ERMUSR 03-12-2024 Special MeetingElk River
Municipal Utilities
1.0 CALL MEETING TO ORDER
SPECIAL MEETING OF THE
UTILITIES COMMISSION
March 12, 2024, 2:30 P.M.
Elk River City Hall Uppertown Conference Room
AGENDA
2.0 ANNUAL COMMISSIONER ORIENTATION
2.1 Conservation Improvement Program Presentation — Frontier Energy
3.0 ADJOURNMENT
Page 1 of 1
2
ElkRiv
Municipal Utilities
Energy Conservation and Optimization
FRONTIER
energy
PRESENTED AT MEETING
Agenda
• Introduction to CIP and ECO
• Overview of the law and requirements for consumer owned utilities
• ERMU CIP History
• ERMU 2024-2026 Conservation Plan
• Residential Programs
• Commercial Programs
Conservation Improvement Program (CIP)
• Minnesota Statue 216B.241
• Started in 1983 and low-income programs required in 1989
• An important energy resource and key customer engagement tool
• Modernized in 2021 with the Energy Conservation and Optimization Act (ECO Act)
• Goals
• Improved awareness and adoption of energy -efficient technologies
• Reduced energy costs for Minnesota households and businesses
• Increased profitability for Minnesota companies and industries
• Deferred costly utility infrastructure investments
• Decreased carbon dioxide emissions
• Conserved resources
CIP Benefits
• Utility Benefits
• Avoided cost of producing energy
• Delay investments in transmission and distribution upgrades
• Reduced wholesale power and capacity prices through Demand Reduction Induced Price Effects (DRIPE)
• Higher customer satisfaction
• Reduced customer disconnection costs
• Participant Benefits
• Decreased monthly bills
• Lower upfront costs through rebates
• Improvements to indoor air quality and moisture
• Auxiliary conservation such as reduced water consumption with some ENERGY STAR appliances
• Societal Benefits
• Environmental
• Economic
ECO Act Requirements
• Minnesota Statute 216B.2403
Baseline Requirements for Cooperatives and Municipalities
Overall Savings Rqmt,
Energy Conservation Rqmt,
Total Spending Goal
Low -Income Spending Rqmt
Program Year
kWh 1.5% of:
kWh 0.95% of:
1.5% of:
0.2% of:
2024-2026
2020-2022
2020-2022
2022 GOR
2020-2022 average
average sales
average sales
residential GOR
ERMU Minimum Goals
4,994,857
3,163,410
$634,500
$28,720
• Subd. 2. — Energy savings goal.
• 0.95% must come from energy conservation improvements
• The balance may be achieved by the following:
• Additional energy conservation improvements
• Electric utility infrastructure projects
• Fuel -switching improvements
ECO Act Requirements cont.
• Subd. 3. - Plans. Submit a three-year plan and report progress annually
• Subd. 4. — Investment. If savings goal is not met, then spending goal is a requirement.
• Subd. 5. — Low-income spending. Spending must be met annually from:
• Dedicated low-income programs
• Other residential programs spending and rate of low-income persons in the service territory
Spending Caps on Optional Investments
Optional Investment
Spending Cap
15% of Low -Income
Pre-Weatherization
Spending
R&D Activities
10% of minimum spending
Distributed and Renewable
5% of minimum spending
Generation (DRG) Programs
Efficient Fuel Switching
0.55% of GOR
Elk River CIP History - Energy Savings
6,000,000
5,000,000
4,522,151
4,133,512 4,166, 765
4,000,000
3,338,144
3,000,000
2,000,000
1,000,000
0
2016 2017
4,490,283
4,306,231
199,352
2018 2019
■ kWh Goal ■ kWh Achieved
4,734,571,597,290
2020
4,855,289 4,907,874
2021 2022
Elk River CIP History — Overall Spending
$600,000
$500,000 $468,933
$444,402
$400,000
$300,000
$200,000
$100, 000
$0
2016
$529,534
$385,824
2017
$502,230
0$419,776
$529,797
1$443,790
$513,645
$486,835
2018 2019 2020
■ Spending Goal ■ Spending Achieved
$547,350
$426,381
2021
$548,026
$414,513
2022
$80,000
$70,000
$60,000
$50,000
$40,000
$30,000
$20,000
$10,000
M
Elk River CIP History — Low Income Spending
$49,587
$21,247
2016
$39,458
$21,797$22,885 $22,793
$23,785$24,682 $25,403
$39,910
2017 2018 2019 2020
■ Low Income Spending Goal ■ Low Income Spending Achieved
$41,384
$26,134
2021
$74,557
$26,898
2022
$0.200
$0.180
$0.160
$0.140
$0.120
$0.100
$0.080
$0.060
$0.040
$0.020
$0.000
a
Elk River CI P History — Cost Effectiveness
$0.140
$0.108
2016
$0.117
$0.093
2017
$0.139
$0.117
$0.118
$0.105
.
