5.6. SR 05-20-1996'ty of
iver
**ITEM 5.6.**
TO:
FROM:
DATE:
SUBJECT:
MEMORANDUM
Mayor & City Council
Lori Johnson, Asst. City Administrator
May 20, 1996
Pay Estimate
Pay Estimate No. 2 - Wastewater Treatment Plant Expansion
Attached is a copy of Pay Estimate #2 to Gridor Construction, Inc., in the
amount of $391,816.00 for work completed on the Wastewater Treatment
Plant expansion project. Most of the recent pay estimate is for foundations
for the trickling filter, main building addition and the final clarifier.
Action Requested
The city engineer has reviewed the pay estimate, inspected the work
completed, and recommends payment to Gridor Construction, Inc., in the
amount of $391,816.00.
s:\council\payest.doc
13065 Orono Parkway · P.O. Box 490 · Elk River, MN 55330 · (612) 441-7420 · Fax: (612) 441-7425
GRIDOR CONSTR., INC.
1888 BERKSHIRE LANE
P.O. BOX 41246
PLYMOUTH, MN 55441
Owner CITY OF ELK RIVER. MN Date
For Period 4/1/96TO5/6/96 Request No. ·
612-559-3734
Engineer MSA CONSULTING ENGINEERS
SUMMARY:
1
2
3
4
5
6
7
8
9
10
11
ORIGINAL CON'IIL~CT AMOUNT
CHANGE ORDER - ADDITION
CHANGE ORDER - DEDUCTION
REVISED CONTRACT AMOUNT
V.a~LUE COMPLETED TO DATE
MATERIAL STORED
AMOLrNT EARNED TO DATE
LESS RETAINAGE - 5%
SUB-TOTAL
LESS AMOUNT PREVIOUSLY PAID
.aMOUNT DUE THIS REQUEST
REQUEST FOR PAYMENT
WWTF UPGRADE
ELK RIVER, MN
$ 3,292,900
$ 3,292.900
$ 418,450
$ 126.809
$ 545.259
$ 0
$ 545,259
$ 153,443
$ 391,816
Recommended for Approval by:
MSA CONSULTING ENGINEERS
HANG ~
Approved by Contractor:
GRIDOR CONSTR., INC.
PROJ. MGR
Specified Contract Completion Date:
5/7/96
Approved by Owner:
CITY OF ELK RIVER, MN
Date
PAYXLS 5/7/96 EQUAL OPPORTUNITY EMPLOYER