Update from RJM Construction on YMCA project
Mr. Bob Jossart and Mr. Brian Recker from RJM Construction will be at the meeting to give
the Council a verbal update on the bidding process and timeline for the YMCA project. We
anticipate the first request for authorization to advertise for bids to come in front of the
Council on June 18. Prior to that, Mr. J ossart and Mr. Recker would like to provide more
information to the Council on how the bid process will work for this project since it is
slightly different than the process used on past projects.
S:\Council\Lori\2007\ Th1CA construction update 06 11 07.doc
~
CONSTRUCTION
5455 HWY. 169
PLYMOUTH, MN 55442
PHONE 763-383-7600
FAX 763-383-7601
www.rjmconstruction.com
Hat~ (~?111{C7
ttt'J'l 5, L
Elk River YMCA Community Center
City Council Workshop Discussion
June 11, 2007
Anticipated Elk River City Council Actions
City Council Approve Bid Advertisement for
Bid Package 1 for Precast and Structural Steel
June 18, 2007
Receive Bids for Bid Package 1 - Precast and
Structural Steel
July 12, 2007
City Council Approve Submittal Costs Only for
Precast and Structural Steel. Postpone Release
of Award for Fabrication of Product.
July 16, 2007
City Council Approve Bid Advertisement for
Bid Package 2 for Remaining Project Bids
July 16, 2007
Receive Bids for Bid Package 2
Aug 30, 2007
Present Final Project Budget for Project to the City
Council and Recommendations for Contract Awards,
Including Recommendations to Release Fabrication
of Structural Steel and Precast.
Sept 17,2007