5.4. SR 04-15-2002gSver
13065 Orono Parkway
Elk River, MN 55330
MEMORANDUM
Item#
5.4.
TO:
FROM:
DATE:
SUBJECT:
Mayor and City Council
Scott Harlicker, Senior Planner~~- .....
April 15, 2002
Northstar Corridor Update
At the NCDA meeting held on April 4~h the Authority received a report on the state
legislative process. As of April 5~h, funding for the Northstar Corridor was included in the
Senate bonding bill but not in the House bill. Funding was also included in the Senate
transportation finance bill but not in the House bill. The final decision regarding funding will
be worked out in conference committees. An overview of federal funding was presented,
included in the presentation was how the budget for Northstar compares to similar projects
in other parts of the country. It turns out that the actual spending for Northstar is under the
industry average for similar projects. The Final Environmental Impact Statement has been
completed and the 30 day comment period has begun. A record of decision is expected by
June. A letter of support was sent to Senator Roger Moe thanking him for his support of
the Northstar project.
Phone: 763.441.7420
Fax: 763.441.7425
· DOCUMENT2
www. ci.elk-river, mn.us
NCDA
Agenda
Thursday, April 4, 2002
4:30 p.m.
Sherburne County Government Center
Elk River, MN
Minutes of the February 7, 2002 NCDA Meeting*
Action Requested
Approval
Intergovernmental Coordination Committee Report
a) Update on Legislative Progress
1) State
2) Federal
Discussion
Executive Committee/Capital Budget Committee Report
a) Update on Public Information Activities
b) Other
Information
Report on Local Transit Oriented Development (TOD)
Activities (Ramsey)*
Mn/DOT Project Update ~ FEIS*
Other
Information
Information
Next Meeting: May 2, 2002
* Documentation Enclosed.
DRAFT DRAFT D RAFT D RAFT D RAFT
NORTHSTAR CORRIDOR DEVELOPMENT AUTHORITY
Regular Meeting Minutes
February 7, 2002
The Northstar Corridor Development Authority met in regular session on February 7, 2002, in the
Board Room at the Sherburne County Government Center, Elk River, Minnesota.
Present were: Betsy Wergin, Tim Yantos, Mary Richardson, Don Nevala, Stephen Peka, Paul
McCarron, Dave Saunders, Steve Billings, Paul Ostrow, Tom Gamec, Bob Barnette, Robert
Kirchner, Gery Then, Duane Cekalla, Duane Grandy, Patrick Cairns, John Ellenbecker, Bob
Johnson, Ewald Petersen, Terry Nagorski, Lewis Stark, Mike Schadauer, John N. Norgren, Jim
McLean, David Carlberg, Jon Sontag, Scott Harlicker, Linda Jungwirth, Kelli Neu, Jean Keely,
Ann-Therese Schmid, Margo LaBau, Luci Botzek, Rick Speak, Dean Michalko, Dartrell Lipscomb,
Elliott Perovich, James E. Norman, Mark J. Peine, Julie Shortridge, Jeff Dehler, Brian Bensen, Peg
Aho, Ken Stevens, David Loch, Steve Novak, John Himle, Jay McLinden, Jeff Schilling, Eugene
Young, and Tom Wenzel.
o
The meeting was called to order at 4:30 p.m. 15y Chairperson Betsy Wergin.
Duane Cekalla made a motion approving the meeting agenda as presented. The motion was
seconded by Patrick Cairns and passed unanimously.
Tom Gamec thanked Chair Wergin and Vice Chair Ostrow for acting as leaders of the
Northstar Corridor Development Authority for the past few years. Mr. Gamec noted that he
is in favor of Betsy Wergin and Paul Ostrow continuing in their roles as Chair and Vice
Chair until the end of March, so that there is no change in leadership during this Legislative
Session. The motion was seconded by Duane Grandy. Ewald Peterson noted that he
concurs that Chair Wergin should be on the front line at the Legislature this session.
Ewald Peterson made a motion that Betsy Wergin be reelected Chair of the NCDA for
another two year term. Duane Cekalla seconded the motion. Paul McCarron moved that
election of officers be closed and a unanimous ballot cast for Betsy Wergin. Steve Billings
seconded the motion. Elections were closed. The motion that Betsy Wergin be reelected
Chair was unanimously approved on a voice vote. Chair Wergin thanked the members of
the Authority for their support.
Paul McCarron made a motion that Paul Ostrow be reelected as Vice Chair of the NCDA for
another two year term. The motion was seconded by Duane Grandy and the motion passed
unanimously on a voice vote.
Chairperson Wergin gave an update on the Commuter Rail Demonstration Project held on
January 28. Chair Wergin noted that the Demonstration Project went smoothly due to all the
hard work put into it by staff. Jeff Dehler, Anoka County, gave an overview of the Demo.
