Fresno Park Playground
Mississippi Oaks Playground
Rivers Edge Park fountain
Total Expenditures
Revenues over/(under) Expenditures
Cash Balance - Ending
Parks Commission Recommended 10-5-22
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$194,237
$52,653
$103
$87,053
($162,697)
3,500
1,000
-
1,500
-
7,416
-
-
-
-
4,450
4,450
4,450
-
-
13,800
8,250
3,750
-
-
250,000
250,000
250,000
250,000
250,000
279,166
263,700
258,200
251,500
250,000
45,000
-
-
-
-
6,250
6,250
6,250
6,250
-
9,500
-
-
-
-
-
125,000
-
-
-
-
-
50,000
-
-
200,000
-
-
-
-
-
-
30,000
-
-
-
-
-
185,000
-
-
125,000
-
-
-
-
50,000
-
-
-
150,000
-
-
-
-
-
-
75,000
-
-
10,000
10,000
10,000
10,000
10,000
-
-
-
300,000
-
-
-
-
-
100,000
-
-
-
-
90,000
-
-
-
-
75,000
420,750
316,250
171,250
501,250
275,000
(141,584)
(52,550)
86,950
(249.750)
(25.000)
$52,653
$103
$87,053
($162,697)
($187,697)
Capital Improvement Plan
City of Elk River, Minnesota
Project# PDF 23-1
Project Name YAC -Park Accessories
Description
Shade structure - $142,000
Park maintenance garage - $60,000
Justification
Acquisition, development, or improvement of the city's park systems.
2023 thru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
Unassigned
Category
Park Improvements
Expenditures
2023 2024 2025 2026 2027
Improvements
202,000
202,000
Funding Sources
2023 2024 2025 2026 2027
Park Dedication
202,000
202,000
Total
202,000
Total
202,000
202,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Prof PDF 23-2
Projej Rivers Edge Dock - Camera System
Description I
Camera system for the dock at Rivers Edge Commons Park
Security camera system to monitor the downtown dock area.
2023 thru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Equipment
Useful Life
7 years
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 9,100 9,100
Total 9,100 9,100
Funding Sources 2023 2024 2025 2026 2027 Total
Park Dedication 9,100 9,100
Total 9,100 9,100
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# PDF 24-1
Project Name Ninja/Fitcore Playground
Description
Ninja/Fitcore playground system
Justification I
Acquisition, development, or improvement of the city's park systems.
Expenditures
Improvements
Funding Sources
Park Dedication
2023 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Equipment
Useful Life
Category
Playground Equipment
2023 2024 2025 2026 2027 Total
280,000 280,000
280,000 280,000
2023 2024 2025 2026 2027 Total
280,000 280,000
280,000 280,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PIF 23-1
Project Name Athletic Field Master Plan
Description
Athletic fields master plan
2023 thru 2027
Department Park Improvement
Contact Park & Rec. Director
Type Study
Useful Life Unassigned
Category Park Improvements
Determine the community needs and usage of the city's athletic fields and develop a master plan based on the demand analysis.
Expenditures
Design
Funding Sources
Park Improvement
2023 2024
2025 2026 2027 Total
45,000
45,000
45,000
45,000
2023 2024
2025 2026 2027 Total
45,000
45,000
45,000
45,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
2023 thru 2027
Department
Park Improvement
City of Elk River, AUnnesota
Contact
Park & Rec. Director
Proje PIF 23-2
Type
Equipment
Useful Life
15 years
Proje= Playground - Lions Park
Category
Playground Equipment
Description
Update playground at Lion John Weicht Park
Justification I
Annual maintenance/repairs of our park system.
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 200,000 200,000
200,000 200,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 200,000 200,000
200,000 200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# PIF 234
Project Name Storage Garage - Woodland Trails
Description
Construction of storage garage
2023 thru 2027
Justification I
Storage garage for equipment used for the maintenance of Woodland Trails Regional Park.
