3.5. SR 03-24-2003City ~
TO:
FROM:
DATE:
SUBJECT:
*Item 3.5.*
MEMORANDUM
Mayor and City Council
Lori Johnson, Finance Director
March 24, 2003
Consider Public Safety Facility and City Hall/Utilities Change
Orders
The fo[lowing change orders have been requested on the public safety and city hah building
projects.
Contractor
Bid Package Change Order Change Order
Number Number Amount
PUBLIC SAFETY BUILDING
Dryden Excavating
(Elevator pit elevation & drainage changes)
Bartley Sales
(Increase in height of lockers from 76" to 84")
George Cook Construction
(Plywood and temporary enclosures)
Daka Metal Fabricators
(Extra materials - angles & bolts)
George Cook Construction
(electrical deduct & temporary enclosures)
Kremer & Davis, Inc.
(Water proofing to exterior planter)
Daka Metal Fabricators
(Grating & related accessories deleted)
Daka Metal Fabricators
(Added brick angles & anchors)
Twin City Tile & Marble
(Proposal Request #9 item 7.6)
Northern Air Corporation
(fittings on water and air piping)
1 1 $ 5,400.00
29 1 1,875.00
14 2 4,498.00
11 2 115.00
14 4 2,962.00
15 2 1,350.0O
11 3 (3,380.00)
11 4 920.00
22 1 (3,600.00)
40 2 (600.00)
Weatherproof Systems
(Flashing)
Western Steel Erection, Inc.
(Brick support angles)
Total
Previously Approved
Total Change Orders to Date
17 1
12 2
300.00
942.00
10,782.00
31,787.00
42,569.00
CITY HALL PUBLIC UTILITIES
Reliance Electric
(Move transformer)
Total
Previously Approved
Total Change Orders to Date
38 1
1,950.00
1,950.00
0
1,950.00
Action Requested
The City Council is asked to approve the change orders as noted above.