7.3. SR 10-14-2002Item 7.3. Howard R, Green Company October 8, 2002 File: 802400J-0325 Honorable Mayor and City Council City of Elk River 13065 Orono Parkway Elk River, MN 55330 RE: PAVEMENT REHABILITATION REPORT Dear Council Members: As directed some time ago, we have begun work on the 2003 Pavement Rehabilitation project. The first project identified in the draft pavement rehabilitation report is Fourth Street from Main Street to Trunk Highway 10 and some of the intersecting roadways. Thus far, we have gathered topographic information, investigated the underlying utility infrastructure, and are beginning work on the feasibility study. According to the schedule in the Pavement Rehabilitation Report, the next step is to hold a public informational meeting with the affected residents. However, prior to scheduling this meeting we want to present the Pavement Rehabilitation Report to the City Council in its final form for formal adoption. The only significant change in the attached final Pavement Rehabilitation Report from the draft that the City Council has seen several months ago is the years have been taken off the exhibit that identifies future projects. Items of importance included in the Pavement Rehabilitation Report that will be presented at the informational meeting consist of the following: Street reconstruction will consist generally of 32-foot wide pavement with barrier concrete curb and gutter. In some cases, this will be a narrowing of the existing street width; in other cases, it will be a slight widening of street widths. There will be instances where on-street parking or traffic volumes may be cause for consideration of a slightly wider or narrower street section. Wherever possible, sidewalks will be constructed on both sides of the reconstructed street. Sidewalks that currently exist will be replaced, and where no sidewalk exists, new sidewalk will be constructed. · Street lighting will be installed in accordance with Elk River Municipal Utilities street lighting policy, using their standard street light fixture. Existing underground utilities will be inspected and repaired or replaced as necessary. There will be no assessment to individual property owners for repair or replacement of existing sanitary sewer and watermain facilities. If a resident were to request a new sanitary sewer and/or water service to their property, the service would be installed and assessed to the individual property. Ltr-100702-Council.doc of R. Green October 2002 City Pavement Rehabilitation Report For The City of Elk River I hereby certify that this plan, specification, or report was prepared by me or under my direct supervision, and that I am a duly licensed professional engineer under the laws of the State of Minnesota. Lic. No. 15316 Prepared by: Kristina Thompson, I~,I.T. Date Howard R. Green Company 1326 Energy Park Ddve St. Paul, MN 55108 Phone: 651-644-4389 Fax: 651-644-9446 Howard R. Green Compaqy Table of Contents IV. V. VI. VII. VIII. INTRODUCTION ..................................................................................... 1 STREET EVALUATION ........................................................................... 2 PROPOSED IMPROVEMENTS .............................................................. 3 Street ............................................................................................ 3 Sanitary Sewer ............................................................................. 4 Watermain .................................................................................... ,5 Storm Sewer ................................................................................. ,5 Right-of-Way and Easements ....................................................... Permits .......................................................................................... 6 ESTIMATED PROJECT COST AND PHASING ...................................... 7 FINANCING ............................................................................................. 8 ASSESSMENTS .................................................................................... 10 PROJECT SCHEDULE ......................................................................... 13 CONCLUSION ....................................................................................... 14 APPENDIX Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota I. INTRODUCTION In 1997, Howard R. Green Company began working on the Pavement Rehabilitation Program. The streets within the old core City were beginning to deteriorate with age and had advanced past the useful life span of the bituminous surface and concrete curb and gutter. It was determined that the most feasible method of pavement rehabilitation for several of the roads was a full reconstruction. As the first step towards identifying the streets that were in need of reconstruction, the streets within the old core City were inspected. After the inspection was completed, the project was put on hold for several years, but in May 2001 City Council authorized the preparation of a Pavement Rehabilitation Report for the City of Elk River to serve as a guideline for street reconstruction projects within the City. There are several issues that this report will address including: · Street Evaluation · Proposed Improvements · Estimated Project Cost and Phasing · Financing · Assessments · Project Schedule The area evaluated as part of this report is outlined on Exhibit 1. The area is identified as the old core City for the purpose of this report. The pavement rehabilitation report addresses how to rehabilitate one of the City of Elk River's largest investments, its paved street network. The report identifies the need for the project and provides a framework for the reconstruction process. -1- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota Due to the relatively young age of the streets within the City and proactive street maintenance efforts, the City of Elk River has not had a need for large-scale street reconstruction projects in the past. However, the streets are continuing to deteriorate with age. Seal coating and overlay projects are no longer adequate measures to increase the pavement life of a number of streets within the City. Total street reconstruction is the only cost-effective means of continuing the City's proactive street efforts and ensuring an adequate means of transportation for the residents. In addition to rehabilitating street pavement, a total street reconstruction will allow for correction of existing drainage problems through the construction of concrete curb and gutter, modifying street grades, and the installation of a storm sewer collection system where needed. In 1997, a survey of the streets within the old core City was completed shows the streets that were determined to be in need of reconstruction. showed severe signs of advanced pavement deterioration. The streets There are several signs that indicate pavement deterioration. They include: Alligator Cracking - 2na Street Potholes - Upland Avenue between York Avenue and Xenia Avenue ,~. Longitudinal Cracking - 4TM Street and Quinn Avenue -2- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota At the time of construction of many of the streets within the old core City, there were no guidelines in place to ensure uniform construction. Design standards are now in place and all streets would be reconstructed in accordance with the current and proposed standards. In conjunction with street