Department
Park Improvement
Contact
Park & Rec. Director
Type
Building
Useful Life
25 years
Category
Buildings
Expenditures 2023 2024 2025 2026 2027 Total
Buildings 150,000 150,000
150,000 150,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 150,000 150,000
150,000 150,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 ^`hru 2027
Department Park Improvement
City of Elk River, Minnesota Contact Park & Rec. Director
Type Unassigned
Project # PIF 23-27 Useful Life Unassigned
Project Name Park Improvement -Miscellaneous Category Park Improvements
Description
WHHCA - Friends of the Mississippi partnership - $6,250
Great Northern Trail master plan - $9,500
Miscellaneous park projects - $10,000
I
Various park improvement expenditurces
Expenditures
2023
2024
2025
2026
2027
Total
Other
25,750
16,250
16,250
16,250
10,000
84,500
25,750
16,250
16,250
16,250
10,000
84,500
Funding Sources
2023
2024
2025
2026
2027
Total
Park Improvement
25,750
16,250
16,250
16,250
10,000
84,500
25,750
16,250
16,250
16,250
10,000
84,500
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023
City of Elk River, Minnesota
Project# PIF 24-1
Project Name Playgrounds - Country Crossing/Trott Brook
Description
Replace playgrounds at Country Crossing and Trott Brook parks
Justification !
Annual maintenance/repairs of our park system.
2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Equipment
Useful Life
15 years
Category
Playground Equipment
Expenditures 2023 2024 2025 2026 2027
Equipment 250,000 250,000
250,000 250,000
Funding Sources 2023 2024 2025 2026 2027
Park Improvement 250,000 250,000
250,000 250,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PIF 24-2
Project Name Basketball Court - Kliever Lake Fields
Description
Replace basketball court at Kliever Lake Fields
Justification
Annual maintenance/repairs of our park system.
Expenditures
Improvements
Total
Funding Sources
Park Improvement
2023 thru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
2023 2024 2025 2026 2027 Total
50,000 50,000
50,000 50,000
2023 2024 2025 2026 2027 Total
50,000 50,000
50,000 50,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
.�Iroject# PIF 25-1
Project11, Basketball Courts - Deerfield/Ridgewood
Description I
Replace basketball courts at Deerfield and Ridgewood parks
Justification I'
Annual maintenance/repairs of our park system.
2023 thru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
Expenditures 2023 2024 2025 2026 2027 Total
Improvements 80,000 80,000
^a#mil 80,000 80,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 80,000 80,000
80,000 80,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
Department Park Improvement
City of Elk River, Minnesota Contact Park & Rec. Director
Type Improvement
Project # PIF 25-2 Useful Life 15 years
Project Name Nature Play -Woodland Trails Category Park Improvements
Description
Construct nature play area at Woodland Trails Regional Park
Annual maintenance/repairs of our park system.
Expenditures 2023 2024 2025 2026 2027 Total
Improvements 75,000 75,000
75,000 75,000
Funding Sources 2023 2024 2025 2026 2027 Total
Park Improvement 75,000 75,000
75,000 75,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
PIF 26-1
'roject i Playground/Basketball Court - Riverplace
Description
Replacement of playground equipment and basketball court
.Justification
Annual maintenance/repairs of our park system.
2023 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
15 years
Category
Park Improvements
Expenditures
2023 2024 2025 2026 2027
Total
Equipment
125,000
125,000
Improvements
60,000
60,000
185,000
185,000
Funding Sources
2023 2024 2025 2026 2027
Park Improvement
185,000
185,000
185,000
185,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PIF 26-2
Project Name Lions Park Shelters
Description
Replace park shelters (3) at Lion John Weicht Park
Justification 1
Annual replacementlimprovement of our park system.
Expenditures
Improvements
Funding Sources
Park Improvement
2023 �hru 2027
Department
Park Improvement
Contact
Park & Rec. Director
Type
Improvement
Useful Life
20 years
Category
Park Improvements
2023 2024 2025 2026 2027 Total
300,000 300,000
300,000 300,000
2023 2024 2025 2026 2027 Total
300,000 300,000
300,000 300,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PIF 27-1
Project Name Playgrounds - Fresno/Mississippi Oaks
2023 thru 2027
Description
Replace playgrounds at Fresno ($100,000) and Mississippi Oaks ($90,000) parks
Justification I
Annual replacement/improvement of our park system.
