6.4. SR 01-22-2001City of River MEMORANDUM Item//6.4. TO: FROM: DATE: SUBJECT: Housing and Redevelopment Authority Mayor & City Council Pat Klaers, City Administrator January 22, 2001 Central Business District Sidewalk INTRODUCTION Staff understood that reaching a consensus and decision on what to do with the sidewalks in the central business district would be difficult. This is especially true as the sidewalk decision is being made prior to an updated downtown comprehensive plan being completed. There are as many options for a downtown sidewalk plan, as there are individuals with opinions about what looks good and what we can afford. I think everyone is going to have to come with "compromise" on his or her mind if a consensus is to be reached on the sidewalk replacement project. After numerous staff meetings and discussions, our recommendation is that the sidewalks in the central business district, including the King and Main site, should be all the same. The downtown area needs one consistent look and appearance. Two or more sidewalk designs installed downtown will give the impression that the project was not well planned and the area will have a disjointed or hodgepodge look. Additionally, it is our recommendation that the best look for downtown is the Cobblestone paver in the random pattern rather than the Symetry paver in the venetian parquet pattern (see attached brochures). Regarding which concrete paver design is best downtown; it is still staffs recommendation that a solid (100%) Cobblestone paver is best. We have some combination paver/fiat gray design options available for review and consideration, but the various widths of the downtown sidewalk and the cutting of the pavers make it difficult for some of the paver/fiat gray combinations to look good. The extra cost between the total paver and a 13065 Orono Parkway · P.O. Box 490 · Elk River, MN 55330 · TDD & Phone (763) 441-7420 · Fax (763) 441-7425 CBD Project January 22, 2001 Page 2 of 4 paver/fiat gray combination is relatively small ($74,000), especially when considering that the project should last for a very long time. SIDEWALK OPTIONS AND COSTS What option is chosen for a sidewalk, the Cobblestone paver versus the Symetry paver, impacts what recommendation is most appropriate for a downtown sidewalk design. The Cobblestone paver with a random pattern can more easily be broken up and look good in a non-solid design as compared to the Symetry paver that is in the venetian parquet pattern. This comment has to do with the width and cutting of the pavers in a non-solid or non-100 percent paver design. (This is tough to explain, but I hope the attached pictures and the design sketches help make this clearer. Regarding the sketches, please note that people don't really see the sidewalk from straight above and that from this angle both the 100 percent paver options are rather "busy," but they look better in person.) Staff is still united in its recommendation that the Cobblestone paver is the best appearance for the downtown sidewalk replacement program. This appearance presents a traditional look (not necessarily historic) that is consistent with the existing downtown streetscape program and the existing older buildings. This look also works well with a new building as the developer of the King and Main site discussed on 10/23. The modern paver (Symetry) look does not work as well with the existing streetscape appearance and the older buildings in the downtown. This modern look is all right with new buildings, but the new buildings are not the dominant look downtown. The Cobblestone and modern (Symetry) paver cost about the same. It should be noted that the city does not plow the sidewalks downtown and that there are minimal, if any, maintenance issues with a paver sidewalk versus a concrete sidewalk. Finally, the pavers are stronger than standard concrete (less salt damage) and are easier to replace than concrete. Also, when replaced, pavers match old pavers better than new concrete matches older concrete. The cost estimates and top three recommendations of the staff for the sidewalks are as follows: 1. 