4.3. SR 12-13-1993
e
e
e
CITY OF ELK RIVER
CITY COUNCIL
RESOLUTION NO. 93 -
A RESOLUTION MAKING FINDINGS OF FACT REGARDING THE ELK PARK
CENTER PROPOSAL AND DENYING A CONDITIONAL USE PERMIT AND
PRELIMINARY PLAT APPROVAL FOR ELK PARK CENTER
WHEREAS, Elk River Associates, Ltd., together with Kraus Anderson
Construction Company (the Developers) have applied for a
Conditional Use Permit to develop a shopping center (the
Project) on certain property located north of the School
District property between Jackson Avenue and Highway 169
(the Property); and
WHEREAS, the City Council, on September 31, 1991, and June 15,
1992, took action to rezone the Property to Planned Unit
Development and designate the Property for Highway
Business Uses on the City's Comprehensive Land Use map;
and
WHEREAS, pursuant to Sections 900.12(15) and 900.42 of the Elk
River City Code of Ordinances, a Conditional Use Permit
and preliminary plat approval must be obtained to develop
the Property as proposed by Developers; and
WHEREAS, an application for a Conditional Use Permit and
Preliminary Plat approval was submitted to the City in
July 1992; and
WHEREAS, a public hearing was held on this application before the
Elk River Planning Commission on August 25, 1992, at which
time the Planning Commission heard a presentation on the
Project, took testimony from all those present who asked
to speak on the matter, and continued action on the
application due to a lack of sufficient information; and
WHEREAS, the Developers subsequently submitted additional
information and a second public hearing was held before
the Elk River Planning Commission on June 10, 1993, at
which time the Planning Commission heard a presentation on
the Project, took testimony from all those present who
asked to speak on the matter, and the application was
continued again for lack of sufficient information; and
WHEREAS, the Developers subsequently revised the site plan for the
Project and submitted additional information in support of
the application for a Conditional Use Permit and
preliminary plat approval; and
e
WHEREAS, the Elk River Planning Commission held a public hearing on
the revised site plan on October 19, 1993, at which time
the Planning Commission heard a presentation on the
Project and received testimony from all those present who
asked to speak on the matter; and
WHEREAS, the Planning Commission, at its meeting on October 19,
1993, recommended approval of the Conditional Use Permit
and Preliminary Plat subject to a number of conditions;
and
WHEREAS, the City Council held a public hearing on the application
for a Conditional Use Permit and Preliminary Plat on
October 26, 1993, at which time the City Council heard a
presentation on the Project and took testimony from all
those present who asked to speak on the matter; and
WHEREAS, the City Council also received a number of written
comments on the Project both before and at the public
hearing held on October 26, 1993; and
WHEREAS, the City Council has reviewed all of the materials
submitted by the Developers, the staff and the public, and
has considered the recommendation of the Planning
Commission and the testimony received at the Public
Hearing on October 26, 1993; and
e
WHEREAS, the Zoning Ordinance of the City of Elk River provides
that a Conditional Use Permit shall not be granted unless
seven (7) specific criteria set forth in Section 900.42(4)
of the Elk River City Code of Ordinances have been met;
and
WHEREAS, the materials and testimony received by the City Council
on the Project have raised a number of questions and
concerns among the City Council Members regarding the
Project and the compliance of the project as presented
with the requirements of the City Zoning Ordinance for
issuance of a Conditional Use Permit;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
Elk River finds that the Project, as proposed, does not
meet the standards for issuance of a Conditional Use
Permit set forth in Section 900.42(4) of the City's Zoning
Ordinance, for the following reasons:
A. Drainage.
1. The Plans as submitted do not make adequate
provision for drainage of the Project site. No
easement has been obtained or submitted which
e
2.
e
B.
e
e
would allow drainage of the Project as proposed,
and no alternative drainage solution has been
identified.
Traffic.
1. Access from Highway 169. The major entrance to
the Project from Highway 169 has only right-
in/right-out access. This restricted access at
the major entrance to the Project from Highway
169 will adversely affect the existing
intersections of Highway 169 with School Street
and Jackson/193rd Avenue, as well as the School
Street/Freeport and Jackson/Freeport
intersections. The Developers have not
adequately addressed the need for or the
possibility of obtaining full access to the
Project from Highway 169.
2. Highway 169/School Street Intersection. The
Project will adversely affect traffic movement
at the intersection of Highway 169 and School
Street/Elk Hills Drive. The Developers have not
adequately addressed how these impacts will be
avoided or mitigated.
3.
School Street and Freeport Avenue Intersection.
The Project will have an adverse impact on the
intersection of School Street and Freeport
Avenue. The Developers have not addressed how
the adverse impact on this intersection and the
flow of traffic between Highway 169 and Freeport
on School Street will be managed.
4. School Street, from Highway 169 to Jackson. The
Project will result in increased traffic levels
on School Street between Highway 169 and Jackson
Avenue. The plans presented by the Developer at
the Council meeting on October 26, 1993 show
medians in School Street which will restrict
access to Burger King and to Parker School. The
adverse impact of the proposed medians on those
property owners has not been addressed by the
Developers.
5. Jackson Avenue. The Developers have not
adequately addressed the impacts of the Project
on Jackson Avenue. Particular concerns include
the proposed access off of Jackson into Taco
Bell and the intersections of Jackson/Highland
Road and Jackson/Freeport.
3.
6.
H~9hland Road. The Developers have not
adequately identified or addressed the impacts
of increased traffic ~olurnes on Highland Road.
e
7. Highway 10 Traffic. The Developers have not
adequately addressed the impact of traffic
travelling to and from the Project from Highway
10 west of Downtown Elk River, nor the impact of
this traffic on Procter Avenue and School
Street.
C. Public Health and Safety.
1. ~pact on schools. Increased traffic along
School Street and Jackson Avenue in close
proximity to the existing schools will adversely
affect the schools and the safety of school
children traveling to and from school and from
the schools to Lions Park. The shopping center
will alSo have an impact on the schools located
immediately south of the Project. The
Developers have not adequately addressed how
these impacts will be mitigated nor how the
Project will be buffered from these schools.
2.
Air ~ality~ Increased traffic along the School
Street corridor will ad~ersely affect the health
and safety of children by creating higher levels
of carbon monoxide around the schools.
e
3. HQlding pond. The holding pond located between
the Project and the SchoolS will be a danger to
children playing in the school playgrounds and
should be enclosed as adequately as possible to
keep children out of the pond.
4. Neighboring procerty_ The increased traffic
congestion and activity whic~ the Proje~t will
bring will detrimentally affect the use and
enjoyment of other property in the immediate
vicinity including properties located along
SchOOl Street, Jackson Avenue and Highland Road.
NOW, THEREFORE, BB IT FURTHER RESOLVED that the City Council of the
City of Elk River, based upon the findings set forth abo~e
and all of the materials submitted to the Council on this
matter, and the testimony received at the public hearing,
does hereby:
1. Deny the application for a Conditional Use Permit for
the project as presented; and
e
4.