reconstruction, improvements to existing utilities including watermain, sanitary sewer, and storm sewer will be completed. A detailed description of each proposed improvement is provided below. Aisc included are digitally prepared photographs showing "before" and "after" proposed improvements. The proposed street improvements include: Uniform road width of 32 feet face-of-curb to face-of-curb All residential streets would be constructed to a uniform width of 32 feet face-of- curb to face-of-curb with B618 concrete curb and gutter. Residential streets that do not currently meet this requirement would be examined to determine if widening or narrowing the street is feasible during the preliminary design stage. There are some streets within the City where a wider street width is necessary based on average daily traffic counts, such as collector and county roads, and where parking occurs on both sides of the street as a regular occurrence, such as Main Street. In order to maintain a high level of service on these heavily used streets, a width that meets the traffic needs would be used. Concrete driveway aprons will be constructed at all driveway locations regardless of driveway type. -3- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota Streets constructed to a standard residential street design Urban residential streets should be constructed to a minimum 7-ton design. Based on typical soils in Elk River, the proposed pavement section for residential streets consists of 6 inches of Class 5 aggregate base, 2 inches of bituminous base course, and 1½ inches of bituminous wear course. The proposed street section will need to be verified by a geotechnical investigation during the design phase. Installation of concrete sidewalk Proposed improvements also include constructing 6-foot wide sidewalk where feasible on both sides of the road, and replacing existing concrete sidewalk where necessary. Installation of street lights Street lighting has been included as part of the proposed improvements to allow for upgrading of intersection lighting and installation of street lights where necessary for improved traffic safety. According to Elk River Municipal Utilities Standard on Street Lighting, street lights shall be installed at all major intersections and at mid-block provided that no lights are spaced closer than 300 feet. Street lighting layout shall be approved by the Elk River Municipal Utilities and shall be consistent with the standard type of lighting currently being utilized by the City to provide for a uniform City Street Lighting System. Standard boulevard restoration will consist of seeding all disturbed areas. The typical street section is shown in The majority of the City of Elk River is currently served with sanitary sewer as shown on At this time, no specific sanitary sewer improvements are proposed; however, before street reconstruction, all of the sanitary sewer within the project area should be televised. Through reviewing televising reports, it will be possible to identify any areas where deterioration of the sewer main from age and/or tree roots has occurred and is compromising the system. Deterioration of the sanitary sewer mains allows clean ground water to enter the mains. Treating this clean water is an unnecessary expense and can be addressed if necessary during street reconstructions. A general proactive street and utility reconstruction and maintenance program is the best way to address infiltration and inflow due to sewer line deterioration. Minimal improvements have been included in the cost estimate. 4 Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota The City Engineer and General Manager of Elk River Municipal Utilities have identified several areas where watermain improvements are necessary to improve the inadequate water flow from east to west due to small sized mains. The small sized mains also result in inadequate fire protection. The existing water system, with proposed improvements noted, is shown on The improvements include: Installation of watermain Currently, there is no watermain on York Avenue from Main Street to 2nd Street, 2nd Street from York Avenue to Xenia Avenue, and Xenia Avenue from 2nd Street to Main Street. A minimum size of six-inch watermain would be installed at the time of street reconstruction in this area. Upsizing of 4-inch watermain Currently all areas between Main Street and Trunk Highway 10 are served with 4-inch watermain. This small watermain size has resulted in Iow fire flows and high head losses across the 4-inch main. All 4-inch watermain will be upsized to a minimum of 8 inches as necessary through the downtown area. The most crucial improvement to the overall water system is the upsizing of the 4-inch watermain along 4th Street from Jackson Avenue to Main Street to provide adequate fire flow protection to residential homes and businesses. The existing storm sewer collection system is shown on Several streets within the study area are not currently served with storm sewer. When streets are reconstructed to an urban section, storm sewer will be constructed. During the preliminary design phase, the collection system will be reviewed to determine if the current pipe and storm sewer outlets are adequate. An example of existing storm sewer that needs to be reconstructed is in the Upland/Tipton area. The existing storm sewer currently runs through properties. The storm sewer location needs to be corrected so that it is within the public right-of-way. Approximately thirty feet of right-of-way (ROW) is necessary on either side of centerline of the street to construct the proposed improvements. Currently, the majority of the streets within the project area have adequate ROW. The streets that have less than 60- feet are: -5- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota Upland Avenue from Main Street to Trunk Highway 10 5th Street from 5¼ Street to Gates Avenue Gates Avenue from 5th Street to 51/~ Street 5% Street from Gates Avenue to 5th Street During preliminary design phase, it will be determined if additional right-of-way will be necessary to construct the proposed improvements. Temporary construction easements may be needed if grading is necessary outside of the permanent ROW due to possible changes in the vertical street alignment. During the preliminary design phase, necessary easement locations will be determined and temporary construction easements acquired from individual property owners. As with all construction projects, there are several permits that will need to be obtained prior to construction of the proposed improvements. The required permits will depend on the specific improvements of the project. They include, but are not limited to: Minnesota Pollution Control Agency Minnesota Department of Health Minnesota Pollution Control Agency (NPDES) Sherburne County Mn/DOT Sanitary Sewer Watermain Grading Work within their ROW Work within their ROW -6- Howard R. Green Company Proiect No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota Exhibit 1 illustrates the streets that need to be reconstructed at this time. The financial burden on the City that would result from the reconstruction of all these streets in a single construction season makes one large project unfeasible. However, the project size must be large enough in scale to insure that competitive bids will be received. Therefore, the streets have been grouped together into projects that have a total project cost of approximately $1,000,000.00 using today's