Page 1
He noted that there were two rail cars brought in by Sounder in Seattle, Washington. Jeff
noted that two trips were run with over 700 riders.
John Himle, Himle Homer, gave an update on public information activities. Mr. Himle
noted that the education process is incredibly important. He noted that significant success
has been achieved on educating people along the Corridor. 5,000 people living along the
Corridor have signed on as supports of the Northstar Project and have offered their help.
Mr. Himle noted that bumper stickers have been developed and are in the process of being
distributed, and that point of purchase materials have been placed at 400 different locations
along the Corridor. Patrick Cairns stated that the billboards are nice and he has seen them
along the Corridor, but he noted that the lettering is too small to read and he suggested
moving the billboard located by the City of Rice to the other side of the highway in hopes
that people would be able to read them as they drive by. Mr. Himle noted that the billboard
placements are continually rotating all along the Corridor. Duane Grandy noted that the
billboards are eye catching.
Steve Novak gave an update on the state and federal legislative activities and handed out to
the members a legislative summary prepared February 6 which showed the various House
and Senate bills being recommended and their status. He noted that the momentum is
building in the House and Senate. Mr. Novak noted that it is expected that a sales tax
exemption bill will be introduced but expects that it may lag behind the bonding request by a
couple weeks. Mr. Novak also passed out copies of newspaper articles from the northern
section of the Corridor which show the support for the Project by Representative Oberstar
and residents who live in the northern part of the Corridor.
Paul Ostrow asked that all members keep heat on legislators and keep them up date on the
Projects' needs. John Ellenbecker noted that he would like help from all members to urge
Representative Knoblach to support this project. Patrick Cairns noted that he and others had
had a meeting with Representative Knoblach and reiterated to him that this Project is very
important to Central Minnesota.
o
Tim Yantos reviewed Resolution 2002-01 which is being presented to the Authority
requesting the consideration of the Members of Congress responsible for the reauthorization
of TEA-21 to establish additional federal funding authority or the creation of a new category
of New Rail Start funding dedicated to commuter rail projects that will allow projects such
as the Northstar Corridor to be funded in a timely and efficient manner. Chair Wergin asked
that a revision be made to the 5th Whereas which would note that Congressmen Jim
Oberstar, Martin Sabo, Collin Peterson and Bill Luther along with Senators Paul Wellstone
and Mark Dayton have been the champions of this project. Steve Billings made a motion
that the NCDA pass Resolution 2002-01 as revised per Chair Wergin's recommendation.
The motion was seconded by Dave Saunders and passed unanimously on a voice vote.
o
Mike Schaduaer, Mn/DOT, gave an project update. Mr. Schadauer noted that'the FEiS has
been signed and is going to the FTA. Mn/DOT is hoping that FTA has reviewed and
commented on the FEIS by the 15th of March. If the FTA does not comment by the 15th, the
project will be delayed another two weeks. Mr. Schadauer noted that Mn/DOT had met with
Santa Fe officials and it seemed clear that Santa Fe officials won't be serious in negotiations
Page 2
until they fee[ that the Northstar Project is a real project. Mr. Schadauer also reviewed for
the Authority Mn/DOT's FTA Quarterly Project Review meeting report for January 23.
o
David Loch reviewed the premise of TOD plans developed by Hoisington Koegler. Scott
Harlicker made a presentation on the Elk River Station TOD which proposes a mixed use of
town homes, wetlands, apartments, retail offices, senior housing, daycare, etc. Mr.
Harlicker noted that a series of side walks and trails will be implemented in the TOD. Mr.
I-Iarlicker noted that the City had approved two land use plans and that the plan is pedestrian
oriented.
Jori Sontag, Big Lake City Planner, gave an overview of Big Lake's plan which includes
businesses, multi-family units, and long term industrial reserve.
10.
Kelli Neu, City of Becker, reviewed what the City has done to date on their comprehensive
plan. She noted that the City is focusing on pedestrian friendly access to the station and on
improving biking/pedestrian crossings.
I1.
David Carlsberg, St. Cloud Planner, noted that Haven Township has indicated that they
would move forward with annexation of the land for the station to the City of St. Cloud once
funding has been achieved for the Project. David Loch noted that the City of St. Cloud,
Haven Township and Sherburne County have been working together with great cooperation
to move this project forward.
12.
Patrick Cairns, Rice, noted that a year and a half ago, the City had adopted an overlay
concept and are considering the process right now. He further noted that they are working in
stages with Langola and Lafayette Townships on a comprehensive plan.
13.