Department
Park Improvement
Contact
Park & Rec. Director
Type
Equipment
Useful Life
15 years
Category
Playground Equipment
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 190,000 190,000
190,000 190,000
Funding Sources 2023 2024 2025 2026 2027
Park Improvement 190,000 190,000
190,000 190,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
Department Park Improvement
City of Elk River, Afinnesota Contact Park & Rec. Director
PIF 27-2
Rivers Edge Park Fountain
Description I
Replace fountain at Rivers Edge Park
Justification
Annual replacement/improvement of our park system.
Expenditures
Improvements
Funding Sources
Park Improvement
1023-2027 CAPITAL IMPROVEMENT PLAN
Type Improvement
Useful Life 15 years
Category Park Improvements
2023 2024 2025 2026 2027 Total
75,000 75,000
75,000 75,000
2023 2024 2025 2026 2027 Total
75,000 75,000
75,000 75,000
City of Elk River, Minnesota
Capital Improvement Plan
2023 thru 2027
PROJECTS BY FUNDING SOURCE
Source Project # 2023 2024 2025 2026 2027 Total
Municipal State Aid
Hwy 169 FrontagelBackage Road Improvements
11-01
750,000
750,000
Kelley PkwylTwin Lakes Rd/TH 10 Intersection
11-08
3,000,000
3,000,000
County Projects - Cost Share
11-20
1,520,000
1,520,000
Trail Development
PF-64
450,000
450,000
Municipal State Aid Total
1,970,000
3,750,000
5,720,000
'Pavement Management
Hwy 169 FrontageBackage Road Improvements
11-01
750,000
750,000
169 Redefine
11-03
1,507,000
1,507,000
County Projects - Cost Share
11-20
750,000
750,000
Pavement Management - Streets
PM-01
3,850,000 300,000
3,600,000 300,000 3,000,000
11,050,000
Pavement Management -Parking Lots/Trails
PM-02
350,000 200,000
350,000 200,000 350,000
1,450,000
Pavement Management Total
4,200,000 2,757,000
4,700,000 500,000 3,350,000
15,507,000
169 Redefine
11-03
1,000,000
1,000,000
Wastewater- Urban Services Expansion
WW-23
16,850,000
16,850,000
Trunk Utility Fund Total
1,000,000
16,850,000
17,850,000
GRAND TOTAL
4,200,000 5,727,000 25,300,000 500,000 3,350,000 39,077,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River
Pavement Management Fund
Cash Balance - Beginning
Revenues:
Charges for Services -
Franchise Fee
Other Revenue -
Interest
MSA - Street Maintenance
Total Revenues
Exrenditures:
Street Projects
Hwy 169 Project
County Projects - cost share
Sealcoat/Overlay program
Parking Lots
Trails
Total Expenditures
Revenues less Expenditures
Cash Balance - Ending
Beginning balance
New Allotment (average)
Allocations:
County Projects - Local cost share
Trail Development
Hwy 169 Frontage/Backage Roads
Kelley Pkwy/Twin Lakes Rd/Th 10
Total Allocations
Ending Balance
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$6,884,375
$4,819,875
$4,177,375
$1,598,875
$3,188,875
1,557,000
1,573,000
1,589,000
1,605,000
1,621,000
137,500
96,500
83,500
32,000
64,000
441,000
445,000
449,000
453,000
458,000
2,135,500
2,114,500
2,121,500
2,090,000
2,143,000
3,650,000
100,000
3,400,000
100,000
2,800,000
-
1,507,000
750,000
-
-
-
750,000
-
-
-
200,000
200,000
200,000
200,000
200,000
350,000
-
350,000
-
350,000
-
200,000
-
200,000
-
4,200,000
2,757,000
4,700,000
500,000
3,350,000
(2,064,500)
(642,500)
(2,578,500)
1,590,000
(1,207,000)
$4,819,875
$4,177,375
$1,598,875
$3,188,875
$1,981,875
Municipal State Aid - Construction Balance
2023 2024 2025
S 2,256,563 $ 4,022,722 $ 3,853,722
1,766,159 1,801,000 1,837,000
2026
$ 1.947,722
1,874,000
2027
5 3,814,722
1,911,000
(1,520,000) - - -
