3.5. SR 10-06-2008REQUEST FOR ACTION
To Item Number
Ci Council 3.5.
Agenda Section Meeting Date Prepared by
Consent October 6, 2008 Phil Hals, Street Su erintendent
Item Description Reviewed by
Authorization to Complete Concrete Floor in Public Works Ter Maurer, Public Works Director
Storage Building Reviewed by
Tim Simon, Finance Director
Action Requested
Staff requests approval from City Council to authorize the expenditure of $19,750 for the
installation of a concrete floor in the public works storage building by Majestic Masonry of Elk
River.
Background/Discussion
The Public Works storage building now has a section of floor approximately 45 feet by 100 feet
that is class 5 gravel. Staff solicited ideas and quotes from four different masonry contractors.
Please see attached list.
Financial Impact
The 2008 budget contains $20,000 that was designated for the completion of the floor in this
building.
Attachments
^ Summary of quotes for concrete floor in Public Works building attached.
Action Motion by Second by Vote
Follow Up
Summary of Quotes for Concrete Work in Storage Building
Majestic Masonry
6" Concrete Slab (approx 4,500 SF @ $3.50/SF) $15,750.00
Evaporation Drain $ 4,000.00
City to do the base grading $19,750.00
Bk Masonry
6" Concrete Slab (approx 7,920 SF) Labor $ 9,700.00
City supplied concrete $15,968.61
City to do base grading $25,668.61
TLS Custom Concrete
6" Concrete Slab (approx 7,920 SF) Labor $ 9,900.00
City supplied concrete $15,968.61
$25,868.61
Greenway Concrete
6" Concrete Slab (approx 7,920 SF) Labor $12,000.00
City supplied concrete $15,968.61
$27,968.61