Tim Yantos reviewed a draft of a letter which had been prepared for a mailing out to House
and Senate Representatives stating the NCDA's appreciation for their continued support for
the commuter rail project and noting the Authority's support of the funding requests for the
Metropolitan Light Rail Transit Joint Powers Board to provide transportation solutions
throughout the region. A motion was made by Duane Cekalla authorizing the Chair to sign
the letters for the mailing on behalf of the NCDA. The motion was seconded by John
Norgren and passed unanimously on a voice vote.
14.
Mary Richardson reviewed a resolution of support signed by Chairperson Myra Peterson on
behalf of the Red Rock Corridor Commission.
15. The Authority adjourned by unanimous consensus to adjourn the meeting at 6:00 p.m.
Betsy Wergin Chairperson
Date
Page 3
City of Ramsey
15153 NOWTHEN BOULEVARD N.W., RAMSEY, MINNESOTA 55303
PHONE: (763) 4.2.7-1~ ,O FAX (763) 427-5543
TOD (763) 4-27-8591
February 4, 2002
Betsy Wergin, Chair
Northstar CmTidor Development Authority
Sherbume County
13880 IZli~kway #i0
Elk River, MN 55330
Re: Ramsey Proposed Station
Dear Chairperson Wergin:
I spoke with you last month to request an. opportunity for Ramsey to be placed on the Northstar
Corridor Development Authority (NCDA) agenda regarding its transit oriented development
activities and a request for station designation. I just received the February agenda for the
NCDA and I find that Rarnsey has. not been placed on the agenda. Please allow this letter to
serve as a formal request to be placed on the March agenda for the two purposes outlined below.
The January NCDA agenda included a report of Local Transit Oriented Development (TOD)
activities for the cities of Minneapolis, Fridlcy, Coon Rapids and Anoka. The February agenda
has similar TOD activity reports for Elk River, Big Lake, Becket, St. Cloud and Rice.
Originally, when these TOD activities began, Ramsey was included, ho.w.,ever, they are no longer
a part of the report. As you may be aware, the proposed Ramsey rail station area was selected by
the Metropolitan Council as art Opportunity Site and a gmat..d~al, of TOD activ, ities have taken
place over the last year. The City would appreciate the opportmaity to provide a report on its
TOD activities as other communities have had their opportunity.
The second matter the City wishes to discuss with the'NCDA is the matter of rail station
designation. As you are aware, a great deal has taken place since the April 2000 meeting, when
the NCDA chose not to allow the Ramsey station site as being part of the first round o.f
commuter rail stations. Perhaps the most significant change is that station selection will not be
performed by the NCDA, rather by the Minnesota Department of Transportation. Since the
NCDA has taken the active role of advocacy for the rail corridor, the City of. Ramsey
respectfully requests that all proposed station-designated sites be proposed as station sites.
'Currently, the proposed station site in Ramsey is listed as a "possible" or "future" station.
Ramsey intends to ask the NCDA to change its status to similar designation as the other station
sites identified along the Corridor.
Zfl 'ri c,'c': F,, 7.f), F.~[ qa4 ,.,,.~.,_,,.,_,79c~c c.7c. c. nJ.,,._,,c.x~.t A INr'IFI-I H~FINH
Letter to Chairperson Wergin
Febmm-Y 4, 2002
Page 2 of 2
If you should have any further questions, please contact City Adn-~.uistrator Jim Norman at
Kamsey City Hall.
Sincerely,
CITY OF RAMSEY
Thomas G. Oamcc
Mayor
TGO/jrat
C:
Anoka County Cormnissioncr Dan Erhart
Anoka County Commissioner Paul McCarron
Ken Stevens, NCDA Administrative Team
Tim Yanto$, NCDA Project Ditector
ccc' r. r. oo _6:×Fe.~
c,'fl',q c,',°:F, KF). KT q0q K~,-~-,~.~-, ,7 AINFII-17] H>IFIN~
Minnesota Department of Transportation
Metropolitan Division
Waters Edge
1500 West County Road B2
Roseville, MN 55113
February 20, 2002
Representative James Kanoblach
45 l State Office Building
St. Paul, IvESl 55155
Dear Representative Knoblach:
I understand that there are some unanswered questions regarding proposed highway
improvements to TH 10, that arose at last week's House Capital Investment Committee meeting
during the discussion involving the Northstar Commuter Rail Line. Hopefully, the following
information will answei- those questions.
The Minnesota Department of Transportation 0Yin/DOT) is currently undertaking two Inter-
Regional Corridor ([RC) studies along TH 10. The first is studying TH 10 from its junction w/th
'I-35W to the junction of TH24 in Clear Lake. The second is studying the segment of THl0 from
Clear Lake to Rice. This second study also looks at segments, such as a river crossing and
connection to 1-94, that are outside the area of the Northstar Corridor. Communities and
legislators along the TH I0 corridor have been active participants in these studies. Currently draft
p'[ans-are m~dc~-review attd fmai-ru-ports mc ¢xpecteOlater-th~s-spring.