(450,000) - - -
(750,000) - -
(3,000,000 i - -
(1,970,000) (3,750,000) - -
$4,022,722 $3,853,722 $1,940,722 $3,814,722 $5,725,722
"=State -aid roads portion of pavement management plan
City of Elk River
Trunk Utility Fund
Cash Balance - Beginning
Revenues:
Special Assessments
Interest
Total Revenues
Expenditures:
Hwy 169 utility modifications
NE & NW urban services expansion
Total Expenditures
Revenues over/(under) Expenditures
Cash Balance - Ending
2023
2024
2025
2026
2027
Estimate
Estimate
Estimate
Estimate
Estimate
$1,861,014
$1,984,314
$1,109,614
($15,627,586)
($15,536,786)
90,800
90,800
90,800
90,800
90,800
32,500
34,500
22,000
-
-
123,300
125,300
112,800
90,800
90,800
1,000,000 - - -
- 16,850,000
1,000,000 16,850,000 - -
123,300 (874,700) (16,737,200) 90,800 90,800
$1,984,314 $1,109,614 ($15,627,586) ($15,536,786) ($15,445,986)
Proposed 2023 Improvements
Reconstruct 0.8 miles
0 0.5 1
Miles
Capital Improvement Plan
City of Elk River, Minnesota
Project # PM-01
Project Name Pavement Management - Streets
2023 thru 2027
Department
Infrastructure Improvements
Contact
Public Works Director
Type
Improvement
Useful Life
25 years
Category
Street Construction
Description a
Preventative maintenance on our streets includes sealcoating, crackfilling and small overlay projects.
Street improvement projects to replace, overlay or rehabilitate aged and deteriorated streets, storm drainage, and adjacent walks will be completed
every other year.
Justification I
Individual street pavement conditions will dictate what pavement management technique will be utilized to extend the life of that specific street
segment. These techniques may range from preventative maintenance to a full reconstruction of the surface and aggregate base. As they are
implemented, the prescribed techniques will continually be gauged to assure their performance is proper in extending the life of our pavements.
Expenditures
2023
2024
2025
2026
2027
Total
Design
100,000
100,000
200,000
Construction
3,700,000
3,500,000
3,000,000
10,200,000
Maintenance
200,000
200,000
200,000
200,000
800,000
3,900,000
300,000
3,700,000
300,000
3,000,000
11,200,000
Funding Sources
2023
2024
2025
2026
2027
Pavement Management Fund
3,860,000
300,000
3,600,000
300,000
3,000,000
11,050,000
Storm Water
50,000
100,000
150,000
3,900,000
300,000
3,700,000
300,000
3,000,000
11,200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
City of Elk River, Minnesota
PM-02
Pavement Management - Parking Lots/Trails
Overlay and sealcoat public parking lots and trails as needed
Department
Infrastructure Improvements
Contact
Public Works Director
Type
Maintenance
Useful Life
15 years
Category
Street Maintenance
Projects will be prioritized based on condition and available funding after all street maintenance project needs are met.
Expenditures
2023
2024
2025
2026
2027
Total
Parking Lot
350,000
350,000
350,000
1,050,000
Trails
200,000
200,000
400,000
350,000
200,000
350,000
200,000
350,000
1,450,000
Funding Sources
2023
2024
2025
2026
2027
Total
Pavement Management Fund
350,000
200,000
350,000
200,000
350,000
1, 5-0, 000
350,000
200,000
350,000
200,000
350,000
1,450,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
Department Infrastructure Improvements
City of Elk River, AEnnesota Contact Public Works Director
II-20 Type Infrastructure
Useful Life 25 years
County Projects - Cost Share
Category Street Construction
Description.
