6.3. SR 11-25-2002MEMORANDUM Item 6.3. TO: FROM: DATE: SUBJECT: Mayor and City Council Lori Johnson, Finance Director November 25, 2002 Consider Award of Bids for Public Safety and City Hall Building Projects As you know, when bids were awarded for the public safety and city hall building projects in August, there were some bid packages that were not awarded. Staff has now reviewed several of the public safety facility bid packages and the project budget in more detail and recommends approval of five bid packages as outlined in the attached letter from Don Stutesman, Project Manager, I~caus-Anderson. Staff is also prepared to award contracts for voice and data cabling and the security system. These items were not included as part of the construction bids that were received in June. The radio system, telephone system, and furniture were not included either and will be presented to the Council for approval in the next few months. Attached is a memo from IT Coordinator Bob Pearson outlining the request to award the cabling contract to Dell-Comm and the security contract to Pro-Tec Design, Inc. Both of these companies hold contracts under the State of Minnesota Cooperative Purchasing Venture so it was not necessary to go through the bid process. The cabling contract includes cabling for the public safety building, city hall, and Elk River Municipal Utilities (ERMU) addition. Final approval of the cable contract for the ERMU addition is contingent upon approval by ERMU. The security contract covers only thc public safety building at this time. Once the security system for city hall has been evaluated, the Pro-Tec Design, Inc., contract may be amended to include city hall. Assistant Police Chief Jeff Beaten has been involved in designing these systems for the public safety building and evaluating vendors and agrees with the contracts as recommended. Finally, I have attached a revised budget for the public safety building that includes award of the bids noted in this memo. To date no significant change orders have been requested. The Council will be asked to approve all change orders when Kraus-Anderson or Tushie Montgomery request change orders. Action Requested The City Council is asked to approve the following bids as stated in the attachments: o Bid Package #22 Twin City Tile $111,600.00 o Bid Package #25 MCI 51,070.00 o Bid Package #31 Haldeman Homme 10,326.00 o Bid Package #37 Haldeman Homme 20,236.00 o Bid Package #38 Haldeman Homme 19,622.00 o Voice &Date Cable Dell-Comm 184,201.62 o Security System Pro-Tec Design, Inc. 149,814.00 ~US-ANDERSON® CONSTRUCTION COMPANY CONTRACTORS & CONSTRUCTION MANAGERS November 13, 2002 Ms. LoriJohnson City of Elk River 13065 Orono Parkway Elk River, MN 55330 Re: Elk River Public Safety Facility Elk River, Minnesota Job No. 7713 Dear Lori: This letter is to request authorization to write contracts for the following bid packages. Bid Package 4/22 Bid Package 4/25 Bid Package 4/31 Bid Package #37 Bid Package #38 Ceramic Tile Flooring Storage Shelving Systems Automatic Filing Systems Movable File Systems Twin City Tile MCI Haldeman Homme Haldeman Homme Haldeman Homme $111,600.00 $51,070.00 $10,326.00 $20,236.00 $19,622.00 The above bid proposals were originally received on June 13, 2002. However, on that date, all of these bids were put on hold pending review. You have subsequently determined that we can proceed with these bid packages, therefore we then request the City's authorization to write the above contracts. If you have any further questions regarding any of the information requested, please do not hesitate to contact me. Very,~truly yours, KI~US-ANDERSON CONSTRUCTION COMPANY o~n~esman Project Manager DLS:mmr St. Paul Division 200 Grand Avenue, St. Paul, MN 55102 Phone: (651) 291-7088 FAX: (651) 290-6120 Equal Opportunity EmplOyer MEMORANDUM TO: Lori Johnson FROM: Robert Pearson, I.T. Coordinator DATE: November 20, 2002 SUBJECT: Request for award of construction contracts Lori, the purpose of this memo is to give you my recommendations on the awarding of construction contracts in the following areas: 1. Supplying and installing copper cabling and cabling products in Public Safety, Public Uflities and City Hall buildings. 2. Supplying and installing fiber cabling and cabling products in Public Safety, Public Utilities and City Hall buildings. 3. Security system for Public Safety building. In regards to item number one, I have worked with Dell-Comm and Anixter on identifying and designing a cabling plant that will meet our current and future needs. Since we began reviewing cabling systems a new American National Standards Institute (ANSI) standard has been published. It is called Category 6 Cabling. It has twice the bandwidth (cables ability to carry data) of the older Category 5e standard. It is my recommendation that we have installed and tested a Category 6 c&blmg system. Our main data center has been designed to be located in the new Public Safety building. I am recommending the building of a high speed backbone between the Public Safety data center and the City Hall wiring closet. A backbone allows users whose computers are terminated in one location to have high speed access to network resources