Utilizing land use information from community comprehensive plans, these studies projected TH
10 traffic volumes for the year 2025, identified corridor deficiencies and developed a vision for
the TH10 corridor for the year 2025 and beyond. These traffic projections assumed that the
Northstar Commuter Rail project was completed and operating. A vision of TH 10 was then
developed that would meet the projected traffic demands of 2025 and beyond. This vision o£
TH10 improvements includes:
1. Expansion to an eight lane freeway from 1-35W to Anoka.
2. Conversion of the existing four lane expressway to a six lane freeway between Anoka and
TH 169 (Elk River).
3. Expansion to a slx lane expressway through Elk River.
4. Actively managing the access along the ex/sting four lane expresswaybetween Elk River
and Clear Lake, including construction of a Big Lake bypass.
5. Conversion from a four lane expressway to a four lane freeway between Clear Lake and
R/ce.
With these potential improvements to TH 10, the corridor will be able to carry the traffic volumes
projected for the year 2025 (approximately 115,000 in the Coon Rapids area and approximately
70,000 through Anoka) and still meet Mn/DOT's IZRC performance targets. These targets are a
60 mile per hour average speed on the high priority segments and a 55 mile per hour speed on the
medium priority seg-ment. TH I0 between 1-35W and Elk River is considered high priority.
Between Elk River and Clear Lake, TH 10 is medium priority, with the segment between TH 24
in Clear Lake and Rice again being high priority.
The current cost estimate for the TH 10 I_nterre~onal Corridor Vision (from 35W to TH 24) is
approximately $450,000,000. The current cost estimate for the TH 10 Interregional Corridor
Vision (from TH24 to Rice) is an additional $145,000,000. These cost estimates include a
proportion for right-off-way and noise wails, but do not include any estimate for program delivery.
An equal opportunity employer
Representative James Knoblach
February 20, 2002
Page 2
These project development costs are generally estimated at 18% of construction costs. These cost
estimates are ha year 2001. dollars and have not been inflated to an expected year of construction.
At this time, there is no specific funding attached to this vision through the year 2025.
Mn/DOT's Metropolitan Division long-range Transportation System Plan (TSP) does have a set
aside, for unspecified ]IRC projects, of upwards of $400 million targeted for the time period
between 2011-2025. Allocation of this set aside is intended to be through a competitive process
for projects that come from any of the current or future IRC planning efforts in the following
IRC segments:
1 35W from 1-694 to Junction 1 35E
1 35E from 1-694 to Junction 1 35W
1 35 from Junction 1 35 E/W to N Chisago County line
1-94 from 1494 to the Crow River
Tlt 101 from Rogers to the Crow River
T-E[-1-69-fro m-I-494-to -8-Seo tt-Go u.n t'~lin e
Tiff 10 from 1 35W to Elk River
TE[ 36 from 1 694 to Stillwater
TEl 8 from 1 35 to Wisconsin
Ti:/212 from 1 494 to W Carver County line
TH 52 from 1 494 to S Dakota County line
1 35E from ! 494 to Junction 1 35W
135W from 1 494 to Junction 1 35E
1 35 from Junction 1 35 E/W to S Dakota County line
Th. is means that Mn/DOT has limited resources to allocate (upwards of only $400 million over 15
years) to improving and managing 14 IRC corridors within the boundaries of the eight county
Mn/DOT Metropolitan Division. Improvements to these corridors outside of Metro Div/sion
boundaries will have to be funded by the construction budgets of the adjacent M_n/DOT Districts.
We must therefore conclude that none of the visions for TH 10 or any of these other corridors wiil
be fully funded or constructed by 2025, if ever, given current levels of transportation funding.
I hope this information has answered the questions concerning TH 10 wl-dch arose in your Capital
Investment Committee meeting. If I can be of further assistance or any additional questions arise,
please contact me at 651/582-1481.
Sincerely,
Area Manager
Metropolitan Division
April 4, 2002
The Honorable Roger D. Moe
Minnesota Senate
208 Capitol
Saint Paul, MN 55155
Executive Committee:
Betsy Wergin. NCDA Chair
Sherburne County
Paul Ostrow. NCE)A Vice Chair
City of Minneapolis Councilmember
Paul McCarron
Anoka County
Mark Stenglein
Hennepin County Regional Railroad
Authority
Steve Billings
City of Fridley
Lewis Stark
Haven Township
Dear Senator Moe:
The proposed Northstar commuter rail between Minneapolis and St. Cloud/Rice is one of
the most important transportation projects in the state and has strong support from the
vast majority of Minnesotans. Local governments and civic organizations along the
corridor are also supporting Northstar, and several unions have unanimously passed
resolutions for the project, including the Minnesota AFL-CIO, Minnesota Central Labor
Union, Minnesota State Building and Construction Trades Council, Minneapolis Building
and Construction Trades Council, and Minnesota Teamsters Joint Council 32.
