REQUEST FOR COUNCIL ACTION
Agenda Section Meeting Date
Consent A enda ul 17, 2006
Item Description
Conditional Use Permit CD 04-19) Extension Re uest
Item Number
3.5.*
Prepared by
Chris Leeseber
Reviewed by
erem T Barnhart
Introduction
The applicant received Conditional Use Permit approval August 16, 2004 to construct a 1:vlotor \' emcle
Repair Shop (Abra Auto Body & Glass) at the north east comer of Line Ave and 183rd Circle.
Tile City ordinance states, (if the proposed lV011e described ill a conditional use pel7JJit has Jlot beeJl substantiallY
cOJJpleted lvithill two )'ears after its date of issuance, the peliJJit shall expire and becoJJJe void, except that the cot/ncil JJJq)',
folio)ving reco/J1JJlendatioJ1 of the planning C01JltJlissioJl, extend the perlJlit for an additional pen"od deteJ7JJined L?J the cot/ncil
on the receipt of a request for a pertJJit extension pJ7"or to its e.:piration. A conditional use pe17JJit authol7"zes 011/)' the lIse
peczjied in the pe17Jlit and shall expire if, for al!J' reason, the authorized use ceases for lJJOre than six lJl0Jlths.
For se,reral reasons, tile applicant is requesting an extension to tlleir Conditional Use Permit for a period
of one year (August 16, 2007).
Attachments
. Request for Extension Letter
Planning Commission Action
Staff and tlle Planning Commission believe the request still complies with the standards set forth in
Section 30-654, Standards for Issuance of Conditional Use Permits. The Planning Commission
unanimously recommended appro\ral of the request.
Action Requested
Staff and the Planning Commission recorrunended the City Council appro\re the request to extend
Conditional Use Permit (CD 04-19) to August 16,2007.
Planning Commission Action
i\Iotion by _
Second by _
\Tote
Follow Up
S:\PL:\l'JNING\Case Files\2004\CU 04-19 PlanScape Partners\CUP Extension_CC.doc
UVONIA PROPERTIES, LLC
25055 - 136TH ST
ZIMMERMAN/ MN 55398 .
612-685-0665
August 10, 2006
Mr. Chris Leeseberg
City of Elk River
13065 Orono Parkway
Elk River, MN 55330
FilE COpy
Dear Mr. Leeseberg:
A Conditional Use Permit (CUP) was approved on August 16, 2004, for Case #CU-04-19,
as submitted on my behalf by PlanScape Partners. This CUP allowed construction of an
auto body repair facility on my property, subject to certain conditions. One of those
conditions was that construction had to be completed by August 16, 2006.
As the result of a number of issues, such as the cyclical business nature of the auto body
repair industry, construction contract and lender negotiations and existing building lease
considerations, the timing of our project has been delayed. As a result, we were not able to
begin construction as we had anticipated and will not complete the project by the required
August 16 deadline. Therefore, we respectfully request an extension of the CUP approval
for a period of one year. I~ is our intent to commence construction later this year so that
construction can be complete and the building can be occupied in advance of the proposed
August 16, 2007 deadline.
We appreciate your consideration and look fonvard to moving forward with the project. If
you have any questions about the timing of the project, please do not hesitate to call me at
(763) 241-9500. .
Thank you.