5. HRSR 09-04-2007ITEM # 5.
mover
MEMORANDUM
TO: Housing & Redevelopment Authority
FROM: Catherine Mehelich, Director of Economic Development
DATE: September 4, 2007
SUBJECT: Discuss Mississippi Connections Redevelopment Framework Plan
Project
Attachments
• Draft City Council meeting minutes of August 20, 2007
Issue
HRA Chairman Wilson has requested an HRA discussion on the Mississip~ii Connections
Redevelopment Framework Plan Project and related issues following the recent action of the
City Council to suspend the Task Force until completion of a Highway 10 geometric study
(see attached draft Council minutes).
The issues for discussion may include:
• Estimated timeframe for Highway 10 geometric study
• Gauge commitment of HRA/Task Force members to reconvene upon completion
of Highway 10 geometric study
• Identify HRA priority projects and work plan during interim
S:\Downtown Revitalization\Master Redevelopment Plan\Task ForceVvlemos\HRA memos\hra 9.4.07.doc
City Council Minutes (1 ~ /(~\ ~ I I Page 3
August 20, 2007 ~ U u(r-V LL11
Mr. Barnhart requested to postpone this item but noted it was advertised for a public
hearing.
Mayor Klinzing opened the public hearing. There being no one to speak to this issue, Mayor
Klinzing closed the public hearing.
MOVED BY COUNCILMEMBER GUMPHREY AND SECONDED BY
COUNCILMEMBER FARBER TO CONTINUE THIS ITEM AND REPUBLISH
THE PUBLIC HEARING NOTICE WHEN IT IS READY FOR
CONSIDERATION. MOTION CARRIED 5-0.
6.2. Confirm the Direction of the Redevelopment Framework Plan (Mississippi Connections)
Task Force Regarding Highway 10
Mr. Leeseberg presented the staff report.
Mayor Klinzing questioned if the proposed cut and cover design for Highway 10 would
have a cover over it. She thought it would be similar to 35W in Duluth and would allow
green space over the top.
Mr. Maurer stated it may not have a cover if it is not needed functionally and Mn/DOT
would make this determination.
Councilmember Motin expressed concerns with having the Taskforce continue this Plan
(Mississippi Connections) when a large part of the puzzle (the final design for Highway 10)
is incomplete. He stated he would like the proposed alignment for Highway 10 finalized
before moving forward. He stated he would like to suspend the Taskforce until a Geometric
Study (Study) could be completed.
Mayor Klinzing stated the Plan is long-term so it would make sense to wait until a Study was
completed. She noted that the Taskforce did an excellent job on this plan.
Councilmember Motin questioned what the Council would like to see if a developer wants
to build along the highway prior to a final plan being completed.
Councilmember Gumphrey stated the Taskforce did an outstanding job with the Plan and
he doesn't want to stop their progress.
Councilmember Zerwas stated the city would be putting property owners in a difficult
position if there are too many plans in place. He questioned the timeframe for the Study.
Mr. Maurer stated the Study might possibly be incorporated into the 169 Study with the
understanding that the city would pay for it. He would need to get confirmation from
Mn/DOT. He stated it could be six to nine months before completed to the alternative
selection stage.
Councilmember Gumphrey questioned the cost of the Study.
Mr. Maurer stated it would depend on the level of work completed but could be up to
$500,000. He stated the cost would depend on whether the Council wanted land use powers
Ciry Council Minutes ~ ' " ~ '. ~ ,_ Page 4
August 20, 2007 ~~ ~~ ~ ~-~ t~ ~~
for right-of--way but further noted the environmental portion of the study would have a
limited shelf life.
Councilmember Farber stated he would like to see Jackson Avenue and Main Street remain
open.
Councilmember Motin questioned members of the Taskforce as to how they feel if the
group was put on hold until the Study could be completed.
Ms. Mehelich stated the taskforce hasn't had an opportunity to discuss this as a group.
Stewart Wilson stated that due to the amount of time spent on the Plan he would like the
original members to stay together.
Councilmember Gumphrey stated work could be done in the interim by the Taskforce but
he was also fine with postponing the group for six months.
Mayor Klinzing stated she would like to hear what the Taskforce would like to do.
Ms. Mehelich stated the Taskforce understands amendments could be made to the original
Plan after the Study is completed.
Councilmember Motin stated the issue with trying to proceed further is that the general
public will focus on the worst parts of the Plan. He stated there will be confusion with the
changes and the city would have to redo all the hearings. He stated he would rather wait 6-9
months and not have a duplication of efforts. He stated this is a long term plan and there is
no rush to complete it.
MOVED BY COUNCILMEMBER GUMPHREY AND SECONDED BY
COUNCILMEMBER FARBER TO SUSPEND THE REDEVELOPMENT PLAN
TASKFORCE UNTIL A HIGHWAY 10 GEOMETRIC STUDY IS COMPLETED
AND WHEN THE TASKFORCE RECONVENES, IT WILL RECONVENE
WITH THE SAME MEMBERS. MOTION CARRIED 4-1. Mayor K]inzing opposed.
Mayor Klinzing stated she could not support this motion because the Taskforce could work
on other areas of the core downtown.
Larry Toth, Stated the motion was off key by not having the Taskforce do anything until
the Study is completed. He stated the Taskforce needs to continue its process due to the
amount of work that will pile up with other studies they could be concentrating on.
6.3. Resolution Authorizing Eminent Domain and Acquisition of Real Property and Adopting-
Approved Appraisals of Value for 193=~ Avenue Project
Mr. Maurer presented his staff report.
MOVED BY COUNCILMEMBER MOTIN AND SECONDED BY
COUNCILMEMBER GUMPHREY TO ADOPT RESOLUTION 07-72
AUTHORIZING EMINENT DOMAIN AND ACQUISITION OF REAL
PROPERTY IN ACCORDANCE WITH MINNESOTA STATUTES CHAPTER
117 FOR THE 193 AVENUE TRANSPORTATION CORRIDOR AND
ADOPTING APPROVED APPRAISALS OF VALUE. MOTION CARRIED 5-0.