Northstar represents a tremendous opportunity for Minnesota to tap into its fair share of
federal funding. At the federal level the project enjoys bipartisan support, including from
the influential senior leadership of Congressmen Martin Sabo and Jim Oberstar, and
support from President Bush. Your leadership in the state Senate has been important to
progress on Northstar so far, and we thank you for your on-going support as we enter this
crucial period of the legislative session.
Recent demographic figures make this project all the more important, with rapid growth
from Anoka through the greater St. Cloud area. This is the fastest growing area in the
state and the third fastest in the U.S. The population is booming and, along with it, traffic
congestion. The existing infrastructure is not capable of handling the current needs and
will be overwhelmed by the growth expected in the next 10-20 years.
Eighty percent of residents along the corridor, whether Democrat, Republican or
Independent, support the Northstar commuter rail project because they are looking for
other transportation options. What the citizens want is an integrated transportation
system that includes roads and transit options.
Northstar Corridor Development Authority
2100 3'" Avenue, Anoka, Minnesota 55303-2265 (763) 323-5700 Fax: (763) 323-5682 www. northstartrain.org
Northstar Corridor residents and elected officials are strongly committed to this project
and have already provided the local dollars necessary to fund it. The federal government
has made it clear that they view this project as viable and rank it positively compared to
the dozens of other transit projects proposed across the country. But the State of
Minnesota must bring funding to the table this legislative session in order to tap into
federal dollars and get this project moving.
As Senate Majority Leader, your leadership has been, and remains, crucial to Northstar's
success. We strongly urge your continued support and encourage you to promote a full
funding package for Northstar in the bonding and transportation conference committee
reports.
Signed,
Status of Northstar commuter rail for Federal funding
April 2002
As of the recently released Proposed Allocations of Funds for Fiscal Year 2003,
the Federal Transit Authority for the third straight year categorizes the Northstar
commuter rail project as a "Recommended" project for federal funding in what's
called the "New Starts Program."
But there are also 27 other transit projects in that category from across the country
with which Minnesota is competing for federal funds. The competition is fierce.
Our advantage is in the strong Congressional support for Northstar. Congress has
been providing Northstar with sufficient funding to move the project through each
stage of development every year since 1998. Our support at the federal level has
been bi-partisan, including Minnesota's U.S. Senators over the years.
President Bush's 2003 budget already includes funding for Northstar. Only five
transit projects are singled-out for funding in the President's budget, and
Northstar is one of them. Even though it is only a portion of the funding needed,
it is a clear signal that Northstar is a favored project.
Our missing piece is state funding. Of the 27 recommended projects, 14 already
have financial commitment from their respective states.
Only with state financial commitment will the federal government give approval
and funding for a project to be developed.
If the Legislature does not provide funding this year, it's very likely that many of
the other projects on the list will surpass Northstar and take the federal money that
could otherwise come to Minnesota.
Minnesota has a history of not getting its fair share of federal funding. Minnesota
ranks 45th in net return of federal tax dollars paid. Forty-four states are doing
better than we are in getting a return on federal tax dollars paid.*
if the Minnesota Legislature fails to support Northstar this year, tax dollars
Minnesotans pay to the federal government will once again go to other projects in
other states, such as projects in Seattle, Salt Lake City, Charlotte and San Diego
that have state funding commitment.
* Source: The Northeast-Northwest Institute at www.NEMW.org/taxburd.htm
NORTHSTAR
@ $270M
(Through Preliminary Engineering =
30% Design and Engineering)
RULES OF THUMB
ACTUAL(includes
all Northstar
Corridor costs)
Mn/DOT State Aid Rule
Ao
Design and Engineering:
8-10% x % of project completed $27M (10%)
x 30%.
$8.1M
B. ElS (completed): 1%
+ 2.7M
$10.8M
TOTAL
$5.95M
+ 0.75M
$ 6.7M
II.
Industry Standard for Commuter Rail Rule
A. Design and Engineering:
3-6% of total project cost
through Preliminary Engineering -
$10.8M (4%)
B. ElS (completed): 1% + 2.7M
TOTAL $13.5M
NORTHSTAR: An FTA Recommended Project
$5.95M
+0.75M
$ 6.7M
Cleveland, Ohio -
$300M of which:
13M - Design & Engineering and ElS through Preliminary Engineerinng
FTA Review of $13M: Fair and Comparable to Industry Standards
18
minis~ration's university transportation research account: Provided
further, That $100.000,000 shall be paid to the Federal Transit Ad-
ministration's job access and reverse commute gear,_ts pro, ram_: ,Pro;
vided further, That $.2,,272,80q, 000 s. hall be ps. id to
Transit Admints~ration s capitat irrvesrment grants account.
