6.1f ERMUSR 07-08-2025______________________________________________________________________________ Page 1 of 1 UTILITIES COMMISSION MEETING TO: ERMU Commission FROM: Chris Sumstad – Electric Superintendent MEETING DATE: July 8, 2025 AGENDA ITEM NUMBER: 6.1f SUBJECT: Staff Update ACTION REQUESTED: None DISCUSSION: • Installed 19 new residential services, which involves the connection of a secondary line once the customer requests service. • Safety Instructor Joe Schmidt from MMUA was here June 25-26 and held safety meetings for all staff on heat stress and biting bugs. He also performed bucket truck rescue training for staff that missed the original session. • Underground wire replacement continues in the Deerfield Addition. Crews are currently installing on Yale Street, between 191st Avenue and 192nd Lane. • Crews finished the remaining electric install for Bradford Park phase one housing development. The next development ready for power will be the second phase of Anna’s Acres in Otsego scheduled for August. • Crews will be returning to Industrial Park in Elk River to finish the new service to J&J Machine as well as energize the new primary wire that the bore crew recently installed at locations here. • Mi-Tech Services was here the week of June 23 and inspected 344 of our wood poles primarily in the NW portion of our service territory. Three poles were found to be rejected. These will be changed out by our crews this year. • Staff and I have been working on our Emergency Preparedness Plan. • Crews removed the EV charger located in Otsego near Rockwoods Restaurant this past month. 86