100% Cobblestone paver. ($290,000) Cobblestone paver at the intersections and along the curbline. ($250,000) 3. 100% Symetry paver. ($290,000) CBD Project January 22, 2001 Page 3 of 4 Staff doesn't think that the Cobblestone or Symetry paver only along the curbline ($237,000 for either), or the Cobblestone or Symetry paver only at the intersections ($216,000 for either) is enough of a downtown sidewalk design. I don't believe anyone wants the 100% fiat gray concrete sidewalk, but for your information, that cost is estimated at $183,000. All of the costs being noted include the cost of removal of the old sidewalk, a 5% contingency, 10% for overhead, and $25,000 for miscellaneous work. At this time the King and Main developer is willing to pay 100% of their sidewalk if it is a solid paver sidewalk. All of the cost estimates exclude this King and Main intersection. Discussion has not taken place regarding the developer's feelings for paying 100% of the sidewalk if the city requires a combination paver/fiat gray concrete sidewalk in this location. It should be noted that all of the costs listed are most likely going to be reduced by about $20,000 as we work with the Utilities on their improvement project. In general, the Utilities need to remove the sidewalk on the entire north side of Main Street and they will pay this cost provided that the city pays the replacement cost. This seems reasonable and it is estimated that their expense will be about $20,000 and a direct reduction in the project figures. As an aside, the Utilities have indicated that they would like to complete their project prior to the Arts Soup Festival (June 22) rather than after. HRA FUNDS The HRA has an anticipated 12/31/00 fund/cash balance of approximately $90,000. Additionally, the 2001 budget shows a surplus of $51,000 for projects that are undetermined at this time. This type of budget surplus could continue for the next few years and, if desired, applied to a sidewalk project. In addition to the HRA tax monies, the TIF project at King and Main needs to repay the HRA for its net investment into this redevelopment project. This repayment of $293,000 begins in 2003 with $49,000 and continues until the investment has been recaptured. Accordingly, if desired, the HRA can afford part or all of a sidewalk project over the next few years, even if the total cost of a sidewalk replacement program is in the $275,000 range. CBD Project January 22, 2001 Page 4 of 4 1988 PROJECT In 1988 the downtown streetscape project took place. Costs that were above and beyond a normal sidewalk and lighting project were assessed out to the benefited property owners in the downtown area. In this regard, extra costs for lights, tree grates, trash receptacles, and textured sidewalk were assessed. The assessment from the 1988 streetscape project shows that lights were 55%, tree grates 25%, trash receptacles 10%, and sidewalk 10% of the total. Accordingly, assessments for sidewalks were a small part of the streetscape assessments. The attached 4/4/88 minutes show the breakdown of the costs that were assessed out thirteen years ago. In 1988, the textured sidewalk was 22.5% more than a concrete sidewalk. With this proposed project in 2001, the construction of a paver sidewalk is about 58% more than a fiat gray concrete sidewalk. If you think that a fiat gray sidewalk would never happen, then it should be noted that the solid paver design is 35% higher than the next cheapest sidewalk option, which incorporates pavers only at the intersections. CONCLUSION As there was no clearly understood consensus from the 10/23 or 11/27 meetings, we are again going to try to reach an understanding on a sidewalk program for 2001. The central business district property owners and the Chamber of Commerce have been notified of this meeting and the developer will be providing examples of the paver products and the sidewalk designs. All Councilmembers are encouraged to come to the