5.5 ERMUSR 05-09-2023Elk River Municipal Utilities UTILITIES COMMISSION MEETING TO: FROM: ERMU Commission Chris Kerzman — Engineering Manager MEETING DATE: AGENDA ITEM NUMBER: May 9, 2023 5.5 SUBJECT: Field Services Facility Expansion Project Change Order ACTION REQUESTED: Authorize approval of Change Order no. 7 DISCUSSION: The attached change order is for stormwater system revisions needed due to contaminated soils found at the south portion of the site. This change order was tracked as labor and materials with the site utilities contractor. Three sump pumps were installed at upstream structures to avoid installation into contaminated soil. Staff continues to work with RJM Construction on closeout items for the project, and RJM is mobilizing crews to finish sitework. If the weather cooperates, they are looking to have the remaining sitework done by early June. ACTION REQUESTED: Authorize the approval of the attached Change Order no. 7 ATTACHMENTS: • Change Order Request no. 7 for Stormwater Revisions Page IofI 114