5.1 ERMUSR 03-11-2025UTILITIES COMMISSION MEETING TO:FROM: ERMU CommissionMark Hanson – General Manager MEETING DATE: AGENDA ITEM NUMBER: March 11, 20255.1 SUBJECT: ERMU Power Plant Project Update ACTION REQUESTED: Discuss project status BACKGROUND: At the August 13, 2024, commission meeting, the Commission discussed the future of the Elk River Municipal Utilities (ERMU) power plant. ERMU has maintained the existing power plant since its construction in 1947. Since 1978, however, ERMU has met all its power generation needs through a cooperative purchasing agency. Since then, the plant has been maintained for auxiliary purposes only. All five of ERMU’s substations are connected to multiple transmission lines and we have multiple distribution tie-lines between our substations providing highly resilient back-feeding capabilities. As such, due to the age and condition of the engines and their relatively low value as back-up operational assets, staff proposed the plant be decommissioned, the salvageable assets be sold, and the building be repurposed, potentially as a history/education center. The Commission officially decommissioned the plant at their September 10, 2024, meeting via Resolution 24-10 - Authorizing the Decommission of the ERMU Power Plant. DISCUSSION: Staff retained the services of LEO A DALY Architects to review the building’s structural integrity for repurposing as a potential history/education center, identify potential funding sources, explore potential design layouts, and estimate the potential construction costs. LEO A DALY will be presenting the results of their work to date at the meeting. The objectives of the presentation/discussion are: 1) Reach consensus and provide direction on the desired audience for a potential history/education center (students/children, organizations/adults, or a combination of both). The intended audience will influence the design layout. 2) Reach consensus and provide direction on the prioritization of costs vs architectural value. It will be considerably more expensive to keep the architectural features of the building such that it could be listed on the national register of historic places. ______________________________________________________________________________ Page 1 of 2 82 3)Reviewthe potential constructioncosts, offsets (e.g. grants, donations, sale of equipment), andresulting net financial commitmentrange. 4)Reach consensus and provide direction on whether to commit to the next step of the pre-design assessment. The next step would include: determining a buildinglayout, refining the cost estimates, and developing sufficient architectural renderings to pursue possible grant funding. Consulting fees for this next step are $15,000. 5) Reach consensus and provide direction on the desired financial recovery for the larger plant assets such as the fuel tanks, engines/generators, and power distribution equipment. Similarly, is the Commission interested in engaging with the City on a potential combined historical focus. NEXT STEPS: If desired, staff will continue working with LEO A Daly to complete Phase 2 of the pre-design assessment and pursue potential funding opportunities. Additionally, staff will continue working with peer agencies to dispose of the large equipment such as the fuel tanks, engines, and distribution equipment. ATTACHMENT: The Elk River Municipal Utilities Power Plant Building Pre-Design Assessment ______________________________________________________________________________ Page 2 of 2 83 ERMU Diesel Plant Pre-Design Assessment PRESENTED AT MEETING - LEO A DALY 1 4 2 5 3 6 9 8 7 9 7 43 2 1 8 56 PRESENTED AT MEETING - LEO A DALY Preliminary evaluation Historic features Evaluation of renovations required to bring building up to code Rough Order of Magnitude Cost Space Programming, Financing, & Grants Space program, bubble diagrams Project funding Next Steps 3 Scope of Work PRESENTED AT MEETING - LEO A DALY What We Did Code Analysis Restrooms ADA entrance Mechanical systems Historic Analysis Should be eligible for listing in the National Register – need SHPO determination Options for Programming Adult-centric Child-centric Combined Adult & Child-centric PRESENTED AT MEETING - LEO A DALY 5 Child Centric – Adult Centric - Combined PRESENTED AT