Loading...
5.3. SR 10-14-2002MEMORANDUM TO: FROM: DATE: Mayor and City Council Pat Klaers, City Admini~,r~to~r October 14, 2002 ~ SUBJECT: Public Safety-Utilities-City Hall Project Update Item 5.3. In June there was discussion with the City Council regarding why the estimate for the Public Safety facility had increased over $7 million. This $7 million project goal had been established based on an $8 million lease-purchase bond issue that included a bond reserve requirement. On July 8, 2002, Council discussion took place regarding the possibility of eliminating the bond reserve requirement by way of insuring the bonds. If this bond insurance approach were to take place, additional funds would be available for the Public Safety project. At this meeting it was further noted that timing was an issue, as the bonds would not be approved until August. On July 8, 2002, the City Council approved the Public Safety-Utilities-City Hall bid packages with the understanding that a number of changes would be required if the bond insurance was not approved. In this regard, a list of potential adjustments to the project was submitted by Tushie-Montgomery Architects. On August 12, 2002, the City Council approved the bonds for the Public Safety facility and the City Hall (Utilities) expansion. Approval of the lease-purchase bond for the Public Safety facility included the use of insurance for the bonds and this freed up additional funds for the Public Safety facility. The total for the project has now been finalized at $7.647 million and the details are outlined in the October 9, 2002, attachment from the finance director. Accordingly, almost all of the items that were proposed to be cut on July 8, 2002, have remained in the project. In addition to the identification of available funds for the project, the attachment from the finance director also outlines the total cost of the project. It should be noted that some of these costs are still based on estimates but the total figures for the project are much more firm today than they were in July or August. The Public Safety project includes the upstairs shell for future office expansion, the gun range shell, and a twelve vehicle garage. The project contingency is slightly over $400,000. It is very unlikely that there will be sufficient funds in the contingency to finance the completion of the gun range ($203,000). The construction managers (Kraus-Anderson) have high expectations that the building will be enclosed before winter so that interior work can move forward without interruption. It is scheduled that part of the parking lot expansion will be completed this fall. Additionally, work on Orono Parkway is scheduled to be completed in the very near future and an update by the city engineer on this project is planned for the October 14, 2002, Council meeting. This item is on the City Council agenda as an update and no Council action is being requested. Coundl/ Pat/ CH-PSUpdatebonds Bond Proceeds Par amount of bonds Plus accrued interest Costs of issuance Ehlers & Associates Briggs & Morgan Moody's Investors Service USBank NA Sherburne County Auditor MBIA Insurance UndenNriter~s discount 2002A Public Safety Project Budget Summary $ 8,000,000.00 15,043.52 ~6,400.00) (17,000.00) (5,330.00) (2,000.00) (123.00) (84,000.00) (76,246.70) Subtotal 7,803,943.82 Deposit to Reserve Fund (24,000.00) Deposit to Bond Fund (132,736.98) DEPOSIT TO CONSTRUCTION FUND $ 7,647,206.84 Project Costs Contracts awarded 8/02 Budget for contracts not awarded (1) Building Permit Special Testing Professional Services Builders Risk Insurance Architect Fees (2) Architect Reimbursables Construction Manager General Conditions Other Land/Bond related costs FF&E $ 5,307,570.15 404,687.00 26,338.64 * 20,000.00 8,000.00 2,000.00 501,944.00 47,101.00 114,346.00 295,680.00 20,000.00 Furniture 110,000.00 Cable 79,918.00 ^ Voice 87,649.00 ^ Data 35,000.00 ^ Radio 50,787.72 * Security 130,000.00 ^ Construction contingency 404,892.00 Balance Available 1,293.33 Change Orders/RFI Delete infra md heating Reuse existing site poles and light fixtures RFI 3 & 4 RFI 11 (9,687.00) (10,000.00) 8,700.00 1,700.00 Subtotal Change Orders (9,287.00) Balance after Change Orders & RFIs $ 10,580.33 10/9/02 2002A Public Safety Project Budget Summary NOTES: * = Final ^ = Based on latest estimate (9/26/02) (~ = From TMI to reduce Contingency to 4% (100,000) (1) BudRet for contracts not awarded Budget 2 Irrigation 46,500.00 6 Chain link fence/traffic signs 12,160.00 7 Sod & landscaping 91,975.00 22 Ceramic tile 29,302.00 25 Carpeting & resilient flooring 22,163.00 30 Awnings 31 Storage shelving systems 32 Audio visual equipment 33 Appliances 6,580.00 34 Shooting range equipment 35 Lab equipment 36 Window treatments 37 Automated filing systems 38 Movable filing systems Plus awnin~ls, lab equipment & AV TOTAL Bid 35,000.00 60,000.00 72,833.00 111,600.00 51,070.00 10,326.00 4,775.00 4,225.00 20,236.00 19,622.00 15,000.00 208,680.00 404,687.00 (2) Architect Fees include 7.5% on construction - $431,944 plus intedor design services - $50,000 plus additional services such as value engineering - $20,000. Updated October 4, 2002 10/9/02 PUBLIC SAFETY FACILITY Bid Package 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 Description Site Demo/Earthwork Irrigation systems Bituminious Paving Concrete Curb & Gutter Site Utilities Chain link fence/traffic signs Sod & landscaping Concrete Formwork Precast Concrete Plan Concrete & masonry Structural Steel Erection of Steel Gypsum drywall Carpentry Waterproofing Exterior insulation & finish Membrane roof & sheetmetal Caulking Doors Overhead Doors Alum entrances & windows Ceramic Tile Acoustical treatments Concrete floor coating Carpeting & resilient flooring Wallcovering & painting Final cleaning Extedor signage Lockers Awnings Storage shelving systems Audio visual equipment Appliances Shooting range equipment Lab equipment Window treatments Automated filing systems Movable filing systems Hydraulic elevators Plumbing Fire protection Geothermal loop HVAC & ductwork HVAC control systems Electical Testing & balancing General Field Conditions Construction Management Contractor Dryden Excavating Omann Brothers Duncan Construction Dryden Excavating Kelleher Construction Molin Concrete Serice Construction Daka Corporation Western Steel Regal Contracting George F. Cook Kremer & Davis Custom Drywall Weather Proof Carciofini Caulk Grewwe Doors Garage Door Store Empirehouse St. Cloud Acoustical Concrete Specialties Steinbrecher Marsden Maintenance Bartiey Sales Bartley Sales Schindler Elevator Northern Air Tri-State Fire Northern Air Sentra-Sota Prairie Technical Collins Electric Systems Management Revised Contract 118,399.00 130,896.00 176,000.00 54,741.15 343,647.00 53,581.00 1,017,500.00 164,500.00 109,370.00 263,452.00 390,900.00 21,000.00 109,900.00 118,637.00 17,126.00 54,925.00 25,750.00 154,781.00 Pay #1 9~3/02 $ 57,997.00 37,877.00 178,600.00 26,045.00 Balance Payable 60,402.00 130,896.00 176,000.00 16,864.15 165 047.00 53 581.00 991 455.00 164 500.00 109 37O.OO 263 452.OO 390 900.00 21 000.00 109 900.00 118,637.00 17,126.00 54,925.00 25,750.00 154,781.00 30,950.00 30,950.00 17,500.00 17,500.00 100,800.00 1,472.00 99,328.00 11,080.00 11,080.00 7,700.00 7,700.00 65,280.00 65,280.00 71,380.00 71,380.00 299,500.00 299,500.00 53,200.00 53,200.00 290,000.00 290,000.00 245,600.00 245,600.00 38,385.00 38,385.00 741,350.00 33,250.00 708,100.00 9,740.00 9,740.00 Kraus-Ande~on 295,680.00 39,665.00 256,015.00 Kraus-Anderson 114,346.00 6,175.00 108,171.00 TOTAL $5,717,596.15 $381,081.00 $ $5,336,515.15 Notes: Bid packages with no contractor or amount listed were not awarded. This page includes only construction and construction management costs. Other costs such as architect, engineering, testing, financing, and etc. are not included.