5.5a EMRUSR 08-13-2024August 8, 2024 M4
Elk River Municipal Utilities
Attn: Mike Tietz
13069 Orono Parkway, PO Box 430 ENGINEERING
Elk River, MN 55330
RE: Award Recommendation
Furnishing an Electric Power Transformer — East Substation
DGR Project No. 429902
Dear Mike:
We have reviewed the bids received on August 1, 2024 for the above -referenced project. A bid
summary form of the bid results is enclosed. We have checked the bids for mathematical accuracy
and compliance with the bid specifications. We are hereby prepared to offer the following
recommendation.
There was one (1) responsive bid received with a total purchase price of $1,535,200.00. This bid
was submitted by WEG Transformers USA, LLC (WEG). WEG has successfully completed similar
projects for us in the past, and we know of no reasons why they would not perform well on this
project. WEG's price was comparable to low bidder pricing on recent DGR projects for similar
sized transformers. We are therefore recommending that WEG be awarded the contract for
Furnishing an Electric Power Transformer for a total purchase price of $1,535,200.00, contingent
on the successful negotiation of proposal clarifications, payment terms, and terms and conditions.
There was one (1) non -responsive bid received by Niagara Power Transformer Corporation
(Niagara). The specifications require that the power transformer be delivered by September 1,
2026, and Niagara quoted a delivery date in February 2027. Niagara failed to meet the required
delivery date listed in the specifications and thus their bid was determined to be non -responsive.
Please review our recommendation and feel free to contact us with any questions you or the
Board may have. Please let us know when an award has been made. We will be sending a copy
of the bid summary to all bidders and plan holders.
Best Regards,
DGR Engineering
Brenton Thompson, P.E.
Enclosure: Bid Summary
DGR Engineering — 1302 South Union Street — P.O. Box 511— Rock Rapids, IA 51246
phone: 712.472.2531 — fax: 712.472.2710 — dgr.com
q',, H7W ;M a up\ 1vx71nan, Y I" ws\l h Rcconii Con Imand Vo Ovvn m 4 °T`02.6x'x
7iWaW Vy ',
95
BID SUMMARY
FURNISHING AN ELECTRIC POWER TRANSFORMER - EAST SUBSTATION
ELK RIVER MUNICIPAL UTILITIES
ELK RIVER, MINNESOTA
(1)-15/20/25 MVA, ONAN/ONAF/ONAF @ 55" C
16.8/22.4/28 MVA, ONAN/ONAF/ONAF (a 65" C
DELTA - GRDY, 69-13.2/7.62 kV, w/LTC
ENGINEERING
1302 South Union Street
Rock Rapids, Iowa 51246
DGR Project No. 429902
Bid Letting:
August 1, 2024 - 2:00 PM
Page 1 of 1
BASE BID
Bidder and Address
Bid Security
Acknowledge
Delivery
Manufacturer /
Comments
o
( /o)
Addendum #1
Total Purchase Price (7C)
Total Eval. Price (8G)
Location
WEG Transformers USA, LLC
6350 WEG Drive
5% Bid Bond
Yes
$1,535,200.00
$1,708,967.00
July, 2026
Washington, MO
Washington, MO 63090
Niagara Power Transformer Corp
1755 Dale Road
5% Bid Bond
Yes
$1,369,945.00
$1,549,174.00
February, 2027
Buffalo, NY
Non -responsive bid: Failed meet the
delivery date required per the specifications.
Buffalo, NY 14225
*Specifications required delivery by Sept 1, 2026
Corrected Amount
P:\04\299\02\Doc\Spec\Xfmr\BidSum-XFMR ERMU 429902 Page 1 of 1