City share of county projects include:
1) CR 33 Realignment and future trail preparation ($2,000,000 less $480,000 county tumback)
2) CR 44 Reconstruction and Trail
City participation in projects initiated by Sherburne County.
Expenditures 2023
2024 2025
2026 2027
Improvements
2,520,000
2,520,000
ew
2,520,000
2,520,000
Funding Sources 2023
2024 2025
2026 2027 Total
Municipal State Aid
1,520,000
1,520,000
Park Dedication
250,000
250,000
Pavement Management Fund
750,000
750,000
00tal
2,520,000
2,520,000
2023-2027 CAPITAL IMPROVEMENT PLAN
2023 thru 2027
City of Elk River, Minnesota
II-03
169 Redefine
Department Infrastructure Improvements
Contact Public Works Director
Type Infrastructure
Useful Life 25 years
Category Street & Utility Construction
Local cost share for MNDOT project to reconstruct TH 169 through Elk River, including sewer modifications.
Justification !
Safety and mobility improvement to the TH 169 corridor and provide better local connection across the highway. Visual quality enhanced railings,
street lights, plantings, colors and textures of the final elements of the TH 169 project.
Expenditures
Improvements
Funding Sources
Pavement Management Fund
Trunk Utility Fund
2023 2024 2025 2026 2027 Total
2,507,000 2,507,000
2,507,000 2,507,000
2023 2024 2025 2026 2027
1,507,000 1,507,000
1,000,000 1,000,000
2,507,000 2,507,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 rhru 2027
City of Elk River, Minnesota
Project # II-01
Project Name Hwy 169 FrontageBackage Road Improvements
Department
Infrastructure Improvements
Contact
Public Works Director
Type
Infrastructure
Useful Life
25 years
Category
Street Construction
Description
Design and implement improvements to the frontage and backage road system east and west of the Hwy 169 Redefine project
Justification i
Improvements to the local road connections to Hwy 169 to assure the successful completion of connecting commercial uses on the east side of
Hwy 169 from Main Street to Dodge Avenue.
Expenditures 2023 2024 2025 2026 2027 Total
Construction 1,500,000 1,500,000
1,500,000 1,500,000
Funding Sources 2023 2024 2025 2026 2027 Total
Municipal State Aid 750,000 750,000
Pavement Management Fund 750,000 750,000
1,500,000 1,500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 thru 2027
City of Elk River, Minnesota
II-08
Kelley Pkwy/Twin Lakes Rd/TH 10 Intersection
Department
Infrastructure Improvements
Contact
Public Works Director
Type
Improvement
Useful Life
25 years
Category
Street Construction
Complete frontage road Kelley Parkway and Twin Lakes Road extension to new signalized intersection on TH 10/169 at 168th Avenue
System expansion and access control on TH 10/169 corridor from 171st Avenue to 165th Avenue.
Expenditures
Construction
Funding Sources
Federal Grant
MnDOT Cooperative Funds
Municipal State Aid
Special Assessments
2023 2024 2025 2026 2027
6,500,000 6,500,000
6,500,000 6,500,000
2023 2024 2025 2026 2027
2,000,000 2,000,000
1,000,000 1,000,000
3,000,000 3,000,000
500,000 500,000
6,500,000 6,500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # PF-64
Project Name Trail Development
2023 thru 2027
Description
Trail extensions and ADA improvements on the following road segments:
1) Cleveland St NW (CR 40) - CR 12 to south of Twin Lakes Pkwy
2) Mississippi Rd NW (CR 30) - Troy St NW to Naples St NW
3) Mississippi Rd NW (CR 30) - Denver St NW to Orono Rd NW
4) Twin Lakes Rd NW - Twin Lakes Pkwy to Cleveland Rd NW
Department
Park improvement
Contact
Public Works Director
Type
improvement
Useful Life
20 years
Category
Trail improvements
Justification I
Trail exptensions and ADA improvements allow for increased options of multi -modal transportation and create a safer path for users to bike, walk,
and roll. These extensions fill in gaps in the current city trail system along the county road system.