HRA meeting to see the presentations and to hear citizen input. Ail HRA and Councilmembers are also encouraged to see the paver examples that are in the driveway and sidewalk of the Plaisted office at County Road 33 and Highway 169. Goals for the meeting include reaching a consensus on: 1) the type of sidewalk, 2) the design of the sidewalk, and 3) who is to pay what for the sidewalk. Whatever is agreed to needs final City Council approval as the sidewalk is in the public right-of-way. Staff recommends that there be one look throughout downtown and that this look be the Cobblestone paver (random pattern). Staff further recommends, but to a lesser degree, that the Cobblestone be a 100% install. Finally, it should be noted that funds are available over the next 4-5 years to finance whatever share of the project the HRA wants to assume. s: \ eda \ hra \ cbdwalks.doc City Council Meeting April 4, 1988 Page 2 5,2. Central Business District Beautification Improvement Assessment Hearin8 Public Hearing Mayor Gunkel explained that the project is priced as low as possible and meets the objectives for beautification of the downtown area. She noted that the bids were open for the lighting aspect of the project and that most of the prices in the project were firm. Greg Korstad, City Attorney, explained the assessment hearing process. He noted that the purpose of the meeting is to receive input from the people proposed to be assessed for the beautification improvement. He noted that the City is proposing to assess the cost of the project on a per unit basis. He noted this is based on the City Council evaluation of the most fair way to proportion all of the costs to the properties benefited. He explained that all property owners should have been notified of the assessment and of the proposed assessment method and that the property owners should make their objections known to the City Council at this time. Mr. Korstad also explained that the lighting contract may not be awarded until the appeal period is expired, which is 30 days from the date of the assessment roll being adopted. Terry Maurer, City Engineer, explained that the City has received the street lighting bids and also has received quotes on the other elements of the project. Mr. Maurer reviewed the cost of the project which is as follows: ITEM ASSESSED OTHER TOTAL COST Street Lighting $65,000 $35,000 $100,000 Trees -0- 18,300 18,300 Tree Grates 29,000 -0- 29,000 Trash Receptacles 11,500 -0- 11,500 Textured Sidewalk 11,800 -0- 11,800 $117,300 $53,300 $170,600 Mr. Maurer explained that the method of assessment of a per unit basis is based on the input from the mock assessment hearing held January 21, 1988. He noted there is a total of 40 assessable units; 37 whole units to be assessed at a rate of $2,950 per parcel, and 6 half units to be assessed at a rate of $1,475 per parcel. Mr. Maurer noted that the interest is calculated at a rate of 10% but may be reduced when the bonds are sold. Mayor Gunkel opened the public hearing at this time. Mr. A1 Nadeau, property owner and business owner, presented a letter including a list of property owners wishing to appeal the assessment. the following names were included in the list: City Council Minutes April 4, 1988 Ronald Kuhn Harvey Wohlers Allen Nadea~ Joseph Sipe Michael Rafferty Ronald Robeck Robert Dare Hetrick - Amoco R.A. Dorsey Dan Anderson (includes 4 parcels) Mayor Gunke 1 indicated Dale Johnson, who is zone. she had also received a notice of appeal from a residential property owner in the commercial Mr. Dan Anderson, property owner of 4 separate parcels of property, indicated that while he did sign the document objecting to the assessment, he was actually not opposed to the assessment or the project, but was opposed to the fact that the commercial properties west of Lowell were not included in the assessment. He indicated the properties west of Lowell had requested to become part of the commercial area and the Council extended the commercial area to accommodate the request. He indicated