CAPITz-L INVESTMENT GRANTS
CINCLUDING TRANSFER OF FUNDS)
For n¢cessar'y expenses to carry out 49 U.S.C. 5308, 5309, 5318,
and 5327, $568,200,000. to remain available until expended: Pro-
vided, That no more than $2,841,000,000 of budget authority shall
be available for thece purposes: Provided further, That there shall
be available for f~ed guideway modernization, $1,136,400,000;
there shail be avaihrb~e for the replacement_, r_eh=bilit, a~io?., and, p. ur-
related facilities, $568,200,000, togerner, wrrn~
¢orred ~rom "Federal Transit Adrnini.~tratwn, ~ ormma ~ranr~ ; aha
'tX~;; "shall be available for new
$1,136,400,000. together with $1,488.,~.40 of. the f~.. ,m.aae a. vau-.
able under '7~ederal Transit Admmrstratwn, ~'qp_r. ra~ rnvesrrnsnr
grants' irt Public Law 205-277; to be available as follows:
$10,296,000 for Alaska or Hawaii ferry projects;
$1,000,000 for ~he Albuquerque, New Mexico, light rail
project;
$25.000,000 for the Atlanta, Georgi¢r, ~orth line extension
project;
$I3,000,000 for the Baltimore, Maryland, centrat t~g~tt tau
transgt double track project;
$I,500,000 for the Baltimore, Maryland, rail transit
project;
$2,000,000 for the Birmingham, Alabama, transit corridor
project;
$10,631,245 for the Boston, Massachusetts, South Boston
Piers. transitway project;
$500,000 for the Bostqn, Massachusetts, urban ring transit
project:
$7,000,000 for tlv¢ Charlotte, North Carolina, South cot-
ridor light rail transit project;
$32,750,000 for the Chicago, Illinoi¢, Douglas bran~h re.
construction project;
$55,000,000 for the Chicago, Illinois, METRA eomrnu~er
rail and line extensgon projects;
$3,000,000 for the Chicago, Illinoi¢, Bavenswood teton.
struetion project;
$6,000,000 for the Cleveland, Ohio. Euclid corridor trans-
portation project;
$70,000,000 for the Dallas, Texas, North Central li§h~ rail
transit extertzion project;
$55,000,000 for the Derwer, Colorado, Southeast corridor
light rail transit project;
$I92.492 for the Denver, Colorado, Southwest corridor light
rail transi~ project;
$150,000 for the Des Moines, Iowa, DSM bus feasibility
project;
19
$200,000 for the Dubuque, Iowa, light rail feasibility
project;
$25,000,000 for the Dulles corridor, Virginia, bus rapid
transit project;
$27,000,000 for the Fort Lauderdale, Florida, Tri. County
commuter rail upgrades project;
$2,000,000 for the Fort Worth, Texas, Trinity railway ex.
press, project;
$750,000 for the Grand Rapids, Michigan, Y[TP metro area,
rna~or corridor project;
$12,000,000 for Honolulu, Hawaii, bus rapid transit
projec, t;
$10,000,000 for the Houston, Texas, Metro advanced transit
project;
$300,000 for the Iowa, Metrolink light rail feasibility
project;
$1.$00,000 for the Johnson County, Kansas.Kansas City,
Missouri, 1-35 commuter rail project;
$2,000,000 for the Kenosha.Racine-Milw~ukee, Wisconsin,
commuter rail extension project;
$55,000,000 for the Largo, Maryland, metrorail extension
projee~;
2.000,000 for the Little Rock, Arkansas. river rail project;
I4, 744,420 for the Long Island Rail Road, New York. East
Side access project;
$9,289,557 for the Los Angeles, California, North Holly-
wood e~tension project;
$7,500,000 for the Los Angeles, California, East Side cor-
ridor light rail transit project;
$3,000,000 for the Lowell, Massachusetts-Nashua, New
Hampshire commuter rail extension project;
$12,000,000 for the Maryland fMA~C) commuter rail ira-
provements projects;
$19,170,000 for the Memphis, Tennessee, Medical center
rail extension
_ project;
$$,000,000 ]'or the Miami, Florida, South Miami-Dade
~ busway extension project;
[ $10,000,000 for the Minneapolis-Rice, Minnesota, Northstar
~ corridor commuter rail pro]cci;
~ . $50,000,000 for the M'inneapolis.St. Paul, Minnesota, His.
watha corridor light rail transit project;
$4,000,000 for the Nashville, Tennessee, East corridor com-
muter rail project;
$141,000,000 for the New Jersey Hudson-Bergen light rail
transit project;
$15.000.000 for the New Orleans, Louisiana, Canal Street
car line project;
$1,200,000 for the/New Orleans, Louisiana, Desire corridor
streetcar project;
$2,000,000 for the New York, New York, Second Avenue
subway t~roject;
$20.000,000 for the Newark-Elizabeth, New Jersey, rail
link project;
$2,500,000 for the Northeast Indianapolis, Indiatm, down-
town corridor project;
2O
$2,500,000 for the Northern Indiana South Shore com-
muter rail project;
$6~500,000 for the Oeeanside,Escondido. California, light
rail extension project;
$500~000 for the Ohio, Central Ohio North corridor rail
(COTA) project:
$5,000,000 for the Pawtucket-TI~ Green, Rhode Island, com.
muter rail and maintenance facility project;
$9,000,000 for the Philadelphia, Pennsylvania, Schgykil!
