5.5. SR 01-31-1994 ~I ~( ( II Ilk River **CONSENT AGENDA ITEM 5.5.** MEMORANDUM TO: MAYOR AND CITY COUNCIL STEVEN B. ACH, CITY PLANNER ~ JANUARY 27,1994 FROM: DATE: RE: PRELIMINARY DEVELOPMENT SCHEDULE FOR ELK PARK CENTER e As the Council has been upd'lted in previous memos, staff has been meeting with Kraus- Anderson to discuss time lines for development of Elk Park Center. A project of this size, with all of the improvements that will be taking place, not to mention the various City approvals that must occur, is a very time consuming and lengthy process. Therefore, to make sure all City approvals can be obtained and construction commence at a reasonable time, a time line was developed identifying key dates when certain actions need to occur. Attached is the preliminary schedule for the Elk Park Center Development. As you will notice, there are several actions that must occur throughout the year to keep this project on schedule. For the most part, the schedule is aggressive with little room for delay if improvements are to be completed this year. The first Council action that will take place is on February 7, 1994, when the Feasibility Study will be presented to the City Council for their review. In addition, a resolution approving the preliminary plat will also be presented. The Council will also be asked to authorize preparation of plans and specifications for the improvements to serve Elk Park Center as well as the trunk facilities to serve Hillside Estates, SuperAmerica, and surrounding areas. In closing, I want to emphasize that this is a preliminary schedule. If there are any delays along the way, the schedule will obviously change. Staff will be discussing this with Kraus-Anderson to make sure that it fits within their construction schedule and does not conflict with any of the property owner issues that they are dealing with. If the Council has any comments or questions on this schedule, both Terry Maurer and myself, as well as Kraus-Anderson, will be at the February 7th Council meeting and will be happy to answer any questions. e P.O. Box 490 · 13065 Orono Parkway · Elk River, MN 55330 · (612) 441-7420 · Fax: (612) 441-7425 JAN-18-94 TUE 15:39 MSA ST PAUL P.02 I:>RELIMINARY e January 21, 1994 January 28, 1994 February 1 J 1994 February 3, 1994 February 7, 1994 February 8, 1994 February 22, 1994 March 1, 1994 March 3, 1994 March 21, 1994 March 22, 1994 e April 13J 1994 April 18, 1994 May 2J 1994 May I1J 1994 May 16, 1994 June 6, 1994 June 30, 1994 August 31, 1994 e October 31, 1994 1 <?_l Slt\1 loft January 18, 1993 ELK PARK CENTER SCHEDULE Draft Feasibility Study to City staff for review. · ISP to City staff for review. · Final revisions to Feasibility Study. Feasibility fmdings reviewed with Developers. Final Feasibility Studies to City for Council packets. City Council receives Feasibility Study and authorizes preparation of Plans and Specifications. ISP submitted to MPCA for review. · Deadline for submittal/application for Phase 1 site plan review. · Final plat approved by City Council. Concept review meeting on Phase 1 site plan. Public hearing notice to paper. City Council approves Plans and Specifications for trunk sewer and water improvements, and authorizes advertisement for bids. Phase 1 site plan public hearing before Planning Commission. Open bids for trunk sewer and water improvements. · Phase 1 site plan public hearing before City Council. · City Council awards contract for trunk sanitary sewer and water. · City Council approves Plans and Specifications for remaining internal improvements and external roadway improvements. · Developer's agreement approved by City Council. · Construction starts on trunk sanitary sewer and water improvements. · MPCA-approved ISP is approved by City Council. · Bids opened for internal improvements and external roadway improvements. · Developers begin site grading operation. · Developers receive building permit for first building. · City Council awards contracts for internal improvements and external roadway improvements. Construction begins on internal improvements and external roadway improvements. Site grading complete. · Construction complete on trunk sanitary sewer and water. · Construction substantially complete on external roadway improvements which directly affect school traffic. Construction complete on internal improvements and all external roadway improvements. "'t-2n tC.., '^