in a different location. Distance limitations and lighmmg protection considerations make fiber optics cabling the best choice for cabling between buildings. It has been planned that the fiber between Public Safety and City Hall will be temporarily terminated in the Public Utilities building during the demolition and construction to City Hall. For item number three, security we have worked with Pro-Tec Design Inc on the design of a security system that includes: an access control system, an intrusion alarm system, a fire alarm monitoring system, a video surveillance system, and a video recording system for the interview areas. Both the surveillance and interview recording systems are eliminating VHS tape and are recording to CD. The system was originally budgeted in June at over $165,000. Since then we have added seven additional card readers (25% more) and five additional cameras (75% more) increasing the size and scope of the project considerably. However, through some value engineering with Pro-Tec and by utilizing the state contract for security we were able to reduce the system cost to $149,814. Most of the equipment needed for the systems we are installing is dkectly off the state contract, for the items that are considered specialty items such as covert cameras and interview recorders; the vendor is obligated to a fi`xed 26% material margin that is auditable by the state for compliance. Pro-Tec Design is cu~enfly providing systems for MnDOT statewide, Minnesota DNR, Steams County, and is the provider of all the camera and access control equipment at the Minneapolis-St. Paul International Airport. All of the systems were chosen to be expandable to meet the needs that we will identify in the future for the Public Utilities, and City Hall buildings. Actions Requested Item 1 A. It is requested that the Mayor and City Council approve the bid from Dell-Corem in the amount of $71,969.43 for the installation and termination of a Category 6 cabling system for the Public Safety building. (Per state contract 417409) B. It is requested that the Mayor and City Council approve the bid from Dell-Comm in the amount of $20,835.17 for the installation and termination of a Category 6 cabling system for the Public Utilities building. (Per state contract 417409) C. It is requested that the Mayor and City Council approve the bid from Deil-Comm in the amount of $78,251.98 for the installation and termination of a Category 6 cabling system for the City Hall building. (Per state contract 417409) Actions Requested Item 2 A. It is requested that the Mayor and City Council approve the bid from Dell-Comm in the amount of $13,145.04 for the installation and termination of fiber cabling between the Public Safety building and City Hall. (Per stats contract 421262) Actions Requested Item 3 B. It is requested that the Mayor and City Council approve the bid from Pro-Tec Design Inc. in the amount of $149,814 for the installation of a security systems for the Public Safety building. (Per state con=act 428234) 2002A Bond Proceeds Par amount of bonds Plus accrued interest Costs of issuance Ehlers & Associates Briggs & Morgan Moody's Investors Service USBank NA Sherburne County Auditor MBIA Insurance Underwriter's discount Public Safety Project Budget Summary $ 8,000,000.00 15,043.52 (26,400.00) (17,000.00) (5,330.00) (2,000.00) (123.00) (84,ooo.oo) (76,246.70) Subtotal 7,803,943.82 Deposit to Reserve Fund (24,000.00) Deposit to Bond Fund (132,736.98) DEPOSIT TO CONSTRUCTION FUND $ 7,647,206.84 Project Costs Contracts awarded 8/02 Contracts awarded 11/25/02 Budget for contracts not awarded (1) Building Permit Special Testing Professional Services Builders Risk Insurance Architect Fees (2) Architect Reimbursables Construction Manager General Conditions Other Land/Bond related costs FF&E $ 5,307,570.15 212,854.00 191,833.00 26,338.64 20,000.00 8,000.00 2,000.00 501,944.00 47,101.00 114,346.00 295,680.00 20,000.00 Furniture 110,000.00 Cable 78,541.95 C1 Voice 87,649.00 ^ Data 35,000.00 ^ Radio 50,787.72 ^ Security 149,814.00 Cl Construction contingency as budgeted 404,892.00 Balance Available (17,144.62) Chan,qe Orders/RFI Delete infra red heating Reuse existing site poles and light fixtures RFI 3 & 4 RFI 11 (9,687.00) (10,000.00) 8,700.00 1,700.00 Subtotal Change Orders (9,287.00) Balance after Change Orders & RFIs $ (7,857.62) Construction contingency currently available $ 397,034.38 11/22/02 2002A Public Safety Project Budget Summary NOTES: ^ = Based on latest estimate (9/26/02) (~ = From TMI to reduce Contingency to 4% (100,000) C1 - Contract award 11/25/02 from State Contract (1) Bud,qet for contracts not awarded 2 Irrigation 6 Chain link fence/traffic signs 7 Sod & landscaping 30 Awnings 32 Audio visual equipment 33 Appliances 34 Shooting range equipment 35 Lab equipment 36 Window treatments Plus awnings, lab equipment & AV Budget Bid 46,500.00 35,000.00 12,160.00 60,000.00 91,975.00 72,833.00 6,580.00 4,775.00 4,225.00 * 15,000.00 * TOTAL 157,215.00 191,833.00 (2) Architect Fees include 7.5% on construction - $431,944 plus interior design services - $50,000 plus additional services such as value engineering - $20,000. *Estimate Updated November 21, 2002 11/22/02