6.1i ERMUSR 02-13-20241i
Elk River -�---
Municipal Utilities UTILITIES COMMISSION MEETING
TO:
FROM:
ERMU Commission
Chris Kerzman — Engineering Manager
MEETING DATE:
AGENDA ITEM NUMBER:
February 13, 2024
6.1i
SUBJECT:
Staff Update
ACTION REQUESTED:
None
DISCUSSION:
• Installation of the expanded fiber loop is scheduled to begin during the week of
February 12.
• We continue to work on the planning and design of the future East substation, which
will be needed to support development in the southeast portion of our service territory.
Work continues on mapping verifications, and locators are adding GPS information for
water curb stops into the database. Winter mapping review and verifications are going
well.
Page 1 of 1
169