construction costs. In addition to the financial concerns, the location of the streets was taken into account to minimize the frequency of the construction impacts to residents when determining which streets should be grouped together. In addition, the streets that contain watermain that needs to be upsized for fire flow protection are proposed to be reconstructed in the first few phases. The base improvements used in determining the $1,000,000.00 project size includes: Reconstruction of the roadway Installation/Improvement of the storm sewer if necessary Installation of sidewalk Street lighting Boulevard Restoration 28% overhead The 28% overhead is in accordance with the City's assessment manual. It includes city administration, engineering design, construction staking and inspection, and fiscal and legal costs. The cost of the installation of watermain and/or sanitary sewer, or the repair of either system would be in addition to the $1,000,000.00 costs. These costs were not included due to the separate means of finance used to fund these types of improvements, such as Elk River Municipal Utilities and the general sanitary sewer budget. A preliminary construction cost estimate for each street is provided in the Appendix. The estimates are based on construction costs from recent years. An increase in construction costs from inflation has not been added, but it should be noted that future project costs would be higher due to inflation of construction costs and/or construction materials. As each individual project is authorized, a more detailed cost estimate will be completed with revised construction costs in the feasibility phase. No costs have been included for the acquisition of utility easements and rights-of-way. The proposed project phasing is shown on Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota The improvements discussed in this report are proposed to be financed through a number of different methods. These include: Assessment to benefiting properties Assessments play an essential role in funding street reconstruction projects. The reconstruction of a street improves the City transportation system for residents in the community, however the major benefactor of the improvements is the adjacent property owners. They are the primary users of the improved street and typically, property values increase due to the reconstruction. Therefore, a portion of the street reconstruction cost should be assessed to all adjacent, benefiting property owners. The method and determination of the assessments is noted in the following section. Elk River Municipal Funds In areas currently served with watermain, it is anticipated that improvements to the system will need to be completed in conjunction with the street reconstruction projects. Improvements may be as minor as additional hydrant installation for increased fire protection, replacement of existing hydrants and valves, and isolated watermain replacement; or as significant as total watermain replacement due to deterioration of the in-place watermain and upsizing of some of the existing 4-inch watermains. The funding for repairs or replacement of an existing watermain system would be paid for through Elk River Municipal Utility funds. Sources of these funds include Water Availability Charges (WAC) and normal water usage fees. In some areas that are not currently served, a minimum of a 6-inch watermain would be installed for fire protection and domestic water service at the time of street reconstruction. The cost for the watermain and all appurtenances would be funded through assessments to the benefiting properties. In the event, an individual property does not have existing watermain service; one would be installed and financed through assessments to the benefiting property. Other Utility funds As described previously within the report, all existing sanitary sewer lines will be televised for cracks, breaks, and infiltration to determine areas in which repair is needed. The repairs will be financed through the general sanitary sewer funds. -8- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota In the event, an individual property does not have existing sanitary sewer service; one would be installed and financed through assessments to the benefiting property. Surface Water Management funds Several of the streets within the project area do not have concrete curb and gutter or a storm drainage system. When the road is reconstructed to an urban section, it will be necessary to address the drainage and install the necessary additions to the storm sewer system. In addition, if repairs are necessary to the existing storm sewer it would be completed as part of the street project. Surface water management funds would be contributed for storm drainage improvements. City contribution In recent budget cycles, the City Council has dedicated a portion of the City levy to a fund for future pavement rehabilitation projects. The purpose of this fund is to provide an additional means of financing for street reconstruction projects when the improvement costs exceed funds that can be obtained through assessments and other sources. State Aid Municipal funds An additional funding source available for only some of the streets within the city is the City's Municipal State Aid Account. Some streets, which provide key connections between State Highways, County Roads, and other major City streets, have been designated as part of Elk River's Municipal State Aid (MSA) street system. These streets typically carry higher volumes of traffic than residential city streets and may have increased width and weight capacity to handle the traffic volumes and loads. Due to the extra width and design standards, the reconstruction costs are higher than that of a normal residential city street. The portion of the construction cost of the reconstruction of MSA streets is eligible for funding through the City's MSA account. However, to insure equitable treatment of all property owners within the City the MSA funds should not be used to lower the property assessment to adjacent property owners. -9- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Repod City of Elk River, Minnesota The current Elk River Assessment Manual does provide some details on how to proceed with assessments for street reconstruction projects. However, the current manual proposes to assess street reconstruction projects based on a lot's front footage. It is proposed that the assessment policy be revised to assess improvements against the abutting or benefiting properties within the project area on a per unit basis. A "per unit" assessment would consist of assessing a residential lot that could not be subdivided as one unit. Lots that can be subdivided would be assessed multiple units as appropriate. In addition commercial, industrial, and multi-use properties such as apartments, schools and churches would be assessed more than one unit as determined on a case-by-case basis. The proposed assessment per unit is $5,000 for residential properties, which includes street, curb and gutter, sidewalks, storm sewer, and street lighting. The maximum assessment rate per unit should be adjusted annually by the construction cost index. It is recommended that the following guidelines be adopted and added to the assessment policy to ensure equitable assessments for all affected property owners. It should be noted that the assessment guidelines that follow have been prepared based on circumstances and factors know