Background/Discussion
The City has been approached by a potential buyer of the 4.74 acres. Their desire is to
construct 22 townhome units and a community center for recovering adults and families.
This use would require a residential zoning (likely R-3). The property is currently zoned C-2
Office District. Information regarding a similar project is attached for information.
Because this project represents a departure from limited commercial zoning, a concept
review is suggested.
Overview/ Analysis
The City Council is asked to identify issues/ concerns with the proposed location and layout
of the project, known as Shepherds Ridge.
It is important to note that this is not a formal request to rezone the property, and the City
Council is not obligated to approve a formal application once received. The concept review
is beneficial for the City Council (to be aware of major developments being contemplated
and provide initial feedback), staff (to understand Council concerns and desires with the
project), and the applicant (to get an understanding of the major issues observed by staff and
the City Council). Following input regarding the concept plans, staff will work with the
applicant towards development of a proposal that meets Council's stated and published
goals.
The Proposal
The proposal includes plans for 22 townhome units in four buildings, a large community
center building, and a play ground. These improvements will be located in the southern 2/3
of the L shaped lot at the SW corner of Jackson and School Street. The northern 1 /3 is not
proposed to be developed at this time.
Access
Access to the site will come from Jackson Street. The Council may recall that upon the
development of the larger parcel south of this site, 8`'' Street will be extended, and access for
these two parcels will come from this location. This reduces the number of driveways on
Jackson, which is expected to become a major street in the years to come. This also
provides maximum. separation between the School/ Jackson intersection and the driveway.
It is expected that an emergency access will come off of School Street, although this will be
refined as planning continues.
Parkuig
The layout shows parking for 76 surface parking stalls, well over the required 55 (2.5 per
dwelling unit). However, the 76 spaces does not include any garage parking, which 22 spaces
axe required per ordinance.
Land Use
The current zoning is C-2. There is limited office zoning in the City and there may be long
term advantages to maintaining a minimum level of available developable commercial
properties. Additionally, there may be a concern with adding more housing in the area
immediately around the park. Development around the park includes many residential
dwelling units, including the approved but not developed Jackson Street Townhomes (78
units). Dwelling units immediately adjacent to the park may be at the saturation point.
The project would be served by City water and Sewer. Staff continues to review the
proposal with regard to storm water management.
No design has been offered of the buildings themselves, although it appears that the building
will be two level.
Staff continues to work with the applicant on addressing these and other concerns.
Preliminary comments are attached for information.
Staff is looking for direction on proposed housing development for property at the SW
corner of School and Jackson, currently zoned C-2. Additionally, the Council is asked to
provide direction as to their desire to amend the zoning for this given property.
Attachments
• Layout
• Staff Comments, dated August 20, 2009
Belle Haven townhomes information
August 20, 2009
Ms. Terri Cermak
Re: Shephards Ridge
.Terri,
Thank you for allowing me to provide some preliminary comments regarding the proposed
Shephards ridge. These comments also include comments received from the City Engineer.
Timetable
1) From a timing perspective, you should allot 2-3 months from the date of a final
application to complete the necessary regulatory approvals, including, if necessary,
Conditional Use Permit, rezoning, preliminary and final plat and site plan.
I understand you are envisioning a City Council workshop review. The Council meets in
workshop the second Monday of each month. The next one is September 14`''. Do you
anticipate wanting to meet with them then? If so, I'll need a copy of the site plan (with
revisions, if possible), proposed elevations, and a written narrative of your operation for
inclusion in their packets. I will need this by September 8r''.
Fees and Apphr cation
2) To complete the use as proposed, the property will need to be rezoned from C-2 to a
residential use, likely R-3, R-4, or PUD. A PUD will require a Conditional use Permit. I am
attaching the necessary applications.
Engineering
3) Some additional right of way will be necessary for a right turn lane off of east bound
School onto southbound Jackson.
4) The site plan should include storm water ponding.
5) There will be trunk sewer and water assessments, and SAC and WAC fees.
6) Water/ sewer and hydrant layouts will be discussed later.
Access/ Parking
7) Access to the property should ultimately be at the south end of the property to work with
the planned access adjacent to 8~' street
8) The access off of Jackson will go away when development to the south occurs, to be
replaced with a shared access adjacent to 8~' street extended.
9) An easement will need to be provided through the townhome property to the lot in the
corner, if these are separated.
