4.3. SR 01-13-2003tkiver TO: FROM: DATE: SUBJECT: MEMORANDUM Mayor and City Council Lori Johnson, Finance Director January 13, 2003 Consider Public Safety Facility Change Orders Item 4.3. The following change orders have been requested on the public safety building. Most of thc items are minor construction changes. The large items include additional storm sewer pipe, the addition of a water softener system, and thc deletion of infra-red heating in thc fire station bays. Bid Package Contractor Number Dryden Excavating Kelleher Construction Daka Corporation Daka Corporation Western Steel George F. Cook Construction Northern Air Corporation Sentra Sota Sheet Metal Sentra Sota Sheet Metal Collins Electrical Total Previously Approved Total Change Orders to Date 11 12 14 4O 43 43 45 Change Order Number 5 1 8 1 11 1 2 1 2 Change Order Amount 10,650.00 280.00 1,922.00 115.00 2,188.00 4,498.00 14,997.00 (10,641.00) 178.00 954.00 25,141.00 5,902.00 31,043.00 Attached is a budget summary for the public safety project that includes these change orders. The project is still well under budget with these change orders. Action Requested The City Council is asked to approve the change orders as noted above.