today. It is recognized that modifications may be necessary from time to time to ensure equitable treatment of affected properties. The proposed additions or revisions to the assessment policy are as follows: The cost for improving intersections of streets and similar parts of public improvements not immediately fronting on either private or publicly owned property should be distributed over the benefited properties within the assessment area. A single-family residential lot should be assessed on a per unit basis in accordance with the following guidelines: Interior lots - Interior lots fronting on streets should be assessed at 100% of the per unit basis. -10- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota Any lot where subdivision is possible based on zoning requirements and placement of existing structures on the lot should be assessed on a per unit basis for each sub-dividable lot. Corner lots - Corner lots that are bordered by two City streets should be assessed at 100% of the per unit assessment regardless of where the improvement is. Double frontage units - If a lot faces on one street and backs onto another, it should be assessed 100% of the per unit assessment regardless of where the improvement is. An exception is if the lot can be subdivided, in which case the lot would be assessed on a per unit basis for each sub-dividable lot. -11 - Howard R. Green Company Project No. 802400J Pavement Rehabilitation Repod City of Elk River, Minnesota All properties other than residential including commercial, industrial, and multi-use such as apartments, churches and schools should be assessed based on the following: All of the above shall be assessed an appropriate number of units as determined on a case-by-case basis. shows the zoning for the properties within the old core City. -12- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota In order for each project to be successful, adequate time needs to be allowed for public involvement in the process. To allow sufficient time for public informational meetings and individual feedback on design concerns, it is proposed that a construction project be authorized every other year. A tentative schedule for a typical construction project, as provided in , is based upon guidelines established in Minnesota State Statues, Chapter 429, Local Improvements, Special Assessments. These dates will be revised as a project develops. Identify pavement rehabilitation project and prepare initial feasibility study including topographic survey Hold a public information hearing with affected property owners Prepare a formal feasibility study, which would include public informational hearing input. Hold public hearing before City Council Prepare plans and specifications Coordinate walk-through of affected properties with 95% completed plans Bid project Hold assessment hearing Award Contract Begin Construction Construction substantially complete Final lift of bituminous placed and any punch list work completed Final project with Contractor Begin new Pavement Rehabilitation Program improvement project July Year 1 September October November November thru February March April April May May September June July August Year 2 Year 3 It is recommended that the first project be authorized in early spring of the first year the project is to proceed in. This is earlier than the typical project schedule provided in and would allow for adequate time for City staff and Council to become familiar with the process. -13- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota In order to maintain the integrity of street network system, it is the recommendation of the report to proceed with the reconstruction projects as they have been outlined. As the projects progress the streets scheduled for reconstruction can be evaluated and revised based on comments from residents. The City Council should take the following actions in order to proceed with the reconstruction process: The report should be adopted The maximum "per unit" assessment rate for residential properties should be finalized and adopted. Authorize televising of the sanitary sewer. Order feasibility study and preliminary survey for the first project. This report focuses on the streets within the old core City. The streets within this area are among the oldest in the City and have reached the end of their useful lifespan and in order to maintain an adequate means of public transportation within the City of Elk River the streets should be reconstructed. As time progresses and the streets are rehabilitated, there will be areas outside of the old core City where the streets will be approaching the end of their useful life. At that time it will be necessary to expand the pavement rehabilitation process to include other areas of the City. Pavement rehabilitation does not eliminate the need for preventative maintenance such as seal coating and overlay programs. Seal coating and overlay projects enhance and prolong the lifespan of the bituminous pavement. Through reconstruction and preventative maintenance programs the City will be able to provide residents with a safe and effective transportation system. -14- Howard R. Green Company Project No. 802400J Pavement Rehabilitation Report City of Elk River, Minnesota Pavement Rehabilitation Program 10/10/2002 Street Improvements Schedule STREE i 2ND ST. 2ND ST. !2ND ST. 2ND ST. 3RD ST. 3RD ST. 3RD ST. FROM RAILROAD DR. FREEPORT YORK EVANS IRVING HOLT GATES FREEPORT EVANS XENIA CUL-DE-SAC HOLT GATES EVANS COMMON EXCAVATION CY $ 10.00 579.4 770.0 727.2 913.9 797.2 855.6 i~ REMOVE BITUMINOUS PAVEMENT SY $ 300 662.2 880.0 831.1 1618.9 1594.4 1857.8 2686.7 REMOVE SIDEWALK SF $ 2.50 0.0 0.0 0.0 0.0; 0.0 0.0 0.0 REMOVE CONCRETE CURB & GUTTER LF $ 3.50 0.0 0.0 00 0.fi' 0.0 0.0 0.0 MAILBOX RELOCATION LS $ 500.00 0.0 0.0 0.0 0.0 0.0 0.0 00 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 0.0 0.0 0.0 0.0 0.0 00 AGGREGATE BASE, CLASS V TON $ 10.50 378.8 504.6 476.7 602.2 520.9 5597 1027.( TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 118.8 157.9 149.1 187.4 163.5 175 5 321.4 TYPE 31B. BASE COURSE MIXTURE TON $ 34.00 92.4 122.8 116.0 145.8 127.2 136.5 25Q0 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 48.0 63.8 60.3' 75.7 66.1 70.9 129.9 CONCRETE CURB & GU]q-ER, DESIGN B618 LF $ 8.00 596.0 792.0 748.0 940.0 820.0 880.0 16120 6" CONCRE YE DRIVEWAY AND APRON SY $ 34.00 15.8 47.3 47.3 1262 15.8 64 3 94.7 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 0.0 99.6 99.6 373.3 49.8 49.8 273.8 CONCRETE SIDEWALK SF $ 2.50 1788.0 4752.0 2244.1 56400 2460.0 2640.0 9672.0 PEDESTRIAN RAMP EA $ 300.00 2.0 4.0 20 40 20 20 40 SODDING, LAWN AND BOULEVARD SY $ 3.00 662.2 880.0 831.1 1044.4 911 .t 977.8 1791.1 FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 6.3 6.3 0.0 6.3 6.3 6.3 125 FURNISH & INSTALL STREET SIGNS EA $ 20000 1.0 1.0 0.0 1.0 1.0 0.0 2.0 ADJUST GATE VALVE EA $ 150.00 0.0 1.0 00 1.0 2.0 0.0 0 0 ADJUST MANHOLE EA $ 200.00 1.0 1.0 20 2.0 1.0 0.0 30 STORM SEWER LF $ 50.00 298.0 396.0 374.0 470.0 410.0 440.0 8060 STREET LIGHTING LS $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 1 0 12" DIP CLASS 50 WATERMAIN LF $ 30.00 12" GATE VALVE EA $ 1,500.00 8" DIP CLASS 52 WATERMAIN EA $ 25.00 8" GATE VALVE EA $ 1,00000 HYDRANT WITH 6" GATE VALVE EA $ 2,000.00 CORP AND CURB STOP EA $ 12000 "COPPER LF $ 11.00 FITTINGS LBS $ 200 CONNECT TO EXISTING EA $ 1,000.00 TRENCH STABILIZATION ROCK TON $ 1600 TOTAL ESTIMATED CONSTRUCTION COST: $ 47,168.02 $ 71,320.17 $ 6I,t 14.65 $ 92,417.26 $ 67,27097 $ 73,374.83 $ 147,282.79 28% OVERHEAD: $ 13,207.05 $ 19,969.65 $ 17,112.10 $ 25,876 83 $ 18,835.87 $ 20,544.95 $ 41,239.18 TOTAL ESTIMATED PROJECT COST: $ 60,375.06 $ 91,289.82 $ 78,226.75 $ 118,294.10 $ 86,106.84 $ 93,919.78 $ 188,521.97 TOTAL COST: $ 7,195,013.85 O.