that the total commercial area should be given an opportunity to be part of the project and not to restrict the assessment to only a portion of the downtown area. Dick Dorsey, property owner and business owner of Dick's Main Tap, indicated his opposition to the beautification project. He stated he was against a majority of the improvements but was in favor of adding trash receptacles to the downtown area. He stated he was also opposed to the method of assessment and felt the assessment should be determined by front footage. He stated this should be dealt with in the same method as sewer and street assessments. Steve Johnson, property owner and business owner of Johnson's Department Store, indicated his support for the project. He indicated that the City of Monticello is proposing the same type of project and the price is much higher than the City of Elk River is charging. Mr. Johnson stated that the' criteria for drawing new business to the community is the location, and the beautification of downtown will draw business to the downtown area. He also indicated that the assessment method is the best compromise for determining the assessment amount due per parcel of property. Mike Rafferty, property owner and business owner of Elk River Chiropractic Office, indicated he was not totally opposed to the assessment, but that he was opposed to the method of assessment. Mr. A1 Nadeau stated that the people signed the document opposing the assessment with the knowledge that the assessment per one full unit would be $3,750. He indicated that with the new figure of $2,950, there may be some people willing to withdraw their signature. City'Council Minutes April 4, 1988 Bud Houlton, property owner, indicated his support for the project. He stated that creating an environment and atmosphere for the downtown area is very important. Mr. Houlton stated the First National Bank would be willing to contribute one extra unit ($3,750) towards the cost of the project. Duane Kropuenske, Senior Officer of the First National Bank, indicated he was in favor of the project. Mr. Kropuenske stated that by adding up the total assessment and dividing it out on a per month basis, the figure is somewhere around $30 to $40 per month. He indicated this is a relatively small price to pay to attract business to Elk River. Mr. Ron Kuhn, property and business owner, stated his opposition due to the fact that the commercial properties west of Lowell are not included in the assessment district and also that the properties east of his business will receive more benefit than his property. He indicated he would like to see the project vetoed until the Council has a chance to look at the benefitting properties and assess them according to benefit received. Mike Rafferty proposed a different assessment method at this time which he indicated was a more fair method than that being proposed by the City Council. He indicated that his method would increase the financial burden of the large properties and decrease the financial responsibility of the smaller properties. This proposal is placed on record with the official City Council minutes. Mr. Jim Mulroy, business owner of Snyder Drug, indicated that he is in favor of the project. Mr. Rob VanValkenberg, property and business owner of three parcels, indicated he was in favor of the project. Councilmember Tralle indicated that both the Governor's Design Team and the 2001 group have heavily encouraged the City to work on the downtown area. He indicated the downtown beautification would serve as a major focal part of the community and it would encourage retail growth and also encourage people to shop in the downtown area. Councilmember Tralle stated that the front footage assessment method was unfair in that the large property owners do not receive much more benefit than the small property owners. He further indicated that the Council should possibly look at extending the assessment district to the commercial properties west of Lowell since these properties are within a commercially