Expenditures
Trails
Funding Sources
Federal Grant
Municipal State Aid
Park Dedication
2023 2024
1,650,000
1,650,000
2023 2024
830,000
450,000
370,000
1,650,000
2025 2026 2027
2025 2026 2027
Total
1,650,000
1,650,000
Total
830,000
450,000
370,000
1,650,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Flan
City of Elk River, Minnesota
Project WW-23
Project Name Wastewater - Urban Services Expansion
2023 °hru 2027
Department
Sewer Department
Contact
Public Works Director
Type
Infrastructure
Useful Life
Unassigned
Category
Plant Expansion
Descriptior
Trunk system upgrades and expansion including headworks, receiving, regional lift stations, forcemains, and gravity sewer.
Justification I
Continued improvements to support future development in the expanded urban service area (NE & NW areas of the city).
Expenditures 2023 2024 2025 2026 2027
Improvements 13,350,000 13,350,000
Utilities 16,850,000 16,850,000
30,200,000 30,200,000
Funding Sources 2023 2024 2025 2026 2027
Sewer Fund 13,350,000 13,350,000
Trunk Utility Fund 16,850,000 16,850,000
30,200,000 30,200,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital ImpYow
2023 thru 2027
PROJECTS BY FUNDING SOURCE
Source Project# 2023 2024 2025 2026 2027 Total
I
Fire - Engines/Ladders FD-03 2,000,000 800,000 2,800,000
Fire - Bum Building FD-07 500,000 500,000
Business Center Drive Extension 11-35 700,000 700,000
Yet To Be Determined Total 3,200,000 800,000 4,000,000
GRAND TOTAL 3,200,000 800,000 4,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# FD-03
Project Name Fire - Engines/Ladders
Description
2023 - #419 - 1990 Pierce Ladder
2025 - #416 - 2005 Pierce Engine 2
2023 thru 2027
Justification
Based on annual condition assessment. The fire engines/ladders are the primary front-line response units.
Department
Fire
Contact
Fire Chief
Type
Vehicle
Useful Life
20 years
Category
Vehicles
Expenditures 2023 2024 2025 2026 2027 Total
Vehicles 2,000,000 800,000 2,800,000
2,000,000 800,000 2,800,000
Funding Sources 2023 2024 2025 2026 2027
Yet To Be Determined 2,000,000 800,000 2,800,000
2,000,000 800,000 2,800,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
FD-07
Fire - Burn Building
Fire bum building for training
2023 thru 2027
Department
Fire
Contact
Fire Chief
Type
Building
Useful Life
25 years
Category
Buildings
Justification
For the continued required training for firefighters to have live fire training. Acquiring residential structures are no longer a long-term solution and
the lack of live fire training is making the job of firefighting unsafe.
Expenditures 2023 2024 2025 2026 2027 Total
Buildings 500,000 500,000
500,000 500,000
Funding Sources 2023 2024 2025 2026 2027 Total
Yet To Be Determined 500,000 500,000
500,000 500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project ii II-35
Project Name Business Center Drive Extension
Pending Developer Project
2023 2027
Department
Infrastructure Improvements
Contact
Planning Manager
Type
Infrastructure
Useful Life
25 years
Category
Street Construction
Description
Extend Business Center Drive from Waco Street west to Big Lake Township
Justification
The project will complete a long planned connection of a frontage road system from Waco Street to Big Lake Township to better serve
transportation needs in the area. The project will further complete a water system loop and add sewer service to an unserved developable parcel.
Expenditures
2023 2024 2025 2026
2027
Design/Construction
700,000
700,000
700,000
700,000
Funding Sources
2023 2024 2025 2026
2027
Yet To Be Determined
700,000
700,000
700,000
700,000
2023-2027 CAPITAL IMPROVEMENT PLAN
City of Elk River, Minnesota
Capital Improvement Plan
2023 thm 2027
PROJECTS BY FUNDING SOURCE
Source Project # 2023 2024 2025
FTCenter I
FTCenter - Zamboni FTC-02 202,000
FTCenter Total 202,000
Liquor Fund
Northbound Liquor - Monument Sign
LS-01
Liquor Fund Total
Sewer Fund
Wastewater - Vehicle
WW-06
Wastewater - Equipment
WW-12
Wastewater - Lift Station Improvements
WW-19
Wastewater - Clarifier Lining
WW-20
Wastewater - Urban Services Expansion
WW-23
Wastewater - Centrifuge Installation
WW-24
Sewer Fund Total
Storm Water
Pavement Management - Streets
PM-01
Stormwater Projects
STW-1
Morton Ave Drainage Improvements
STW-2
Storm Water Total
GRAND TOTAL
80,000
80,000
These projects have been
approved or were reviewed
during budget work sessions.
