6.1i ERMU 12-12-2023Elk River Municipal Utilities UTILITIES COMMISSION MEETING TO: FROM: ERMU Commission Chris Kerzman — Engineering Manager MEETING DATE: AGENDA ITEM NUMBER: December 12, 2023 6.1i SUBJECT: Staff Update ACTION REQUESTED: None DISCUSSION: • We continue to work with City of Elk River IT staff on expansion of the fiber loop to the northeast area of Elk River and have a project kickoff meeting with the contractor during the week of December 11. • We continue to work with DGR and WEG on design questions for the Otsego substation transformer, and still expect full review drawings in January of 2024. • We continue to work on the planning and design of the future East substation, which will be needed to support development in the southeast portion of our service territory. • We continue to assist with Advanced Metering Infrastructure system planning and setup as the first meters are installed. • We are expanding Multi Factor Authentication and have noticed an increase in spam and phishing emails recently. Page IofI 193