2018 2019
■ Goal $/kWh ■ Actual $/kWh
$0.189
$0.113 ■ $0.112 $0.117
$0.108 $0.106
2020 2021 2022
ERMU 2024-2026 Plan
ERMU 2024-2026 Plans
Program
kWh Goal
Spending Goal
Low Income
Contribution
Low Income
741753
$33,214
$33,214
Residential Programs
5401640
$164,583
$64,681
Electric Vehicle Charging
0
$35,894
$0
Commercial Programs
3/369/131
$319,014
$0
Regulatory Costs
0
$39,417
$0
Distributed and Renewable Generation
0
$8,000
$0
Electric Utility Infrastructure
1/052/854
$0
$0
Research and Development
0
$18,000
$0
Load Management
0
$10,500
$41127
Tota 1:
5,037,378
$628,622
$102,022
ERMU Residential Programs
ERMU Residential Rebate Offerings
Category
Measure Name
Requirements
ERMU
Appliances
Clothes Dryer
Must be ENERGY STAR certified
$40.00
Appliances
Dehumidifier
Must be ENERGY STAR certified
$30.00
Appliances
Refrigerator/Freezer Recycling
$100.00
Appliances
Refrigerator/Freezer
Must be ENERGY STAR certified
$35.00
Appliances
Air Purifier
Must be ENERGY STAR certified
$35.00
Appliances
Ceiling Fan
Must be ENERGY STAR certified
$10.00
Appliances
Appliances
Appliances
Misc.
Misc.
Tier II Power Strip
NEEP Tier 2 Advanced Power Strip
$20.00
Clothes Washer
Dishwasher
Must be ENERGY STAR certified
Must be ENERGY STAR certified
Must have UEF of 2 or higher
$40.00
$40.00
$200.00
Variable Speed Pool Pump
Heat Pump Water Heater- 50-79 Gallon
$400.00
Misc.
Heat Pump Water Heater- >_80 Gallon
Must have UEF of 2 or higher
$450.00
Misc.
ECM Circulator Pumps
Specs must show ECM
$100, <_50% of fixture cost
Misc.
EV Charger
No Rebate
ERMU Residential Programs Cont.
ERMU Residential Rebate Offerings
Category
Measure Name
Requirements
ERMU
Heating & Cooling
Central AC - 16:5 SEER
AC only 16 SEER and higher
$125.00
Heating & Cooling
Mini Split Ductless 16!5 SEER AC Only
Ductless AC only 16 SEER and higher
$150.00
Heating & Cooling
Room Unit/Window AC
Must be ENERGY STAR certified
$10.00
Heating & Cooling
Central & Ductless Heat Pumps
Cold Climate Heat Pumps
Heating and Cooling over 15 SEER and
$400.00
Heating &Cooling
Heating and Cooling over 15 SEER and
over 9 HSPF. Also must have COP>=1.75 @
$1,000.00
Heating & Cooling
Ground Source Heat Pumps
Heating and Cooling over 15 SEER and
$600/Ton
$75.00
$40.00
Heating &Cooling
Central AC/ASHP Tune Up
Professional contractor invoice showing
tune up activity performed.
Heating & Cooling
WiFi Thermostat
NEEP Tier 2 Communicating
Heating & Cooling
Programmable Thermostat
NEEP Tier 1 Programmable
$20.00
Heating & Cooling
Replacement Furnace w/ ECM Blower Motor
Specs must show ECM
$150.00
Lighting
Ceiling Fan w/ Integral LED Light
Must be ENERGY STAR certified
$20.00
Lighting
Screw -in Bulb
Must be LED
$2/lamp, <_50% of fixture cost
Lighting
Outdoor Fixture
Must be LED
$15/fixture, <_50% of fixture cost
Lighting
Holiday Lighting
Must be LED
Must be LED
Control on occupancy, timer, or daylight
harvesting
$10/string, <_50% of fixture cost
Lighting
Custom Lighting
$0.20/watt reduced, <_50% of
fixture cost
Lighting
Lighting Controls
$15/control, :550% of fixture cost
ERMU Commercial Programs
• Commercial and industrial energy audits
• Project savings and payback analysis
• New construction plan reviews
• Design assistance
• Custom energy rebates @ $0.035/kWh
• Custom and Specialized Lighting
• HVAC and Controls
• Data Centers/IT Equipment
• Industrial Process
• Refrigeration
• Food Service Equipment
FRONTIER
energy
Tanuj Gulati
(612) 205-9241
TGulati@frontierenergy.com
Doug Eli
(76afrontierenergy.com
222-3039
Deli
Alexandra Blair
(906) 281-2898
Ablair@frontierenergy.com