zoned area. Robert Dare, business owner and property owner, stated that he is not against the cost of the project but opposes the fact that the commercial properties west of Lowell Avenue are not included. Elmer Anderson, property and business owner, thanked the Council for all they have done so far for the downtown beautification project. He indicated his support of the project. Mr. Keith Holme, business owner, indicated his support for the project. City Council Minutes April 4, 1988 rage Mr. Cliff Lundberg, business and property owner, and Chairman of the Downtown Committee, stated that the proposal before the Council and the residents is a very cost effective proposal and that it would possibly be more expensive if the project were delayed until a later date. He stated that he would like to see the Council order the project tonight so the electrical contractor can start work and not delay the project. Charles Christian, property owner and business owner, indicated his support for the project. There being no further comments from the public, Mayor Gunkel closed the public hearing. Mayor Gunkel indicated that there was a lot of discussion and thought process by the Council and Staff in determining the method of assessment and the area to be assessed. She indicated that the main element in this is timing and coordinating the lighting aspect of the downtown beautification project with the entire Main Street Project. She indicated that if the Council did choose to reconsider the method and area of assessment, the carefully planned timing schedule would no longer be valid. Pat Klaers, City Administrator, informed the Council that if the assessment roll is adopted at this time, the people who have submitted letters of objection will have the right to appeal, however, there are additional steps to the appeal process which must be taken by these individuals. Councilmember Dobel indicated that if the Council does not go ahead with the project, valuable time from a number of people will have been lost. He stated that this project is needed and has been needed for a long time and if the opportunity is missed it may never present itself again. He indicated he was in favor of approving the project but would like to look again at the method of assessment. Mayor Gunkel indicated that the Council has tried everything possible to make the project acceptable. She stated that if property owners do appeal the project, the City would be in a defensible position regarding the amount and the method of assessment. She indicated that one of the reasons for keeping the assessment area east of Lowell was to keep the assessment at a defineable boundary, which is Lowell Avenue. She indicated she felt the Council is satisfying a majority of the people and that the project is very cost effective. Councilmember Holmgren indicated he was in favor of the project, however, would like to see the Council look at extending the assessment area to the commercial properties west of Lowell. Mayor Gunkel indicated that if the Council were to look at possibly changing the assessment area, it would be a great inconvenience to the customers. She noted a lot of preliminary work has went into coordinating the project in order to keep a strict time schedule. She stated that the Council has already reviewed and determined the area to be assessed and method of assessment at a previous meeting, and stated Page 6 City Council Minutes April 4, 1988 there is no reason to reconsider these elements as it will result in delaying the entire project. The City Administrator indicated that if the four or five commercial properties west of Lowell Avenue were added, it would add to the expense of the project and more than likely would not decrease the assessment amount to the property owners. Coun¢ilmember Tralle indicated that he agreed with the City Administrator and also with Mayor Gunkel in that changing the assessment district would delay the project. COUNCILMEMBER DOBEL MOVED TO ADOPT RESOLUTION 88-23, A RESOLUTION ORDERING THE IMPROVEMENT