10) The larger community building in the SE corner of the site will need to be relocated.
11) There appears to be access out of the site to the west. Easements will be required.
12) The fire department has not commented. I will forward these on once received.
13) The Zoning Ordinance requires 2.5 spaces per unit, one of which must be covered. The
Council may reduce the number constructed, if there is sufficient area for future
construction of the spaces.
Landscaping/Vegetation
14) Conceptually, the Landscape plan looks consistent with the intent of the ordinance.
Parks
15) Park dedication will be required. This may be cash or land, based on the Park and
Recreation recommendation to the City Council. If it's cash, the amount will likely be
$3,639 per dwelling unit.
Please do not hesitate to contact me should you have any questions, I can be reached at
(763) 635-1034.
Sincerely,
~f _.__.
,~
=f
~~~
~-
Jeremy Barnhart, AICP
Planning Manager
CSH
Key Features and Innovations:
• Belle Haven provides tenants with
a safe, sober and affordable place
to call home while allowing them
the opportunity for a fresh start.
• Belle Haven programs also focus
on children and assist them in
building skills needed to be
successful in school and in the
broader community. Services for
children include a weekly "Kid's
Club" for school-aged children, a
preschool readiness class, job
skills, individual tutoring,
mentoring, planned activities and
volunteer opportunities.
• Belle Haven tenants are required
to remain sober, do at least 25
hours of productivity a week and
be lease abiding. The average
length of stay is 22-36 months.
Financing
:Capital
LIHTC Tax Credit Proceeds
Federal Home Loan Bank
Rum River Health Services Capitol Campaign
HUD SHP
MHFA Housing Trust Fund (HTC)
Greater MN Housing Fund (GMHF)
General Partner Capital Contribution
Greater MN Housing Fund (GMHF)-Bridge
Misc Funds
:Total Sources of Funds
j Operating
Group Residential Housing (GRH)
Housing Trust Fund (HTF)
Services
$2,256,451
$ 80,000
$ 365,000
$ 400,000
$ 498,818
$ 160,000
$ 29,224
$ 156,510
$ 4,600
$3,950,603
Determined by Counties
On an as Needed Basis
MN DHS $ 152,000
HUD SHP $ 50,000
About Rum River Health Services, Inc. (RRHS)
RRHS is a 501 (c) (3) non-profit organization, incorporated in 1987, located in Mille Lacs County, Princeton,
Minnesota. The mission of RRHS is "To identify and respond to community health needs as an advocate, as
a catalyst for community collaboration, and provider of needed services." The agency conducts periodic
health needs assessments, advocates for needed programs, and directly provides programs when appropriate. The
agency secures funding and administers programs in accordance with its articles of incorporation and by-laws at
the discretion of its governing board.
Current programs under management include the Rum Rivers Women's Health Project, a subsidized family
planning program; Rum River Recovery Alliance, a case management program for substance abusing pregnant or
parenting women; Spirit River Recovery Services, a chemical dependency outpatient treatment and dual diagnosis
treatment program. In 2007 RRHS opened Belle Haven Townhomes, a permanent supportive housing project
which provides sober housing for families affected by homelessness and chemical dependency. The newest
program is Family House, a residential facility where mothers in treatment for chemical dependency can live with
their children.
RRHS maintains a focus on quality of life issues in its area. When identified needs can be met by other agencies or
organizations, RRHS advocates for transition and change that will improve availability, access and affordability for
the population groups served. It recognizes the evolutionary= changes characteristic of the health care industry, and
is poised to grow and serve changing community needs.
About CSH
The Corporation for Supportive Housing (CSH) is a national non-profit organization and community development
financial institution that helps communities create permanent housing with services to prevent and end
homelessness. Founded in 1991, CSH advances its mission by providing advocacy, expertise, leadership, and
financial resources to make it easier to create and operate supportive housing. CSH seeks to help create an
expanded supply of supportive housing for people, including single adults, families with children, and young adults,
who have extremely low-incomes, who have disabling conditions, and/or face other significant challenges that
place them at on-going risk of homelessness. For more information about CSH, please visit ~7ww_ csh.org.
Corporation for Supportive Housing
2801 21S` Avenue S., Suite 230
Minneapolis, MN 55407
T: 612.721.3700
F: 612.721.9903
E: mn@csh.org
www.csh.org
N
n
y
.i
,f
JAc~sav.~vE.