2026 2027 Total
202,000
202,000
80,000
80,000
65,000 65,000
30,000 200,000 230,000
146,000 55,000 55,000 55,000 55,000 366,000
90,000 90,000
13,350,000 13,350,000
63000,000 6,000,000
266,000 120,000 13,405,000 255,000 6,055,000 20,101,000
50,000 1003000 150,000
250,000 250,000 500,000
250,000 250,000
550,000 350,000 900,000
1,098,000 120,000 13,755,000 255,000 6,055,000 21,283,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# FTC-02
Project Name FTCenter - Zamboni
Description
Replace 2008 Zamboni
2023 thru 2027
Based on age and condition of equipment needed for ice operations maintenance of the FTCenter.
Expenditures 2023
Equipment 202,000
202,000
Funding Sources 2023
FTCenter 202,000
202,000
2024 2025 2026
Department
FTCenter
Contact
Multipurpose Facility Supt.
Type
Equipment
Useful Life
15 years
Category
Equipment
2027 Total
202,000
202,000
2024 2025 2026 2027 Total
202,000
202,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project # LS-01
Project Name Northbound Liquor - Monument Sign
Description
Northbound monument sign
2023 thru 2027
Department
Liquor Fund
Contact
Liquor Operations Manager
Type
Improvement
Useful Life
20 years
Category
Buildings
Justification
New monument sign for Northbound Liquor, with an updated logo, will need to be installed due to visibility related to the reconstruction of TH
169.
Expenditures 2023 2024 2025 2026 2027 Total
Improvements 80,000 80,000
80,000 80,000
Funding Sources 2023 2024 2025 2026 2027 Total
Liquor Fund 80,000 80,000
80,000 80,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# WW-06
Project Name Wastewater - Vehicle
Description
Pickup Truck
An additional pickup is needed due to current staffing.
2023 thru 2027
Department Sewer Department
Contact Chief Wastewater Operator
Type Vehicle
Useful Life 10 years
Category Vehicles
Expenditures 2023 2024 2025 2026 2027 Total
Vehicles 65,000 65,000
65,000 65,000
Funding Sources 2023 2024 2025 2026 2027 Total
Sewer Fund 65,000 65,000
65,000 65,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# WW-12
Project Name Wastewater - Equipment
Description
2023 - Sewer line rapid assessment tool (SL-RAT)
2026 - Sewer camera trailer
2023 thru 2027
Department Sewer Department
Contact Chief Wastewater Operator
Type Equipment
Useful Life 25 yews
Category Equipment
Justification
2023 - The SL-RAT allows for the inspection of 10,000-20,000 feet of sewer lines per day and maintenance efforts can be concentrated on cleaning
out the dirty lines since it is getting harder to jet half the sewer lines each year.
2026 - The sewer camera trailer, which is used frequently to televise sewer mains for preventative maintenance, was purchased in 2010 and is
starting to show signs of wear.
Expenditures 2023 2024 2025 2026 2027 Total
Equipment 30,000 200,000 230,000
30,000 200,000 230,000
Funding Sources 2023 2024 2025 2026 2027 Total
Sewer Fund 30,000 200,000 230,000
30,000 200,000 230,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan 2023 2027
Department Sewer Department
City of Elk River, Minnesota Contact Chief Wastewater Operator
Project# WW-19 Type Equipment
Useful Life 15 years
Project Name Wastewater - Lift Station Improvements category Equipment
Description 1
2023 - Chopper pumps for lift stations
2023-2027 - Arc flash safety lift station panels
2023 - Chopper pumps eliminate the debris that plugs the lift station pumps.