IN THE MATTER OF THE DOWNTOWN BEAUTIFICATION IMPROVEMENTS OF 1987. COUNCILMEMBER TRALLE SECONDED THE MOTION. Councilmember Schuldt indicated that he has heard many indirect negative comments from the business people (tenants) regarding the downtown project. He stated he had hoped that the people would have come forward and personally voiced their concerns, but has not heard any first hand objections since the start of the project and noted that because of this he would be voting to order the improvement. THE MOTION CARRIED 5-0. ~0UNCI~M]~M]$ER TRAL~E MOVED TO ADOPT RESOLUTION 88-24, A RESOLUTION ADOPTING THE FINAL ASSESSMENT ROLL IN THE MATTER OF THE DOWNTOWN $~AUTIFICATION IMPROVEMENTS. COUNCILMEMBER DOBEL SECONDED THE MOTION. Councilmember Tralle indicated that to reconsider the method or area of assessments would delay the project and would be too costly at this point. Councilmember Schuldt stated that street and sewer is based on a front footage basis. He noted that the method of assessment for the beautification items is a different matter as the items being assessed do not run by properties on a front foot basis. He noted that it is difficult to assess this in the same manner as the sewer and street improvements. He noted that because the improvements are of the nature they are, he is in favor of the method of assessment. THE MOTION CARRIED 5-0. C0UNCILM~aMBER SCHULDT MOVED TO ADOPT RESOLUTION 88-25, A RESOLUTION ACCEPTING BID FROM SPENSOR ELECTRIC AT A PRICE OF $73,243 AND AUTHORIZING EXECUTION OF CONTRACT IN THE MATTER OF THE DOWNTOWN STREET LIGHTING IMPROVEMENT OF 1988. COUNCILMEMBER HOLMGREN SECONDED THE MOTION. THE MOTION CARRIED 5-0. EXISTING BUILDING <~ Z O EXISTING GAZEBO WIDE VARD EX. STREET LIGHT (TYP.) EX. TREE GRATE (TYP.) 10' WIDE BOULEVARD MAIN STREET ,////---10' WIDE BOULEVARD ~~~~~~. ////////////////////////////////// r////////////, / / / / / / EXISTING / EXISTING BUILDING EXISTING BUILDING / ALLEY / / / / / / / / / NOTE: SIDEWALK PAVERS ARE NOT SHOWN TO SCALE NO.DATE ~Y R~M~ON DESC~PTION ~ ~J~aY c[R'~"Y 'mA'r 'mrs PL~, ~[OnC~T~0~, 1326 ENERGY P~K DRI~ DE~ED BY:~ DRA~ BY: EY ~~ ~R~m ST, PAUL, MINNESOTA ~108 ~ ~ ~AT I ~ A ~LY ~S~R~ (651) 644--4~59 ~RO~D BY:APPRO~D BY ~ NUMBER 81142~ ~ ENGN~R ~ ~ LA~ ~ ~[ ~ ~,~:~ .... ~ ,,. ~oo, ,,:~,:,~ .... ~d R. ~en Company C~ FILE: 2300~m~exhlblts~AIN-JAC[SON6.DW~ ~ A~ CONSULTING ENGINEERS cn'Y OF B_K RNER COBg_E - RANDOM PA'FrERN MAIN STREET AT JACKSON AVENUE SIDEWALK IMPROVEMENTS o lO SHEET NO. 1 EXISTING BUILDING -- EX. STREET LIGHT (TYP.) EX. TREE GRATE (TYP.)/ EXISTING GAZEBO WIDE 10' WIDE BOULEVARD MAIN STREET ////////////. / / / / / / / / / EXISTING ALLEY EXISTING BUILDING / EXISTING / / / / BUILDING NOTE: SIDEWALK PAVERS ARE NOT SHOWN TO SCALE DESIGNED BY:K7 DRAWN BY: EY APPRO~D BY:APPROVED BY JO~ NUMBER 811420J CAD DATE: Jonuory 11 2001 11:54:18 o.m. CAD FILE: ~,3000Om~exhibits",,MAIN-JACKSON6o.DWG ~ 1526 ENERGY PARK DRIV~ ST. PAUL, MINNESOTA ,55108 (651) 644-4589 -Ioward R. Green Company CONSULTING ENGINEERS CITY OF ELK RIVER TOWN-SQUARE + ~ PA'F['ERN MAIN Sq'REET AT JACKSON AVENUE SIDEWALK IMPROVEIVlE~[TS 0 10 S~££T NO, EXISTING BUILDING · ' .~' - · ' ' ' ' '~' '~' '~. -'~' ~' .',~ '. "" EX. TREE GRATE (TYP.) EXISTING GAZEBO WI DE VARD 10' WIDE BOULEVARD MAIN STREET ///--10' WIDE BOULEVARD / EXISTING / EXISTING BUILDING EXISTING BUILDING / ALLEY · · CAD DATE:Jonuary 11, 2001 11:54:18 e.m. CAD FILE: 230000m\exhibits\MAIN-JACK$ON.DWG DESIGNED By:K'f DRAWN BY: EY APPROVED BY:APPROVED BY JO~ NUMBER 811420J KO. DATE -BY [ [ 1526 ENERGY PARK DRIVE ST. PAUL, MINNESOTA .5.5108 (651) 644 - 4,~89 Howard R. G'een Company CONSULTING ENGINEERS crfY MAIN STREET AT JACKSON AVENUE SIDEWALK IMPROVE~ 0 10 NO. 2 aa' EXISTING BUILDING :'~,' · '. "'i .,' 4~ ....... ~ .' . . . · ....' · ,1, . ,~ . ~.. . /1' . . .. . . a , . ' ' ,~ - ' .