MEETING - LEO A DALY Cost Estimate Estimate – $4,860,000 - $7,430,000* *This is an all-in number, including… Construction Costs (Base Bid and Alternates) Soft Costs (30% of Construction) 5% escalation (Compounding annually through 2026) Funding Sources Grants - $200,000 - $400,000 (6%) State Funding - $2,430,000 - $3,175,000 (max. 50%) Philanthropic - $892,500 - $1,627,500 (22%) ERMU Contributions (Remainder) - $1,069,200 - $1,634,600 (22%) Grant Funding State Funding Philanthropic Funding ERMU Contributions (Remainder) $0.2M - $0.4M 6% 22% $0.89M - $1.63M 22% $1.07M - $1.63M 50% $2.43M - $3.18M PRESENTED AT MEETING - LEO A DALY Next Steps o Refine One (1) Layout & Create Renderings o Refine Cost Estimate Possible Timeline PRESENTED AT MEETING - LEO A DALY 84 85 Table of Contents ........................................................ .................................................................. ......................................................... ................................................... ................ .............................................................. ................................................................ ........................................................ ................................................. .......................................... ..................... ................................................................ ........................... 86 87 88 89 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 90 9 9 91 10 10 92 93 94 95 96 97 98 99 11 11 100 12 12 101 13 1415 13 14 15 102 16 17 18 19 20 16 17 18 19 20 103 21 22 23 Examples of eligible projects include but are not limited to: adaptive uses of older and historic buildings into community gathering spaces, improvements to outdoor parks or trails, and technology projects for the public library. Funds may opu be used for: engineering and architectural plans or fees, salaries or annual operating expenses, or reimbursement for projects that are already completed. 21 22 23 104 105 Low High Base Bid Subtotal $ 1,750,000 $ 2,500,000 Add Alternates Subtotal $ 1,815,000 $ 2,945,000 Total Construction Cost $ 3,565,000 $ 5,445,000 Projected Soft Costs (30%) $ 1,069,500 $ 1,633,500 Total Project Cost (2025) $ 4,634,500 $ 7,078,500 Total Project Cost (2026) $ 4,866,225 $ 7,432,425 Total Project Cost (2027) $ 5,109,536 $ 7,804,046 Total Project Cost (2028) $ 5,365,013 $ 8,194,249 Total Project Cost (2029) $ 5,633,264 $ 8,603,961 106 107 Alternate #1 Allowance for interior finishes and buildout of main ADD $750,000 - $1,350,000 floor only (assumes roughly 7,700 SF). Alternate #2 Allowance for educational displays. ADD $100,000 - $200,000 Alternate #3 Allowance for signage and signage related lighting. ADD $50,000 - $100,000 Alternate #4 Allowance to provide (1) additional 20 Ton RTU ADD $30,000 - $50,000 (adds 1 new zone). Alternate #5 Allowance to include fire protection (wet system), if ADD $75,000 - $110,000 required by code. Alternate #6 Allowance to include fire alarm, if required by code. ADD $25,000 - $40,000 Alternate #7 Curtainwall glazing at 20' x 20' opening (to remove ADD $30,000 - $50,000 engines) in lieu of filling back in with CMU/brick. Alternate #8a Allowance to restore existing windows in lieu of ADD $125,000 - $175,000 existing to remain (assumes roughly 575 SF). Alternate #8b Allowance to replace existing windows in lieu of ADD $100,000 - $150,000 existing to remain (assumes roughly 575 SF). Alternate #9 Allowance for tuckpoint restoration of full existing ADD $175,000 - $250,000 building façade (assumes roughly 8,000 SF). Alternate #10 Allowance to reroof existing structure (assumes ADD $200,000 - $250,000 roughly 7,700 SF). Alternate #11 Allowance for an additional ADA entrance upgrade ADD $150,000 - $200,000 (per each). Assumes (2) new double door storefront entrance doors, associated storefront glazing, and 200 SF of concrete sidewalk/ramping and associated covered walkway. Alternate #12 Allowance for (4) new parking stalls (assumes ADD $20,000 - $40,000 restriping in existing paved areas in not achievable). Alternate #13 Allowance for landscaping upgrades. ADD $10,000 - $40,000 Alternate #14 Allowance to dispose of exterior exhaust ADD $75,000 - $90,000 piping/tanks. 108 109