\Proj\8024OOj\costest-repod[1 ] 1 Pavement Rehabilitation Program 10/10/2002 Street Improvements Schedule STREET 4TH ST. 4TH ST. 4TH ST. 4TH ST. 4IH ST. 4TH ST. 41H Sr. FROM KING JACKSON OXFORD MORTON MORTON NORFOLK PROCTOR LOWELL KING PROCTOR TH 10 NORFOLK OXFORD QUINN COMMON EXCAVATION CY $ 10.00 606.7 600.8 830.3 437.5 830.3 933.3 834.2' REMOVE BITUMINOUS PAVEMENT SY $ 3.00 1040.0 1030.0 1992.7 1050.0 1992.7 2240.0 2002.0 REMOVE SIDEWALK SF $ 2.50 0.0 0.0 4270.0 1125.0 4270.0 48000 4290.0 REMOVE CONCRETE CURS & GU-FI-ER LF $ 3.50 0.0 0.0 854,6 0.0 854.0 960.0 858.( MAILBOX RELOCATION LS $ 500.00 0.0 0.0 0.0 0,0 0.0 0.0 00 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 AGGREGATE BASE, CLASS V TON $ 10,50 397.7 394.2 542.1 285.5 543,9 610.4 544.3 TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 124.4 123.2 170.3 89.7 170.3 191.4 171.1 TYPE 31B. BASE COURSE MIXTURE TON $ 34.00 96.8 95.8 132.4 69.8 132.4 I48,9 133.0 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 50.3 49.8 68.8~ 36.3 68.8 77.: 69.1 CONCRETE CURB & GUTTER, DESIGN B618 LF $ 8.00 624.0 618.0 854.0: 450.0 854.0 960.0 858.0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 394 112.9 734 32.8 47.3 97.1 131.1 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 249 74.7 24.9 00 149 3 74.7 00 CONCRE~' E SIDEWALK SF $ 2.50 0.0 0.0 5124.0 1350.0 5124,0 57600 51480i PEDESTRIAN RAMP EA $ 300.00 0.0 0.0 4.0 2,0 40 4.0 40; SODDING, LAWN AND BOULEVARD SY $ 3.00 693.3 686.7 9489 500.( 9489 1066.7 9533 FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 0.0 6.3 6.3 63 0.0 00 63 FURNISH & INSTALL STREET SIGNS EA $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 1.01 ADJUST GATE VALVE EA $ 150.00 0.0 1.0 1.0 0.0 0.0 1.0 0.0 ADJUST MANHOLE EA $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 1.0 STORM SEWER LF $ 50.00 312.0 309.0 427.0 225.0 427.0 480.0 429.0 S [REET LIGHTING LS $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 1.0 ~2" DiP CLASS 50 WATERMAIN LF $ 30.00 450.0 12" GATE VALVE EA $ 1,500.00 1.0 8" DIP CLASS 52 WATERMAIN EA $ 25.00 430.0 475.0 410.0 8" GATE VALVE EA $ 1,000.00 1.0 1.0 1.0 HYDRAN¥ WlTt{ 6" GATE VALVE EA $ 2,000.00 1.0 1 0 1.0 1 0 CORP. AND CURB STOP EA $ 120.00 5.0 9.0 12.0 6.0 1" COPPER LF $ 11.00 200.0 300.0 4200 210.0 FITTINGS LBS $ 2.00 1,0 1000.0 1.0 1.0 CONNEC] fO EXISTING EA $ 1,000.00 0.0 2.0 0.0 20 TRENCH STABILIZATION ROCK TON $ 1600 100.0 1000 100.0 1000 TOTAL ESTIMATED CONSTRUCTION COST: $ 46,068.38 $ 49,220.49 $ 111,18809 $ 41,116.35 $ 120,689.26 $ 127,88828 $ 114,76391 28% OVERHEAD: $ t2,899.15 $ 13,781.74 $ 31,132.66 $ 11,512.58 $ 33,792.99 $ 35,808.72 $ 32,133.90 TOTAL ESTIMATED PROJECT COST: $ 58,967.52 $ 63,002.22 $ 142,320.75 $ 52,628.93 $ 154,482.26 $ 163,696,99 $ 146,897.81 TOTAt. COST: $ 7,195,013.85 O:\Proj\80240Oj~costest repod[1 ] 2 Pavement Rehabilitation Prograrn 10/10~2002 Street Improvements Schedule STREET '4TH ST. 5TH ST. 5 lf2TH ST. 5TH ST. 5TH ST. 5TH ST 5TH ST. FROM QUINN SEYMOUR GATES NORFOLK OXFORD PROCTOR QUINN RUSH END HOLT OXFORD PROCTOR QUINN RUSH COMMON EXCAVATION CY $ 1000 830.3 565.8 1102.5 1098.6 824.4 840.0 834.2 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 1992.7 1164.0 1701.0 1946.1 1884.4 1920.0 19067 REMOVE SIDEWALK SF $ 2.50 4270.0 0.0 0.0 O0 42400 2160.0 2145.0 REMOVE CONCRETE CURB & GU%'FER LF $ 3.50 854.0 0.0 0.0 0.0 848.0 0.0 858.0 MAILBOX RELOCATION LS $ 50000 0.0 0.0 0.0 0.0 0.0 0 0 0.0 MILL BI'! UMINOUS PAVEMENT SY $ 9 50 0.0 0.0 0,0 20.7 0.0 0.0 0 0 AGGREGATE BASE, CLASS V TON $ 10.50 541.7 371.( 721.2 718.7 554.9 565.3 561.8 TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 170.3 116.0 226.1 225.3 174.9 178.2 1770 TYPE 31B, BASE COURSE MIXfURE TON $ 34.00 132.4 90,3 175.8 1752 136.0 138.6 1376 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 68.8 46.9 91.4 91 0 70.7 720 71 5 CONCRETE CURB&GUTTER, DESIGNB618 LF $ 800 854.0 582.0 1134.0 1130.0 848,0 864.0 858.0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 98.3 72.2 268.9 105.0 187.6 122,0 97.1 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 0.0 74.7 124,4 74.7 74.7 49.8 49 8 CONCRE-~ E SIDEWAI_K SF $ 2.50 5124.0 1746.0 3402.0 33900 5088.0 5184.0 5148,0 PEDES fRIAN RAMP EA $ 300.00 4,0 2.0 2.0 2.0 4.0 4.0 4.0 SODDING, LAWN AND BOULEVARD SY $ 3.00 948.9 646,7 1260.0 1255.6 942.2 960.0 9533 FURNIS~I&INSTALLSIGNPANEt. S, TYPEC SF $ 28.00 6.3 00 0,0 0.0 6.3 63 0.0 FURNIStt & INSTALL STREET SIGNS EA $ 200.00 1.0 0.0 0.0 1,0 0.0 1 0 0.0 ADJUST GATE VALVE EA $ 150.00 1.0 0.0 0.0 0.0 O0 2.0 0.0 ADJUST MANHOLE EA $ 200.00 2.0 0.0 2.0 3.0 1 0 1 0 1.0 STORM SEWER LF $ 50.00 427.0 291,0 567.0 5650 424.0 432.0 429.0 SIREET LIGHTING LS $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 1.0 12" DiP (;LASS 50 WA7 ERMAIN LF $ 30.00 12" GATE VALVE EA $ 1,500.00 8" DIP CLASS 52 WATERMAIN EA $ 25.00 450.0 8" GAfE VALVE EA $ 1,000,00 1 0 ttYDRANI WI1tt 6" GATE VALVE EA $ 2,000 00 1.0 CORP AND CURB STOP EA $ 120.00 5.0 "COPPER LF $ 11 00 175.0 FITTINGS LBS $ 2.00 1.0; CONNECT TO EXISTING EA $ 1,000.00 0.0 fRENCH SfABILIZATION ROCK TON $ 1600 100.0 TOTAL ESTIMATED CONSTRUCTION COST: $ 112,082.12 $ 50,132.81 $ 99,645.48 $ 94,36791 $ 96.946.93 $ 88,074.74 $ 88,99862 28% OVERHEAD: $ 31,382.99 $ 14,037.19 $ 27,900.73 $ 26,423.01 $ 27,145.14 $ 24,660.93 $ 24,919 6I TOTAL ESTIMATED PROJECT COST: $ 143,465.11 $ 64,170.00 $ 127,546.22 $ 120,790.92 $ 124.092.08 $ 112,735.67 $ 113,918.23 TOTAL COST: $ 7,195,013.85 O:\Proj\802400j\costest report[1 ] 3 Pavement Rehabilitation Program 10/10/2002 Street improvements Schedule SIREE! 5TH ST. 5TH ST. 5TH ST. 5TH SI-. 5F~,I ST. 6TH ST. 6IH ST. FROM RUSH IRVING HOLT IRVING END GATES JACKSON SEYMOUR HOLT GATES JACKSON UPLAND IRVING IRVING COMMON EXCAVATION CY $ 10.00 591.1 591.1 1092.8 7078 552.2 445.3 713.6 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 12160 1080.9 17484 14964 631.1 9669 13049 REMOVE SIDEWALK SF $ 2.50 0.0 0.0 0.0 0.0 0.0 0 0 0 0 REMOVE CONCRETE CURB & GUTTER LF $ 3.50 00 0.0 0.0 0.0 0.0 0.0 0.0 MAll BOX RELOCATION LS $ 500.00 0.0 0.0 0.0 0.0 0 0 0 0 0.0 MILL BITUMINOUS PAVEMENT SY $ 9.50 O0 0.0 0.0 0.0 00 0.0 0.0 AGGREGATE BASE, CLASS V TON S 10.50 387.5 386.1 714.5 463.6 3625 293.1 467.1 TYPE 41A. WEAR COUSE MIXTURE TON $ 35.00 121.2; I21.2 224.1 1451 113.2 91 3 146.3 TYPE31B, BASECOURSE MIXTURE TON $ 3400 943 94.3 1743 112.9 881 71.0 1138 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 49.0 49.0 90.5 58.6 458 36.9 59.' CONCRETE CURB & GUTTER, DESIGN B618 LF $ 8.00 608.0 608.0 1124.0 728.0 568.0 458.0 734.0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 105.0 40.7 195.4 72.2 112.9 415.8 64.3 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 1500 74.7 24.9 99.6 74.7 1493 149 3 0.0 CONCRETE SIDEWALK SF $ 2.50 1824.0 3648.0 3372.0 43680 0.0 1374.0 44040 PEDESTRIAN RAMP EA $ 300.00 20 4.0 2.0 40 00 2.0 40 SODDING. LAWN AND BOULEVARD SY $ 3.00 675.6 6756 1248.9 808.9 631.1 508.9 815.6 FURNISH & INSTALL SIGN PANELS. TYPEC SF $ 28.00 0.0; 12.5 0.0 12.5 6.3 6.3 125 FURNISH & INS'fALL STREET SIGNS EA $ 20000 0.01 20 1.0 1 0 1.0 0.0 1 0 ADJUST GATE VALVE EA $ 150.00 0.0i 2.0 1.0 1.0 00 1 0 00 ADJUST MAN,tOLE EA $ 200.00 2.0 2.0 2.0 1.0 10 10 2.0 STORM SEWER LF $ 50.00 304.0 304.0 562.0 3640 284 0 