Valley metro project;
$10,000,000 for the Phoenix, Arizona, Central Phoenix/
East Valley corridor project;
$8,000,000 for the Pittsburgh, Penn6~ytvania, North Shore
cor~nector ligh~ rail transit projec~;
$28.000,000 for the Pittsburgh, Pennsylvania, stage II light
rail transit reconstruction project;
$64,000~000 for the Portland, Oregon, Interstate MAX light
rail transit extension project;
$20,000,000 for the Puget Sound, Washington, RTA Sound-
er commuter rail project;
$9,000,000 for the Raleigh, North Carolina, Trlag£le tran-
sit project;
$328,000 for the Sacramento, Californig, light rail transit
extension project;
$14,000,000 for the SaZt Lake City~ Utah, CBD to Univer-
sity light rail transit project;
$3,000,000 for the Salt Lake City, Utah, Universit~ Medical
Center light rail tranzit ext'ension project;
$60,000.000 for the San Diego, California, Missiog Valley
Ec~t light rail transit extension project;
$1.000,000 for the San Diego, California, Mid Coast cot-
ridor project;
$75,675,790 for the San Francisco, California, BART exten-
s~on to ~he airport project;
$113,336 for the San Joee, California, Tasman West light
rail trar~sit project;
$40,000,000 for the San Juan, Puerto Rico, Tren Urbano
project;
$1,700,000 for the Sioux City, Iowa, light rail project;
$28,000,000 for the St. Louis-St. Clair. Missouri, metrolink
extension project;
$5,000,000 for the Stamford, Connecticut, urban tran$itway
project;
$3,000.000 for the Stockton, California, Ali'amont commuter
rail project;
$3,000,000 for the Virgoinia Railway Express station ira.
provements project;
$500,000 for the Washington County, Oregon, Wilsonville to
Beaverton commuter rail project;
$2.500,000 for the Wasilla, Alaska, alternative route
project; and
$400,000 for the Yosemite, California, area regional tran~-
portatior~ system project.
M. edttonic, Inc.
710 Medtronlc Par{o~uy
Minneapolis, MN 55432.5604
wwv. medtronic.com
763.514.4000
March 22, 2002
The Honorable Steve Sviggum
1_.0_3.. S~Lat~Q~_C. e~B u._ild~ng
lO0 Constitution Avenue
St. Paul, MN 55155-1206
RE: Medtronic Transportation Positions
Dear Representative Sviggum:
Medtronic is the world's leading medical technology company with nearly 6,000 high paying
jobs located here in Minnesota. For more than 50 years, we have been proud to call Minnesota
home.
When we decided to invest $139 million in our world headquarters on 1-694 at TH 65 in Fridley,
we knew there were transportation issues that would have to be addressed in order to get our
employees and thousands of annual visitors to and from our facility safely and efficiently.
Phase I of our operation (530,00 square foot) is now fully functioning, and the transportation
problems we feared face us every day. While manageable now, these problems must be resolved
before we begin to think about the viability of Phases II and Ill of the site (1.1 million additional
square feet). You have a unique opportunity during the 2002 Legislative session t0'provide the
funding that would alleviate the difficulties we ate experiencing now, difficulties that prohibit us
· from considering expansion opportunities at the site. ·
We respectfully request you support the following issues in the remaining days of this Session:
1) We, and our neighbors in Fridle~', need a third through lane in each direction from
Medtronic Parkway just north of 1-694 across Moore Lake to an upgraded signalized
intersection at 61~t Avenue N.E., including a walkway along the eastslde of the
causeway. We encourage your support of gas tax increases to provide the funds needed to
accomplish this improvement as soon as possible. The City of Fridley and MN/DOT have
worked together to bring this project to the point that it can be placed under contract for
construction this year. The project is "Ready To Go."