- .,~,; - ' . ' ' . ' ' - - ~ .. . .. '~ · "~ - 4l' " ~, ·' - ~ EX. TREE GRATE (TYP.) -~ Z 0 3.5' WIDE PAVERS MAIN STREET 3.5' WIDE PAVERS / EXISTING / EXISTING BUILDING EXISTING BUILDING / ALLEY NOTE: SIDEWALK PAVERS ARE NOT SHOWN TO SCALE DESIGNED BY: KT DRAWN BY: ~ APPROVED BY:APPROVED BY JO~ NUMBER 811420J CAD DATE: Jonuery 11 2001 11:54:18 o.m. CAD FILE: 230000m~exh;bltsX, MAIN-JACKSON7.DWG I 1,326 ENERGY PARK DRIVE ST. PAUL. MINNESOTA 55108 (651) 644-4589 Howard R. Green Company CONSULTING ENGINEERS MAIN STF:EET AT JACKSON AVENUE SIDEWALK IMPROVEMENTS o Io ~'lEE T NO. 3 · ~ ." , .~ · ~. · ,~ . ,, .~ · · . ..~ ., ,. , . . :. '..- , .., ~ .~ .~..~,;,~.,~// EX. TREE GRATE (TYP.)-~ Z <I: 3,5' WIDE PAVERS MAIN STREET / EXISTING / EXISTING ILDING EXISTING BUILDING / BU / ALLEY NOTE: SIDEWALK PAVERS ARE NOT SHOWN TO SCALE DESIGNED BY: k'T DRAWN BY: EY APPROVED BY:APPROVED BY JOB NUMBER 811420J CAD DATE.' Jonuory 11 2001 11:54:18 o.m. CAD FILE: ~3000Om~,exhiblts~MAIN-JACKSON7A. DWG ST. PAUL. MINNESOTA 55108 (651) 644-4,389 R. Green Company CONSULTING ENGINEERS jOI'TY OF ELK RIVER TOWN-SQUARE -I- 8YMETRY PATTERN MAIN STREET AT JACKSON AVENUE SIDEWALK IMPROVEMENTS 0 10 ~F..~T NO. 3A EXISTING BUILDING " ' '"""' '"""'"':' ;' '" '" '?..'"~" "t .""' '"' "" " ' ':. 'i'.'i:' 'rb7 i-.~-,.i~ .i,~. ,. i.,",.. '..-.' :'..?"..." ' F51. "~ GRATE EX. TREE TYP.) Z 0 EXISTING GAZEBO MAIN STREET ,~ 10' WIDE BOULEVARD EXISTING BUILDING / / / / / / / / EXISTING ALLEY · .' '. 4 . . ;' ~' '' / / /  EXISTING BUILDING NOTE: SIDEWALK PAVERS ARE NOT SHOWN TO SCALE DESIGNED BY: K'f DRAwN BY: EY APPRO~B BY:APPROV~D BY JOI3 NUMBER 811420J CAD DATE:Januor¥ 11 2001 11:54:18 o.m. CAD FILE: 230000m~exhlbits%MAIN-JACKSON8.DWO ? 1526 ENERCY PARK DRIVE ST. PAUL. MINNESOTA ,55108 (631) 644-4589 rd R. Green Company SULTING ENGINEERS crI'Y OF ELK BVE~ COBBLE - RANDOM PA'R'ERN MAIN STREET AT JACKSON AVENUE SIDEWALK IMPROVEMENTS 0 10 ~'IEET NO. 4 z EXISTING GAZEBO WIDE ~VARD 10' WIDE BOULEVARD MAIN STREET 10' WIDE BOULEVARD ,4' ~ '~.. .. ,a .'~ "" :,~ ': .... . :- ~ ',4 . . ,~.~' ~, : , · '' .' ~ : .. .. ~ ... . . ~ ... ',~ '. . . ~ .. .~ '. · . . : ' . . . . ..'. . . · . · . ' ..~ ~ ' . .,~ ,4" ~ ' ,~ ,~'~. .. .. ~. · . . '.. · -/ EXISTING / EXISTING BUILDING EXISTING BUILDING / ALLEY / NOTE: SIDEWALK PAVERS ARE NOT SHOWN TO SCALE DESICNED BY: K'I' DRAWN BY: APPROVED By:APPROVED BY JO~ NUMBER 811420J CAD BATE: Jonuory I1 2001 11:54:18 a.m. CAD FILE: 230000rn~exhiblts~MAIN-JACKSONSA. DWG 1526 ENERGY PARK DRIVE: ST. PAUL. MINNESOTA 55108 (651) 644- 4,.~89 -Ioward R. CN'een Company CONSULTING ENGINEERS CITY OF ELK RNER TOWN-SQUARE + SYMETRY PATFERN MAIN STREET AT JACKSON AVENUE SIDEWALK IMPROVEMENTS 0 10 SHEET NO. 4A EXISTING BUILDING ~ ' · ',:-":,.~ ...-... :.' .. '.. ..-.-.' -,, .,.. ;.. ., 4',;. ' .'-. 'L .~ . . .,~ · ' 4~ '. ." .*" '" ,, -. '.'.. ': " '. -' -' . .- . ~' ' . ~* · E · ~. . · .. .'~. .~...~. . .- . · ... . .~ .-.... ~ ... . . ~,. :.. -,~..~ LEX. STREET LIGHT (TYP.) EX. TREE GRATE (TYP/)/ Z 0 (/3 ,,~ CD MAIN STREET 3.5' WIDE PAVERS /////////////////////////////////~ EXISTING BUILDING / / / / / / / / EXISTING ALLEY ////////////, / /  EXISTING BUILDING / / / / / NOTE: SIDEWALK PAVERS ARE DESIGNED BY:KT DRAWN BY: EY APPROVED BY:APPROVED BY JOB NUMBER 811420J CAD DATE:Jonuory 11 2001 11:54:18 o.m. CAD FILE: 2.30000m~exhibits%MAIN-JACK$ONg.DWC; NOT SHOWN TO SCALE  (651) 644-4589 ~ IHoward R. Green Company CONSULTING ENGINEERS CITY OF ELK RIVER COBELE - RANDOM PA'i'rERN MAIN STREET AT JACKSON AVENUE SIDEWALK IMPROVEMENTS 0 10 SHEET NO. 5 L3 5' WIDE PAVERS MAIN STREET .....,..~'. ,.: ~'.~,.~ .?., '..!, ,., ,,.......,-- ,...;- -.. -.- .-.,-.. ,- , .... -. ~, . -...: ////////////////////////////////// ////////////, / / / / / / EXISTING / EXISTING BUILDINO EXISTING BUILDING / ALLEY / / / / / / / / / / NOTE: SIDEWALK PAVERS ARE NOT SHOWN TO SCALE DESI~/ED BY: KT DRAWN BY: EY APPROVED BY:APPROVED BY ~ NUMBER 811420J CAD DATE: Januory 11, 2001 11:54:18 CAD FILE: 230000m~exhiblts'~MAIN-JACK~ONgA.DWO l 1326 ENERGY PARK DRIVE ST. PAUL, MINNESOTA 55108 (651) 644-4589 Howard R. Green Company CONSULTING ENGINEERS CfTY OF ELK RIVER TOWN-SOUARE + SYMETRY PATTERN MAIN STREET AT JACKSON AVENUE SIDEWALK ~PROVEMENTS 0 10 ~ET NO. 5A