2290 367 0 STREET LIGtITING LS $ 200.00 1 0 1.0 1.0 1.0 1.0 1 0 1.0 12" DIP CLASS 50 WATERMAIN LF $ 30.00 12" GAfE VALVE EA $ 1,500.00 8" DiP CLASS 52 WATERMAIN EA $ 25.00 8" GATE VALVE EA $ 1,000.00 HYDRANT WITH 6" GATE VALVE EA $ 2,000.00 CORP. AND CURB STOP EA $ I20.00 1" COPPER LF $ 11.00 FITTINGS I BS $ 2.00 CONNECT TO EXISTING EA $ 1,00000 TRENCH STABILIZATION ROCK TON $ 16.00 TOTAL ESTIMATED CONSTRUCTION COST: $ 53.690.53 $ 56,545.77 $ 96,53764 $ 68,687.93 $ 45,739.44 $ 53,874.22 $ 671251.71 28% OVERHEAD: $ 15,033.35 $ 15,832.81 $ 27,030.54 $ 19,232.62 $ 12,807.04 $ 15,084.78 $ 18.830.48 TOTAL ESTIMATED PROJECT COST: $ 68,723.88 $ 72,378.58 $ 123,568.18 $ 87,920.55 $ 58,546.49 $ 68.959.00 $ 86,082.19 TOTAL COST: $ 7,195,013.85 O:\Proj\802400j\costest repoft[1 ] 4 Pavement Rehabilitation Program 10/10~2002 Street Improvements Schedule SiREET 7TH ST. 7TH ST. 8TH ST. 8TI-t ST. 8]tt ST. EVANS EVANS FROM IRVING IRVING HOLT GATES IRVING RAILROAD DR. 1ST GATES JACKSON GATES END JACKSON 1 ST 2ND COMMON EXCAVATION CY $ 10.00 925.6 711.7 822.5 301.4 717,5 915.8 6533 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 1745.3 1138.7 1880.0 688.9 984,0 889.7 7093 REMOVE SIDEWALK SF $ 2.50 00 0.0 0,0 00 0.0 0 0 REMOVE CONCRETE CURB & GUTTER LF $ 350 0.0 0.0 8460' 310.0 0.0 0.0 00 MAILBOX RELOCATION LS $ 500.00 0.0 0.0 0.0 00 O0 00 00 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 0.0 00 00 0.0 0.0 0.0 AGGREGATE BASE, CI ASS V TON $ 10.50 6046 466.2 5374 197.0 470.4 597.9 428 1 TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 189.8 145.9 168.7 61.8 147.1 187.8 134 0 TYPE 31B, BASE COURSE MIXTURE TON $ 34.00 147.6 113.5 131.2 48.1 114.4 146.1 1042 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 76.7 59.0 68.2 25.0 59.5 759 541 CONCRETE CURB & GUTTER, DESIGN B618 LF $ 8.00 952.0 732.0 846.0 310.0 738.0 942.0 672 0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 409.1 72.2 212.4 73.4 80.1 40.7 394 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 24.9 49.8 49.8 24.9 124.4 24.9 99( CONCRETE SIDEWALK SF $ 2.50 2856.0 4392.0: 5076.0 1860.0 4428.0 0.0 40320 PEDESTRIAN RAMP EA $ 300.00 2.0 4.0 40 4.0 40 0.0 40 SODDING. LAWN AND BOULEVARD SY $ 3.00 1057.8 813.3 9400 344.4 820.0 1046.7 7467 FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 6.3 12.5 0.0 00 125 63 00 FURNISH & INSTALL STREET SIGNS EA $ 200.00 0.0 1.0 1.0 0.0 1.0 0.0 1 0 ADJUST GATE VALVE EA $ 150.00 1.0 0.0 1.0 0.0 0.0 1.0 00 ADJUST MANHOLE EA $ 200.00 2.0 1.0 1.0 1.0 1.0 2.0 1.0 STORM SEWER LF $ 50.00 476.0 366.0 423.0 1550 369.0 471.0 336.0 STREET LIGHTING LS $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 1.0 12" DIP CLASS 50 WATERMAiN LF $ 30.00 12" GATE VALVE EA $ 1,500.00 8" DIP CLASS 52 WATERMAIN EA $ 25.00 8" GATE VALVE EA $ 1,000.00 HYDRANT WITH 6" GATE VALVE EA $ 2,00000 CORP. AN[) CURB STOP EA $ 120.00 1" COPPER LF $ 11.00 FITTINGS LBS $ 2.00 CONNECT TO EXISTING EA $ 1,000.00 TRENCH STABILIZATION ROCK TON $ 1600 TOTAL ESTIMATED CONSTRUCTION COST: $ 90,155.19 $ 67,411.61 $ 86.282.58 $ 32,453.12 $ 68,820.22 $ 66,666.35 $ 60,600.58 28% OVERHEAD: $ 25,243.45 $ 18,875.25 $ 24,159.12 $ 9.08687 $ 19,269.66 $ 18,666.58 $ 16,968.16 TOTAL ESTIMATED PROJECT COST: $ 115,398.65 $ 86,286.86 $ 110,441.70 $ 4t,539.99 $ 88,08988 $ 85,332.93 $ 77.568.74 TOTAL COST: $ 7,195,013.85 O:\Proj\802400j\costest-repod[t ] 5 Pavement Rehabilitation Program 10/10~2002 Street Improvements Schedule STREE 1: EVANS FREEPORT GATES GATES GATES GATES HOLT FROM 2ND 2ND 8TH 5TH 7TH ST. RAILROAD DR. 5TH ST. MAIN ST MAIN ST. SCHOOL 5 1f2 ST 6TH ST. MAIN sr. 5Ttt sr. COMMON EXCAVATION CY $ 10.00 771.9 775.8 884.7 575.6 604.7 595.0 245.0 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 838.1 931.0 1921.1 723.6 1313.1 1020.0 392.0 REMOVE SIDEWALK SF $ 2.50 0.0 0.0 0.0 0.0 0.0 0.0 0 0 REMOVE CONCRETE CURB & GLJ~FI-ER LF $ 3.50 0.0 0.0 910.0 0.0 00 0.0 00 MAILBOX REI OCATION LS $ 500.00 00 0.0 0,0 0.0 0,0 0.0 0.0 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 00 0.0 0.0 0.0 0.0 00 AGGREGATE BASE, CLASS V TON $ 10.50 504.8 508.4 5787 375.9 395.3 389.3 1602 TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 158.3 159.1 181.4 118.0 1240 1220 50.2 TYPE 31B. BASE COURSE MIXTURE TON $ 34.00 123.1 123.7 141.1 91.8 96.5 94.9 39.I~ BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 64.0 64.3 73.3 47.7 50.1 49.3 20 3i CONCRETE CURB & GUTTER, DESIGNB618 LF $ 800 794.0 798.0 910.0 592.0 622.0 6120 252.0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 56.4 47.3 97.1 7.9 146.9 23.7 7.9 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 49.8 149.3 99.6 24.9 49.8 49.8 24.9 CONCRETE SIDEWALK SF $ 2.50 2382.0 47880 5460.0 1776.0 1866.0 1836.0 756,0 PEDESTRIAN RAMP EA $ 300,00 2.0 4.0 4.0 2.0 2,0 2,0 2.0 SODDING, LAWN AND BOULEVARD SY $ 3.00 882.2 886.7 1011.1 657,8 691.1 680.0 280.( FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 0.0 12,5 6.3 0.0 0.0 6.3 0.0 FURNISH & INSTALL STREET SIGNS EA $ 20000 0.0 1.0 1.0 1.0 2.0 1 0 00 ADJUST GATE VALVE EA $ I50.00 2.0 0.0 1.0 00 0.0 0.0 0.0 ADJUST MANHOLE EA $ 200.00 0.0 1.0 1.0 1.0 1.0 1.0 20 STORM SEWER LF $ 50.00 397.0 399.0 455.0 296.0 311.0 306.0 126.0 STREET LIGHTING LS $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 1.0 12" DIP CLASS 50 WATERMAIN LF $ 30.00 12" GATE VALVE EA $ 1,500.00 8" DIP CLASS 52 WATERMAIN EA $ 25.00 8" GATE VALVE EA $ 1.000.00 HYDRANT WI]H 6" GATE VALVE EA $ 2,000.00 CORP AND CURB STOP EA $ 120.00 1" COPPER LF $ 11.00 FliTINGS LBS $ 2.00 CONNECT TO EXISTING EA $ 1,000.00 TRENCH STABILIZATION ROCK TON $ 16.00 TOTAL ESTIMATED CONSTRUCTION COST: $ 63,926.21 $ 72,725.36 $ 88,763.56 $ 46,987.92 $ 56,237.4t $ 50,421.50 $ 21.313.48 28% OVERHEAD: $ 17,899.34 $ 20,363.10 $ 24.853.80 $ 13,156.62 $ 15,746.47 $ 14,118.02 $ 5,967.77 TOTAL ESTIMATED PROJECT COST: $ 81,825.55 $ 93,088.46 $ 113,617.36 $ 60,144.54 $ 71,983.88 $ 64,539.52 $ 27,281.26 TOTAL COST: $ 7,195,013.85 O:\Proj\8024OOj\costest-repod[1 ] 6 Pavement Rehabilitation Program 1011012002 Street Improvements Schedule STREET HOLT HOLT IRVING IRVING IRVING IRVING IRVING FROM 5 1/2 ST SCHOOL 6TH ST. 4TH ST. 5TH ST. 6TH ST. 7TH ST. 5TH ST. '8TH ST. 6TH ST. 3RD ST. 5TH ST. 7TH ST. 8TH ST. COMMON EXCAVATION CY $ 10.00 318.9 824.4 420.0 773.9 455.0 348.1 540.6 REMOVE BITUMINOUS PAVEMENT SY $ 300 510.2 1884.4 768.0 1724.7 9620 596.7 926 7 REMOVE SIDEWALK SF $ 2.50 0.0 0.0 1080.0 3980.0 1170.0 895 0 1390.0 REMOVE CONCRETE CURB & GUTTER LF $ 3.50 0.0 848.0 0.0 796.0 0.0 0.0 00 MAILBOX RELOCATION LS $ 500.00 0.0 0.0 0.0 0.0 0.0 00 0.0 MILL BITUMINOUS PAVEMENT SY $ 950 0.0 0.0 0.0 0.0 0.0 0.0 00 AGGREGATE BASE, CLASS V TON $ 10.50 208.4 539.8 274.~ 507.1 298.0 227.8 353.1 TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 65.4 169.1 86.1 158.7 93.3 71.4 110.9 TYPE 31B, BASE COURSE MIXTURE TON $ 34.00 50.9 131.5 67.0 123.4 72.6 55.5 86.2 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 26.4 68.3 34.8 64.1 37.7 28.8' 448 CONCRETE CURB & GUF~ER, DESIGN B618 LF $ 8.00 328.0 848.0 432.0 796.0 468.0 358.0 556.