6.2. SR 05-03-1993
rei ---\)
( )j
Iril
ITEM 6.2.
TO:
MAYOR & CITY COUNCIL
River
FROM:
PHIL HALS, STREET/PARK SUPT.
DATE: APRIL 29, 1993
SUBJECT: WORK SCHEDULE FOR MAY-JULY
The following schedule is an estimate of time needed for this
department to complete projects that are on the "drawing board"
for this year. The labor day column represents one employee
for one eight hour day. Twelve labor days could be a six
person crew for 2 days or a four person crew for 3 days. The
intent is to give the Council an accurate estimate of the size
of these projects and the staff time needed for completion. I
would ask that the City Council consider some sort of priority
for these projects, bearing in mind that there will be some
lost time due to weather and also a few projects that are not
scheduled will demand some time. Employee vacations usually
come during this time period too.
.
I plan to reserve the month of August for bituminous overlays
and in-house seal coating because the weather is more favorable
than September or October. The fall months will be dedicated
to work on the Woodland Trails park under the grant we received
and, if we are successful with the ISTEA application, we will
have to start work on the railroad trail. As you can see, the
Street/Park Department has a full schedule for the coming
season and I would appreciate Council input on prioritizing.
.
P.O. Box 490 · 13065 Orono Parkway · Elk River, MN 55330 · (612) 441-7420 · Fax: (612) 441-7425
.
.
.
NEW CITY HALL SITE
Install irrigation system
Plant trees and shrubs
Fine grading for lawn
Install lawn edging & rock mulch
Seed grass
Labor Days
36
10
6
8
2
With this scenario, we would fine grade the lawn area and seed
it immediately with annual rye grass, and then proceed with the
irrigation installation and landscaping. The rye grass will
"green up" rapidly and will remain as the turf grass until
August when we "slit seed" in the perennial turf grass. This
is a duplication of effort to a certain degree, but it allows
us to start grass growing while we are installing the
irrigation system and the seed is much cheaper than sod. The
two seedings would cots less than $1,000. The berm by the
police garage will be enlarged during the trail grading
operation.
The second scenario would have us fine grade the yard and
install the irrigation system as quickly as possible so that
water would be available for the new grass. The sod would be
for the area between the building and Orono Parkway, the
building and Orono Road, and a 30' wide strip along the
northwest side of the building and also the lake side. The
cost to have sod delivered but not installed would be about
$6,000. For the Street/Park Department to install the sod
would add an additional 50 labor days to the project. To have
the sod delivered and contractor intsta1led would be about
$12,000.
-.
.
.
ORONO PARK
Labor Days
Grade the new park area 4
Grade the trail from Orono Parkway to
Orono Beach 4
Install Class 5 on Orono trail 8
Install bituminous on Orono trail 12
Move fishing pier 4
Build steps to access fishing pier 10
Build handicap access ramp to fishing pier 30
The Orono trail will parallel the lakeshore from Orono Parkway
to the beach at Orono Park with an extension from the beach
area to the north end of the park up near the boat launch to be
installed in late summer or early fall. The fishing pier
relocation amount to many hours of work, but, in the long term,
it is going to be an ideal location for the pier, putting it
out of the swimming area, away from the boat launch, and near
the trail for easy pedestrian access.
We also have plans to install new drinking fountains that will
be connected to City water in Orono Park, but that will have to
be a fall project.
JACKSON SQUARE PARKING LOT
Labor Days
Remove existing surface 4
Remove stumps (contractor)
Install storm drainage (contractor)
Install concrete curb & gutter (contractor)
Repair sidewalk cut 4
Install Class 5 base 10
Install bituminous surface 10
Paint stripe parking stalls 2
Install lighting system (contractor)
Install irrigation system 6
The total project should be completed in two weeks with
cooperation from the contractors and the weather, and close
coordination with our crews. The lot would be unusable for the
entire two weeks and Jackson Place would also have to be closed
during the reconstruction.
.
.
.
OLD CITY HALL SITE ON MAIN STREET AND HIGHWAY 10
Install irrigation system
Build retaining walls
Plant trees and shrubs
Asphalt parking lot improvements
Paint striping
Labor Days
15
40
10
10
2
This project has high visibility due to its location and,
therefore, the need for an aesthetically pleasing landscape.
COMMUNITY EDUCATION ATHLETIC FIELDS
Line soccer fields
Finish baseball infields
Class 5 parking lots
Install bituminous paving
Install trail system
Labor Days
6
10
15
25
10
The grass on the athletic fields is growing well and the last
fencing will be installed in the next two weeks. The Area Wide
Recreation programs are planning on using these fields in early
June which means all of the work should be completed by then
except the bituminous paving and the trail system, either of
which could be done at a later date.
DEPOT SITE
Finish topsoil
Timber edging
Rail fence
Labor Days
3
4
4
This work on this site is mostly nonskil1ed labor and would be
an excellent project for our summer youth workers.
LIQUOR STORE
Labor Days
2
10
Finish landscaping
Parking lot improvement w/drainage improvement
The project could be done in the very near future and have the
contractor on Main Street overlay the "street" area that
accesses Ron's Foods.
.
.
.
BOULEVARD TREES
Plant 125 trees
Labor Days
30
Last fall, the City applied for and received a grant from the
Minnesota Releaf program to purchase $9,000 worth of trees with
the City providing $9,000 worth of equipment and labor to plant
and maintain the trees. The two areas for planting are the
Westwood Addition and the new City Hall site. The trees are to
be planted by June 1.
IRRIGATION SYSTEM START UP
Softball Complex
Community Education Athletic Complex
Library
Liquor Store
Depot Site
Labor Days
5
2
1
2
1
This is a once each spring start up maintenance procedure where
we service the system and check the operation of each component.
DISPOSE OF SILICA SAND
Gary Street
Labor Days
6
As part of the well drillers bid last year, it was up to the
contractor to level the material removed from the well on site,
which is normally a truck load or two. Since the well
excavation amounted to 1600 cubic yards, I thought it was in
our best interest for the City to dispose of the material. The
Fair Board has expressed an interest in filling a hole within
the fairgrounds and Sherburne County Highway Department will
furnish a loader and one truck, and we will furnish a loader
and one truck to complete the project.
GRIND STUMPS
Contractor with City filling holes and
collecting chips
Labor Days
10
.
NORMAL MAINTENANCE
Street Sweeping
Paint Striping
Gravel road maintenance
pothole patching
Service squad cars
Park mowing
Labor Days
20
25
20
12
12
60
These are some of the normal maintenance items that we deal
with on a weekly basis.
The total labor days equal 544 or 15.5 weeks for a seven person
crew. I can see several solutions to this situation:
1. Work at these projects on a schedule and rate that
allows flexibility.
2. Hire additional part time help.
3. Contract out some of the more time consuming projects
realizing this could cause budget shortfalls.
4. Delay some of the projects until fall.
. I would appreciate the Council's input on this schedule.
.