Wher~ Life Depends on Medical Technology
Medtronic Transpo~ation Positions
March 22, 2002
Page 2
2) We, and our Fridley neighbors, also need the Northstar Corridor Commuter Rail
Project fully funded. That means $120 Million in General Fund Bonding to provide the
state's match of Federal funds so that this project can move forward on schedule. With
the Fridley Train Station located at 61't & East River Road, many of our employees would
benefit from the opportunity to use transit services. The tracks already exist and the sooner
we can put trains on them, the better for ali of us.':
Please find attached to this letter additional information on the TH 65 and Northstar Commuter
Rail Projects. Theae projects will provide Medtronie and our neighbors with badly needed
transportation and transit services that will better serve oar world headquarters facility and the
State of Minnesota.
Thank you for your consideration and for your leadership on behalf of Minnesota.
Very truly yours,
David D. Etzwiler
Director, Community ~q~ffairs
Attachment
'Medt, ronic's Position on the TH 65 Causewa~t
Medtronic, along with other conunercial enterprises north of 1-694 in Fridley and beyond,
strongly supports the TH 65/Moore Lake Causeway Project to provide access to our facilities
in a saf~ and ~ffi~ient manner.
The TH 65/Moore lake Causeway project is needed to safely and efficiently serve the
estimated 3,000 new jobs the Medtronic Corporate campus is expected tO generate along
with ancillary commercial facilities such as hotel and restaurant facilities along the corridor.
The TH 65/Moore Lake Causeway is needed to reduce congestion on streets that serve the
residential neighborhoods abutting the campus. Previous improvements have helped, but
additional lanes are.needed to reduce delays, improve access, improve goods.movement
efficiency and reduce accidents. Medtronic supports other transit service options to further
address congestion issues,
The TH 65/Moore Lake Causeway project is needed to reduce carbon monoxide emissions
caused by the present congestion on TH 65 from 1-694 to W. Moore Lake Drive. The
proposed improvement would reduce carbon monoxide emissions by 40% daily,
This project meets the essential test of good public policy, as it is consistent with the
Metropolitan Council's Development Guide, including the Transportation Policy Plan and
the Regional Blueprint. This project supports many of the explicit policies of both
documents.
Medtronic's Position on the Northstar Corridor
Medtronic strongly supports full funding by the Legislature for the Northstar Commuter Rail
Project as a viable and needed lxansportation option.
· The Northstar Project will help to alleviate growth in congestion by taking nearly 10,000
vehicles off the roads each day, the equivalent of 1~ lanes of traffic during peak usage.
· The Northstar Project provides an excellent retum on investment as the rail lines are in place
and can be readied for passengers in a relatively short period of time.
The Northstar Project is a critical transportation element for the rapidly growing northwest
suburbs and the immediate corridor communities.
Medtronic has made its commitment to provide thousands of employment opportunities to
residents in the North Metro area. Safe, efficient, and effective transportation options
including the Northstar Corridor are necessary for us carry out that commitment.
FLOOR DEBATE
HOUSE OF REPRESENTATWES
MARCH 14, 2002
Speaker of the House:
The Representative from Anoka, Rep. Tingelstad.
Rep. Tingelstad:
Thank you Mr. Speaker. Well I hope everybody's paying attention.
seeing politics at it's worst. This is a game.
Tonight you are
(applause)
I know emotions are really running high, and I gotta tell you this Northstar legislation is
the toughest bill I've ever carried. But if you believe in something, if it's going to work,
you follow it through to the end.
You know through this process I've lost a lot of friends, and I feel bad about that because
I really thought you were my friends. I've been called greedy. I've been called a caucus
buster. I'm really a bad person over here for doing what I think is right, for doing what
people in my community say we need!
Let me tell you. We are underrepresented here in the House of Representatives. After
Tuesday we get some new maps for redistricting. There's gonna be four more members
from Anoka County, Sherburne County, Benton County - then we get the correct
representation for an area that is really important to our state.
This just drives me crazy. I can't believe these games. What's come up here? Right
now we're on the homeless issue. Okay they want us to vote against homeless. Next we
have anti-terrorism equipment grant. Okay they want us to vote against that. But the
killer of all. Student per pupil funding. This is getting ridiculous.
Mr. Speaker I appreciate the process we've gone through tonight. I appreciate that you
allowed us to follow the process. In the transportation finance committee Rep.
Westerberg had the amendment for $60 million. He got the votes. It went on the bill.
What happened? The bill was pulled. So next, the bill failed, they voted no on the bill
because it had the Northstar amendment on it. Okay, next step. We do our work.
Capital Investment. I offer the amendment for $30 million. It goes on. After working
really hard with all the Capital Investment .,. Capital Investment Committee thought it
was right. It went on. So what happens next? It goes to Ways and Means and it gets
peeled off. You don't even leave me a respectable 8 or 9 million to negotiate with the
Senate - you zero it out!
And here we are back at the House. We follow the process again. 71 votes. Bi-partisan.
This is a sham all these amendments! Members, we're trying to stay away from bad
politics, and I think tonight we're giving bad politics quite a name.
(applause)