( 6" CONCRETE DRIVEWAY AND APRON SY $ 3400 73.4 236.1 48.6 80.1 23.7 48.6 1062 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 24.9 99.6 49.8 49.8 24.9 498 0.0 CONCRETE SIDEWALK SF $ 2.50 984.0 5088.0 2592.0 4776.0 2808.0 21480 3336.0 PEDESTRIAN RAMP EA $ 300.00 2.0 4.0 4.0 4.0 4.0 4.0 40 SODDING, [.AWN AND BOULEVARD SY $ 3.00 364.4 942.2 480.0 884.4 520.0 397.8 6178 FURNISH & INSTALL SIGN PANELS. TYPEC SF $ 28.00 0.0 6.3 0.0 12.5 0.0 0.0 0.0 FURNISH & INSTALL STREET SIGNS EA $ 20000 1.0 1.0 1.0 1.0 1.0 1 0 1 0 ADJUST GATE VALVE EA $ 150.00 1.0 1.0 0.0 1.0 1.0 0.0 00 ADJUST MANHOLE EA $ 200.00 00 1.0 1.0 2.0 00 00 1 0 STORM SEWER LF $ 50 O0 164.0 424.0 216.0 3980 234.0 1790 2780 SIREET LIGHIlNG LS $ 200.00 1.0 1.0 1.0 1.0 1.0 1.0 10 I2" DIP CLASS 50 WA[ERMAIN LF $ 30.00 12" GA FE VALVE EA $ 1,50000 8" DIP CLASS 52 WATERMAIN EA $ 25.00 8" GATE VALVE EA $ 1,000.00 HYDRANT WITit 6" GATE VALVE EA $ 2,000.00 CORP AND CURB STOP EA $ 120.00 1" COPPER LF $ 11.00 FI lflNGS LBS $ 2.00 CONNECT TO EXISTING EA $ 1,000.00 TRENCH STABILIZATION ROCK TON $ 16.00 TOTAL ESTIMATED CONSTRUCTION COST: $ 29,363.69 $ 88.200.99 $ 43,807.10 $ 87,653.30 $ 46,231.56 $ 36,704.12 $ 56,199.10 28% OVERHEAD: $ 8,22183 $ 24,696.28 $ 12,265.99 $ 24,542.92 $ 12,944.84 $ 10,277.15 $ 15,735.75 TOTAL ESTIMATED PROJECT COST: $ 37,585.53 $ 112,897.27 $ 56,073.09 $ 112,196.22 $ 59,176.39 $ 46,981.27 $ 71,934.85 TOTAL COST: $ 7,195,013.85 O:\Proj\802400j\costest-re pod[ t] 7 Pavement Rehabilitation Program 10/10/2002 Street Improvements Schedule IS I REEF IRVING IRVING IRVING IRVING KING ST. KING ST. MORTON FROM 8TH ST. 5TH ST. 5TH ST. 7TH ST. MAIN ST. MA N ST. fH 10 SCHOOL ST. 4TH ST. 6TH S¥. 7TH ST. TH 10 RIVER 4TH ST. COMMON EXCAVATION CY $ 10.00 925.6 1108.3 460.8 256.7 865.3 755.3 234 7 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 1586.7 2660.0 895.3 440.0 1966.7 1373.3 526 2 REMOVE SIDEWALK SF $ 2.50 2380.0 2850.0 1185.0 660.0 3540.0 1545.0 0.0 REMOVE CONCRETE CURB & GUI~ER LF $ 3.50 0.0 1140.0 0.0 0.0 708.0 0.0 2560 MAll BOX RELOCA]ION LS $ 500.00 0.0 0.0 0.0 0.0 0.0 0.0 0 0 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 00 0.0 0.0 0.0 0.0 0.0 AGGREGATE BASE, CLAqS V TON $ 10.50 607.6 723.9 3014 1675 555.2 484.6 162.4 TYPE 41A. WEAR COUSE MIXTURE TON $ 35.00 189.8 227.3 94.5 52.6 180.1, 157.2 51.0 TYPE 31B, BASE COURSE MIXTURE TON S 3400 147.6 176.8 73.5 40.9 1401 122.3 39.7 BITUMINOUS MATERIAl. FOR TACK COAT GAL $ 1.50 76.7 91.8 38.2 21.3 72.~ 63.-~ 206 CONCRETE CURB & GUTTER, DESIGN B618 LF $ 8.00 952.0 1140.( 474.0 264.0 708.0 0.0 256.0 6" CONCRETE DRIVEWAY AND APRON SY $ 3400 78.9 48.6 114.1 328' 1390 1062 0.0 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 149.3 24.9 49.8 00 249 24.9 0.0 CONCRETE SIDEWALK SF $ 2.50 5712.0 6840.0 2844.0 1584.0 4248.0 18540 15360 PEDESTRIAN RAMP EA $ 300.00 4 0 40 4.0 40 4.0 2.0 4.0 SODDING, LAWN AND BOULEVARD SY $ 3.00 1057.~ 12667 526.7 2933 786.7 686 7 284.4 FURNISH & INSTALL SIGN PANELS. fYPEC SF $ 28.00 63 63 0.0 00 12.5 6.3 t25 !FURNISH & INSTALL S]'REET SIGNS EA $ 200 00 1.0 1.0 1 0 1 0 2.0 0.O 10 ADJUST GATE VALVE EA $ 150.00 0.0 2.0 0.0 0.0 2.0 0.0 0 0 ADJUST MANHOLE EA $ 200.00 1.0 3.0 1.0' 1.0 2.0 2.0 00 STORM SEWER LF $ 50.00 476.0 570.0 237.0 1320 354.0 309.0 128.0 STREET LIGHTING LS $ 200.00 1.0 1.0 1.0 1.0 1.0 1 .O 10 12" DIP CLASS 50 WATERMAIN LF $ 30.00 12" GA]E VALVE EA $ 1.500.00 8" DIP CLASS 52 WATERMAIN EA $ 25.00 8" GATE VALVE EA $ 1,000.00 HYDRANT WITH 6" GATE VALVE EA $ 2.000.00 CORP. AND CURB STOP EA $ 120.00 1" COPPER LF $ 11.00 Fll~INGS LBS $ 2.00 CONNECT TO EXIS rING EA $ 1,000.00 TRENCH STABILIZATION ROCK TON $ 16.00 TOTAL ESTIMATED CONSTRUCTION COST: $ 93,889.17 $ 115,101.77 $ 50,044.17 $ 27,027.56 $ 87,179.03 $ 57,884.00 $ 24,784.86 28% OVERHEAD: $ 26,288.97 $ 32,228.49 $ 14,012.37 $ 7,567.72 $ 24,410.13 $ 16,207.52 $ 6,939.76 TOTAL ESTIMATED PROJECT COST: $ 120,178.13 $ 147,330.26 $ 64,056.53 $ 34,595.28 $ 111,589.16 $ 74,091.53 $ 31,724.62 TOTAL COST: $ 7,195,013 85 O \Proj\892400j\costest-repod[ 1] 8 Pavement Rehabilitation Program 10110~2002 Street Improvements Schedule S7 REE 1 MORTON NORFOLK NORFOLK NORFOLK OXFORD OXFORD QUINN FROM 4TH ST. TH 10 5TH ST. 4TH ST. TH 10 5TH ST. TH 10 MAIN ST. 5TH ST. 4TH ST. MAIN ST. 5TH ST. 4TH ST. 5TH ST COMMON EXCAVATION CY $ 10.00 1079.2 127.0 583.3 1147.2' 365.6 810,8 546,4 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 2035.0 152.4 933.3 1835.6 647.6 1343.7 874.2 REMOVE SIDEWALK SF $ 2.50 0.0 245.0 1500.0 2950.0 0.0 0.0 REMOVE CONCRETE CURB & GUTTER LF $ 3.50 1110.01 98.0 600.0 1180,0 376.0 0.0 0.0! MAILBOX RELOCATION LS $ 500.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 18.7 0.0 0,0 0.0 0,0 0.0 AGGREGATE BASE, CLASS V TON $ 10.50 705.6 62,2 381.3 750.( 238.5 529.8 356.9 'TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 221.3 19.5 1 I9,6 235.3 75.0 166.3 112.0 !TYPE 31B, BASE COURSE MIXTURE TON $ 34.00 172.1 19.5 93.0 183.0 583 129.3 87.' BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 89.4 7.9 48.3 95.1 30.3 67.2 453 CONCRETE CURB & GU~FER, DESIGN B618 LF $ 8.00 1110.0 98.0 600.0 1180.0 376.0 834.0 562.0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 162.7 0.0 15.81 129.9 32.8 212.4 734 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 0,0 0.0 24.! 49.8 0.0 49.8 249 CONCRETE SIDEWALK SF $ 2.50 6660.0 0.0 1800.0 3540.0 11280 5004.0 3372( PEDESTRIAN RAMP EA $ 300.00 4.0 0.0 2.0 20 20 4~0 4.0 SODDING, LAWN AND BOULEVARD SY $ 3.00 1233.3 108.9 6667 1311.1 417.8 926.7 624 4 FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 12.5 63 00 6.3 12.5 125 6.3 FURNISH & INSTALL STREET SIGNS EA $ 200.00 1.0 1.0 1.0 1.0 1 0 0.0 1 0 ADJUST GATE VALVE EA $ 150.00 1.0 0.0 0,0 0.0 0.0 0.0 0.0 ADJUST MANHOLE EA $ 200.00 0.0 0.0 0.0 1.0 0.0 0.0 0.0 STORM SEWER LF $ 50.00 555.0 49.0 3000 590.0 188.0 417.0 281 0 S i REET LIGHTING LS $ 200.00 1.0 1,0 1.0 1.0 1.0 1.0 1.0 2" DIP CLASS 50 WA fERMAIN LF $ 30.00 2" GATE VALVE EA $ 1,500.00 8" DIP CLASS 52 WATERMAIN EA $ 25.00 550.0 415.0 8" GATE VALVE EA $ 1,000.00 2.0 2.0 I(YDRANT WITH 6" GATE VALVE EA $ 2,000.00 2.0 1.0 CORP. AND CURB STOP EA $ 120.00 10.0 5.0 1" COPPER LF $ 11.00 350,0 175 0 FIITINGS LBS $ 2.00 1000.0 2,0 CONNECT TO EXISTING EA $ 1,000.00 1.0 1.0 TRENCH STABILIZATION ROCK TON $ 16.00 100.0 100.0 TOTAL ESTIMATED CONSTRUCTION COST: $ 135,933.30 $ 9,008.97 $ 54,120.04 $ 109,218.32 $ 33,016.04 $ 100,055.53 $ 52,281.18 28% OVERHEAD: $ 38,061.32 $ 2,522.51 $ 15,153.61 $ 30,581.13 $ 9,244.49 $ 28,015.55 $ 14,638.73 TOTAL ESTIMATED PROJECT COST: $ 173,994.62 $ 11,531.48 $ 69,273,64 $ 139,799.45 $ 42,260.53 $ 128,071.07 $ 66,919.91 TOTAL COST: $ 7,195,013.85 O:\Proj\802400i\costest repod[1] 9 Pavement Rehabilitation Program 10/10/2002 Street Improvements Schedule STREET QUINN RAILROAD DR. RAILROAD DR RAILROAD DR RAILROAD DR RUSH RUSH FROM 5TH ST. JACKSON IRVING GATES 2ND ST. TH 10 5TH ST. 4TH ST. IRVING MAIN 2ND ST. EVANS 5TH ST. 4TH ST. COMMON EXCAVATION CY $ 1000 801.1 838.1 1411.7 262.5 2000.8 593 I 865,3 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 1281.8 1676.1 2016.7 360.0 2744.0 948.9 1878.9 REMOVE SIDEWALK SF $ 2.50 2060.0 2155.0 0.0 0.0 0.0 00 4450.0 REMOVE CONCRETE CURB & GUTTER LF $ 3.50 0.0 0.0 1452.0 0.0 0.0 0.0 8900 MAILBOX RELOCATION LS $ 500.00 0.0 0.0 0.0 0.0 0.0 0 0 0.0 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 0.0 0.0 0.0 0.0 0 0 0.0 AGGREGATE BASE, CLASS V TON $ 10.50 524.2 547.2 922.9 171,3 1306.6 387.7 566.0 TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 164,3 171.9 289.5 53.8 410.3 121.6 177.4 TYPE 31B, BASE COURSE MIXTURE TON $ 34.00 127.8i 133.7~ 225.2 41.9 319.1 94,6 138.0 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 66.4 69.4 117.0 21.8 165.8 49.1 71.7 CONCRETE CURB & GUTTER, DESIGN B618 LF $ 8.00 824.0 862.0 1452.0 270,0 2058.0 610.0 890.0 16" CONCRETE DRIVEWAY AND APRON SY $ 34.00 64.3i 7.9 39.4 0.0 23.7 15.8 I29,9 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 4981 24.9 124.4 0.0 49.8 24.9 498 CONCRETE SIDEWALK SF $ 2.50 4944,01 2586 0 0.0 0.0 0.0 3660.0 5340.0 PEDESTRIAN RAMP EA $ 300.00 4.0 2.0 0.0 0.0 0.0 40 4.0 SODDING, LAWN AND BOULEVARD SY $ 3.00 915.6 957.8 1613.3 3000 2286.7 677.8 988.9 FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 6.3 6.3 12.5 0.0 0.0 12.5 12! FURNISH & INSTALL STREET SIGNS EA $ 200.00 1.0 1.0 2,0 1.0: 1 0 1.0 2.0 ADJUST GATE VALVE EA $ 150 00 0.0 1.0 0 0 00 0.0 1,0 10 ADJUST MANHOLE EA $ 200,00 1.0 3.0 2.0 0.0 0.0 00 00 STORM SEWER LF $ 50.00 412.