2023-2027 - The lift station panels are starting to age and with newer tecnologies the arc flash safety panels make it safer for the wastewater
operators.
Expenditures
2023
2024
2025
2026
2027
Total
Equipment
146,000
55,000
55,000
55,000
55,000
366,000
Total 146,000
55,000
55,000
55,000
55,000
366,000
Funding Sources
2023
2024
2025
2026
2027
Total
Sewer Fund
146,000
55,000
55,000
55,000
55,000
366,000
Total 146,000
55,000
55,000
55,000
55,000
366,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# WW-20
Project Name Wastewater - Clarifier Lining
2023 thru 2027
Description
Hiperline high performance lining to the concrete walls in the clarifier troughs.
Department Sewer Department
Contact Chief Wastewater Operator
Type Maintenance
Useful Life Unassigned
Category Sewer Maintenance
Justification I
Sand blast and spray with Spectrshield the concrete walls in the clarifier troughs that are starting to deteriorate.
Expenditures 2023 2024 2025 2026 2027 Total
Maintenance 90,000 90,000
90,000 90,000
Funding Sources 2023 2024 2025 2026 2027 Total
Sewer Fund 90,000 90,000
90,000 90,000
2023-2027 CAPITAL IMPROVEMENTPLAN
2023 thru 2027
City of Elk River, Minnesota
WW-24
Wastewater - Centrifuge Installation
i
Replace undersized screw presses with centrifuges
Department Sewer Department
Contact Chief Wastewater Operator
Type Improvement
Useful Life 25 years
Category Utilities
Justification
Original screw presses were undersized and are expected to be beyond capacity need of the wastewater treatment plant 30 years earlier than
designed.
Expenditures
Improvements
Funding Sources
Sewer Fund
2023 2024 2025 2026 2027 Total
6,000,000 6,000,000
6,000,000 6,000,000
2023 2024 2025 2026 2027 Total
6,000,000 6,000,000
6,000,000 6,000,000
2023-2027 CAPITAL IMPROVEMENT PLAN
2023 1hru 2027
City of Elk River, Minnesota
Project # STW-1
Project Name Stormwater Projects
Description
Bi-annual pond cleaning, stormwater repairs, BMP inventory.
2023 - Public shoreline improvements
2025 - Elk Park Center basin and Zane Street basin
Department
Storm Water
Contact
Storm Water Coordinator
Type
Maintenance
Useful Life
Unassigned
Category
Utilities
(Storm water infrastructure projects combined with street projects are included on the pavement management CIP sheet.)
Justification
These projects include the testing, removal, and disposal of sediment deposits from our stormwater ponds. This is needed to assure the storm water
system is functioning as designed and achieving the water quality standards of our NPDES permit.
The smaller stormwater repairs include minor pipe upsizing, culvert replacement, manhole and catch basin repairs and fixing of washout areas.
Expenditures
2023 2024
2025 2026
2027
Construction/Maintenance
250,000
250,000
500,000
250,000
250,000
500,000
Funding Sources
2023 2024
2025 2026
2027
Storm Water
250,000
250,000
500,000
250,000
250,000
500,000
2023-2027 CAPITAL IMPROVEMENT PLAN
Capital Improvement Plan
City of Elk River, Minnesota
Project# STW-2
Project Name Morton Ave Drainage Improvements
Description
Morton Avenue stormwater drainage improvements
2023 thru 2027
Department
Storm Water
Contact
Storm Water Coordinator
Type
Improvement
Useful Life
50 years
Category
Utilities
Justification I
Precipitation volume and intensity weather patterns have contributed to temporary street flooding at Morton Avenue north of Main Street that
spreads outside of the right-of-way.
Expenditures
Improvements
Funding Sources
Storm Water
2023 2024 2025 2026 2027 Total
250,000 250,000
250,000 250,000
2023 2024 2025 2026 2027 Total
250,000 250,000
250,000 250,000
2023-2027 CAPITAL IMPROVEMENT PLAN