5.4. SR 06-17-1996rqty of iver **Item 5.4 a-b*~ MEMORANDUM TO: FROM: DATE: SUBJECT: Mayor & City Council Lori Johnson, Asst. City Administrator June 17, 1996 Pay Estimates Pay Estimate No. 3 - Wastewater Treatment Plant Expansion Attached is a copy of Pay Estimate #2 to Gridor Construction, Inc., in the amount of $281,662.00 for work completed on the Wastewater Treatment Plant expansion project. To date construction completed includes the structural works for the primary clarifier No. 2, the final clarifier No. 1, and the foundation of the final clarifier No. 2. Final Pay Estimate County Road 12/13 Storm Sewer Improvement Also attached is a copy of the Final Pay Estimate to Dave Perkins Contracting, Inc. for completion of the above referenced project. The final pay estimate is in the amount of $5,307.94. The final construction cost of the project is $347,842.31 which is approximately one percent over the original contract amount. Action Requested The city engineer has reviewed the pay estimates, inspected the work completed, and recommends payment as noted above. s:Xcou ncilXp aye st. doc 13065 Orono Parkway · P.O. Box 490 · Elk River, MN 55330 · (612) 441-7420 · Fax: (612) 441-7425 GRIDOR CONSTR., INC. 1886 BERKSHIRE LANE P.O. BOX 41246 PLYMOUTH, MN 55441 Owner CI'[~ OF ELK ~VER~ MN Date For Period 5/6/96TO6/3/96 Request No. 612-559-3734 Engineer MSA CONSULTING ENGINEERS SUMMARY: 1 ORIGINAL CONTRACT AMOUNT 2 CHANGE ORDER - ADDITION 3 CHANGE ORDER - DEDUCTION 4 REVISED CONTRACT AMOUNT 5 VALUE COMPLETED TO DATE 6 MATERIAL STORED 7 AMOUNT EARNED TO DATE 8 LESS RETAINAGE - 5% 9 SUB-TOTAL 10 LESS AMOUNT PREVIOUSLY PAID ! 1 AMOUNT DUE THIS REQUEST Recommended for Approval by: /BILL-CHANG ~ Approved by Contractor: GRIDOR CONSTR., INC. PROS. MGR pecified Contract Completion Date: REQUEST FOR PAYMENT WWTF UPGRADE ELK RIVER, MN $ $ $ 3,292,900 $ 3,292,900 $ 612,950 $ 213,971 $ 826,921 $ 0 $ 826,921 $ 545,259 $ 281,662 6/3/96 Approved by Owner: CITY OF ELK RIVER, MN Date PAYXLS 6/3/96 EQUAL OPPORTUNITY EMPLOYER FROM: TO:. FIN~J. PAYMI2~ ~STLV~'I'g NO. 5 JANUARY 16. 1~ MAY 17, 1996 CONTRACTOR: ADDRF.,~,S: OWNI~: COMPLETION DATE ORIGi~A.L,: DAVE PERKINS CONTRACTING, INC. PO BOX 2T/, 14230 BASALT ST., RAMSEY, MN $~03 CrTY OF ELK RIVER 5TH ST./CSAH 13/CSAH 12 STREET & STORM SEWER IMPROVE. (2.30-21 !-30) 60 DAYS AMOUNT OF CONTRACT: ORIGINAL,: $ 344.480.00 DESCRI]'I'ION SCHEDULE 1.0 - SITE WORK - TOTAL SCHEDULE 2.0 STREET CONSTRUCTION-TOTAL SCHEDULE 3.0 STORM DRAINAGE-TOTAL SCHEDULE 4.0 ADDITIONAL WORK-TOTAL SCHEDULE 5.0 CHANGE ORDER NO. I-TOTAL TOTAL THIS PERIOD TOTAL TO DATE 0.00 34,448.00 50.00 39,820.18 180.00 250.686.00 1.618.00 17.998.13 0.00 4.890.00 .......................................... ';": ...... MATERIAL ON SITE $0 00 :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::i>:.S.:.:.::~:~:~.~:~:~:i:~:.:~:!:~>::~:~$!::~:~::::$:::::.~<::&¥~::::i:~:!:~.j~:~:~:.)~!:~.::~:i:~:i:: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: MATERIAL DEDUCT. Ii .001 ~000 :=~:~...-'??:::'.~!:!:i:i:!:.:::'..~: ~:::~::~::~::!:.-':~:!:::.-:.-:'::.-':i.-:':!::-.~....':..': ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: .P.~OUS PAYMENTS .... ~.~-~-~ ........ ~ · -. -~ · .'-'+~ ~-'.'~.'.'-...~.~-..~r-~....~...~.~,~- .. ~.~;...:<.=.:.:.~:~.:.:.~=.:.:~:.:.:.~.:.~.~.~.=.~.~.=~:.:~:.:.~.~.~......<.~.:....:~:.~.~=::¥~::~::::~:~:;:~:~:~¥:~ :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ~Y~.~<~`~:<~:~:~x~:~:~:~:~:~:~:~:~:-:~:~:~:~:~:~:~:~:~:~:~-~<~:~:~:~:~