( 431.0 726.0 135,0 1029.( 305.0 445 0 STREET LIGHTING LS $ 200.00 1.0 1.0 1.0 1.0 1 0 1.0 1 0 2" DiP CLASS 50 WATERMAIN LF $ 30.00 3900 2" GATE VALVE EA $ 1,50000 1.0 ~" DIP CLASS 52 WATERMAIN EA $ 25.00 8" GA~'E VALVE EA $ 1,000.00 HYDRANT WITH 6" GATE VALVE EA $ 2,000.00 1.0 CORP. AND CURB STOP EA $ 120.00 7.0 1" COPPER LF $ 11.00 245.0 F TT NGS LBS $ 2.00 1000.0 CONNECT TO EXISTING EA $ 1,000.00 1.0 TRENCH STABILIZATION ROCK TON $ 16.00 100.0 TOTAL ESTIMATED CONSTRUCTION COST: $ 79,911.92 $ 75,556.73 $ 110,216.22 $ 19,053.64 $ 144,145.12 $ 54,717.58 $ 121,967 92 28% OVERHEAD: $ 22,375,34 $ 21,155.88 $ 30,860.54 $ 5,335.02 $ 40,360.63 $ 15,320.92 $ 34,151.02 TOTALESTII~ATED PROJECT COST: $ 102,287.26 $ 96,712.62 $ 141,076.76 $ 24,388.66 $ 184,505.76 $ 70,038.50 $ 156,118.94 TOTAL COST: $ 7,195,013.85 O:\Proj\802400j\costest-~epor ti 1J 10 Pavement Rehabilitation Program 10/10/2002 Street Improvements Schedule S IREE I' RUSH :TIPTON UPLAND UPLAND UPLAND WATSON XENIA FROM 4TH ST. MAIN TH 10 TIPTON 5TH ST. MAIN 2ND ST. MAIN UPLAND TIPTON 5TH ST. MAIN END MAIN COMMON EXCAVA1 ION CY $ 10.00 00 1678.1 618.3 750.6 1403.9 425.8 762.2 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 0.0 2493.1 848.0 857.8 1604.4 584.0 958.2 REMOVE SIDEWALK SF $ 2.50 0.0 0.0 0.0 0.0 0.0 00 0.0 REMOVE CONCRETE CURB & GUTTER LF $ 3.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 MAILBOX RELOCATION LS $ 500.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 0.0 0.0 0.0 0.0 00 0.0 AGGREGATE BASE, CLASS V TON $ 1050 0.0 1098.2 403.8 490.1 917.8 278.9 498.4 TYPE 41A, WEAR COUSE MIXTURE TON $ 35 00 0.0 3441 126.8 153.9 287.9 87.3 156.3 TYPE 31B, BASE COURSE MIXTURE TON $ 3400 0.0 267.6 98.6 119.7 223.9 67 9 121.6 BITUMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 0.0 139.0 51.2 62.2 116.3 35.3 63.2 CONCRETE CURB & GUTTER, DESIGN B618 LF $ 8.00 0.0 1726.0 636.0 772.0 1444.0 438 0 784.0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 00 136.6 7.9 1390 137.8 56.4 89.2 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 00 149.3 24.9 24.9 74.7 0.0 49.8 CONCRETE SIDEWALK SF $ 2.50 0.0 103560 3816.0 4632.0 4332.0 0.0 2352.0 PEDESTRIAN RAMP EA $ 300.00 0,0 4.0 4.0 4.0 2.0 0.0 2.0 SODDING, LAWN AND BOULEVARD SY $ 3.00 0 0 19178 706,7 857.8 t604,4 486.7 871,1 FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 0.0 125 0.0 0.0 6.3 6.3 6.3 FURNISH & INSTALL STREET SIGNS EA $ 200.00 0,0 2.0 1.0 0.0 1.0 1,0 1,0 ADJUST GATE VALVE EA $ 150.00 0,0 2,0 0.0 20 0.0 1.0 10 ADJUST MANHOLE EA $ 200.00 0.0 4.0 0.0 20 1.0 0.0 1,0 STORM SEWER LF $ 50.00 0.0 863.0 318.0 386.0 7220 219 0 3920 S1REET LIGHI lNG LS $ 200.00 0.0 1.0 1.0 1.0 1.0 1.0 1.0 12" DIP CLASS 50 WAIERMAIN LF $ 30.00 12" GATE VALVE EA $ 1,500.00 8" DIP CLASS 52 WATERMAIN EA $ 2500 8" GATE VALVE EA $ 1.00000 HYDRANT WITH 6" GATE VAt VE EA $ 2,000.00 CORP AND CURB STOP EA $ 120.00 1" COPPER LF $ 11 00 FI%FINGS LBS $ 2.00 CONNECT TOEXISIlNG EA $ 1,000.00 TRENCH STABILIZATION ROCK TON $ 16.00 TOTAL ESTIMATED CONSTRUCTION COST: $ $ 155,878.09 $ 55,725.11 $ 71,604.13 $ 116,828.52 $ 32,916.04 $ 65,t00.12 28% OVERHEAD: $ $ 43,645.86 $ 15,603.03 $ 20,049.16 $ 32,711.98 $ 9,216.49 $ 18.228.03 TOTAL ESTIMATED PROJECT COST: $ $ 199,523.95 $ 71,328.14 $ 91,653.28 $ 149,540.50 $ 42,132.53 $ 83,328.15 TOTAL COST: $ 7,195,013.85 O:\Pr oj\802400j\costest- report[1 ] 11 Pavement Rehabilitation Program 10f10/2002 Street Improvements Schedule S YREET YORK YORK FROM MAIN 183RD CT. 183RD CT. 2ND ST. COMMON EXCAVATION CY $ 10.00 530.8 208.1 REMOVE BITUMINOUS PAVEMENT SY $ 3.00 667.: 261.6 REMOVE SIDEWALK SF $ 2.50 0.0 0.0 REMOVE CONCRETE CURB & GU~'ZER LF $ 3.50 0.0 0.0 MAILBOX RELOCATION LS $ 500.00 00 0.0 MILL BITUMINOUS PAVEMENT SY $ 9.50 0.0 0.0 AGGREGATE BASE, CLASS V TON $ 10.50 347.! 136.5 TYPE 41A, WEAR COUSE MIXTURE TON $ 35.00 108.9 42.7 TYPE 31 B, BASE COURSE MIXTURE TON $ 34.00 84.7 33.2 BI1 UMINOUS MATERIAL FOR TACK COAT GAL $ 1.50 44.( 17.2 CONCRETE CURB & GUTTER, DESIGNB618 LF $ 8.00 546.0 214.0 6" CONCRETE DRIVEWAY AND APRON SY $ 34.00 23.7 15.8 2" BITUMINOUS DRIVEWAY RESTORATION SY $ 15.00 74.7 49.8 CONCRETE SIDEWALK SF $ 2.50 1638.0 642.0 PEDESTRIAN RAMP EA $ 300.00 2.0 2.0 SODDING, LAWN AND BOULEVARD SY $ 3.00 606.7 237.8 FURNISH & INSTALL SIGN PANELS, TYPEC SF $ 28.00 6.3 0.0 FURNISH & INSTALL STREET SIGNS EA $ 200.00 1.0 0.0 ADJUST GATE VALVE EA $ 150.00 0.0 0.0 ADJUST MANHOLE EA $ 200.00 1.0 1.0 STORM SEWER LF $ 50.00 273.( 107.0 STREET LIGHTING LS $ 200.00 1.0 1.0 12" DIP CLASS 50 WATERMAIN LF $ 30.00 12" GATE VALVE EA $ 1,500.00 8" DIP CLASS 52 WATERMAIN EA $ 25.00 8" GATE VALVE EA $ 1,000.00 HYDRANT WITH 6" GATE VALVE EA $ 2,000.00 CORP. AND CURB STOP EA $ 120.00 1" COPPER LF $ 11.00 FITTINGS LBS $ 2.00 CONNECT TO EXISTING EA $ 1,000.00 TRENCH STABILIZATION ROCK TON $ 16.00 TOTAL ESTIMATED CONSTRUCTION COST: $ 44,946.05 $ 18,609.23 28% OVERHEAD: $ 12,584.89 $ 5,210.59 TOTAL ESTIMATED PROJECT COST: $ 57,530.95 $ 23,819.82 TOTAL COST: $ 7,195,013.85 O:\Proj\8024OOj\costest repor([l] 12 ,,~m TOUR f ¸',4 Ji / / / / PLAZA R/VER ~ / LECEND STREET RECONSTRUCTION OLD CORE CITY BOUNDARY CORE CITY STREETS PAVEMENT REHABILATION PROGRAbl STREET RECONSTRUCTION EXHIBIT CONSULTING ENGINEERS EXHIBIT R R fW 60' 14, 32.00' FACE TO FACE 13-50' 16.00' 16.00' ~B618 CONCRETE CURB ANE GUTTER 6' - ' ~ ~1' SIDEWALK 7' / I ~ DE CONC. SIDE NALK ~ 1.5" 2550 T~E MV3 ~ARING COURSE MIX~R~ ~ TACK COAT 2" 2350 T~E LV3 NON~ARING COURSE MIX, IRE 6" CLASS 5 AGGREGATE BASE APPRO~D SUBGRADE I ~ EXHIBI I ; [~ ~PICAL SEC~ON ~.~~ ~ver i / / x \ J OAX \ i! ~,NOLL PARK (hTO~R / / / / SCHOOL STREET k /' RIVER DJ I PLANT i CONSULTING LEGEND STREET RECONSTRUCTION SANITARY SEWER LINE W/ PIPE SIZES &: MANHOLES CORE crl'Y STREETS PAVEMENT REHABILATION PROGP~M SANITARY SEWER EXHIBIT EXHIBIT 3 OAK KNOLL PARK (NOT IN USE) 100,000 TOUR ORONO / / / / / SCHOOL /C'ENTE~ / /SECOND ADDITION R[V£R ~ D~O. .ArO- 4 LEGEND STREET RECONSTRUCTION INSTALL WATERMAIN INCREASE WATERMAIN SIZE WATERMAIN W/ PIPE SIZES & VALVES HYDRANT CORE CITY STREETS PAVEMENT REHABLATION ~ WATER MAIN EXHIBIT CONSULTING ENGINEERS EXHIBIT 4 / ORONO t,r NOLL ~ i, ~,--~ TO~,{R 'xx PARK ! / PLA ZA '~x \ CONSULTING ENG!~ERS LEGEND STREET RECONSTRUCTION STORM SEWER W/ PIPE SIZES & STRUCTURES CORE CITY STREETS PAVEMENT REHABILATION PROGRAM STORM SEWER EXHIBIT ~~_ EXHIBIT L___.',~ L~ ~ \ PLA ZA \ /t / LEGEND PROPOSED STREETS WITHIN A RECONSTRUCTION PROdECT (1ST PROJECT) CORE CITY STREETS PAVEMENT REHABILATION PROGRAM STREET ~ONS'TRUCTION EXHIBIT CONSULTING ENGINEERS EXHIBIT 6 R2bl-- Rlc SCFiOOL II Antenna Tower Mineral Excav&tion LEGEND AgriculKraJ Conaervation Agriculttr~ Reaidental anee Fame/ResidenU~ Single Famiy Residential Single Famiy Reaiclential S~Ce Fan-ay Resk~t~U ~ Farm'y Residential Two Famiy Residential Two Famiy Residential Townhouae/MtJtip~ Famly Residential MuiUple Farniy Reeidential Planned Unit Developement Business Park Office District Highway Commercial Ught Industdal CORE CITY STREETS PAVEMENT REHABILATION PROGRAM ZONING MAP EXHIBIT CONSULTING :EXHIBIT 7