INFORMATION #2 10-04-1993
INFORMATION
e
CONSTRUCTION FOR THE JACKSON SQUARE PARKING LOT
AND RAILROAD PARKING LOT
FF~: I DAY :1.0/B/9:::;;
Close Jackson Square for the day. Street Dept. will
remove the 2 large elm trees.
MONDf'~Y
TO t',lED.
10/1LICjl3 to
10/ 13/cjl:::;;
CIO!5e the lot.
A.N. Johnson Construction Co. - Remove stumps and
install storm sewer lines and 2 catch basins.
Street Dept. - Remove existing bituminous, Main
Street driveway entrance, posts, etc. and grade.
Move a telephone pedestal, install conduits for
street light wires and irrigation equipment.
~'JED.. .1.0/1::;/~T)
Street Dept. will close the parking lot between
Highway 10 and the railroad tracks, remove the
posts, cable,and fencing and grade the area for
for concrete curb.
THURS.I0/14/93 to
FR IDA',!" 10/15/93
e
Schmidt Concrete will pour the concrete curbing
on both lots.
MONDAY 10/18/93 to
TUES. 10/19/9::::'
Street Dept. will install Class 5 base in Jackson
Square parking lot.
WED. 10/20/93 to
Street Dept. will install Class 5 base in Jackson
Square parking lot and patch up to curb on railroad
par-king lot.
FRI n 1()/2~,2/':;)3
"ION. 10/2::,/r1:~;
Paint stripe the lot and reopen it for public use..