5.2 ERMUSR 01-10-2023��i Elk River Municipal Utilities UTILITIES COMMISSION MEETING TO: FROM: ERMU Commission Chris Kerzman — Engineering Manager MEETING DATE: AGENDA ITEM NUMBER: January 10, 2023 5.2 SUBJECT: Field Services Facility Expansion Project Update ACTION REQUESTED: Approve Change Order #6 DISCUSSION: The attached change order is for movement of fencing on the east side of the site to avoid frost issues with the wetland, as well as removal of retaining block along the same line. ERMU expects the majority of the site work is done until frost is out of the ground. Fencing and security are installed to keep the site secure through the winter and two of the three gates are operational. Permanent railing delivery did not arrive on schedule, and RJM Construction is scheduling installation for after the commission meeting. We have moved all staff into the new building and continue to work with RJM on completion of punch list items. ATTACHMENT: • Change Order #6 Page 1 of 1 m